Local Guide · AC and heating

Mechanic's Liens From AC Work: Texas and Florida Homeowner Protections

An unpaid AC contractor, subcontractor or supplier can sometimes put a lien on your home. Here is when that is legal in Texas and Florida, the deadlines, the paperwork that protects you, and how to remove an improper lien.

Yes, an AC contractor can put a lien on your house in Texas or Florida if it was not paid and it follows strict rules. In Texas, a lien on a homestead needs a written contract signed before work began (by both spouses if married) and filed with the county clerk. In Florida, most jobs of $2,500 or less are exempt, and liens must be recorded within 90 days of the last work. Protect yourself with written contracts, lien releases and a final payment affidavit before you pay in full.

Key facts

  • A Texas mechanic's lien on a homestead requires a written contract signed before work begins, signed by both spouses if the owner is married, and filed with the county clerk (Prop. Code §53.254).
  • Texas owners must reserve 10% of the contract price during the work and for 30 days after completion (Prop. Code §53.101).
  • For residential projects, a Texas original contractor must file its lien affidavit by the 15th day of the third month after the month its work was completed, terminated or abandoned (§53.052, as amended by HB 2237, effective Jan. 1, 2022).
  • Texas contractors must give a final bills-paid affidavit when final payment is tendered on a residential construction contract (§53.259).
  • Florida improvements with a direct contract price of $2,500 or less are exempt from most of the Construction Lien Law (Fla. Stat. §713.02(5)).
  • Florida subcontractors and suppliers must serve a Notice to Owner within 45 days of starting work; failure is a complete defense to their lien (§713.06(2)(a)).
  • A Florida claim of lien must be recorded within 90 days after the lienor's final furnishing of labor or materials (§713.08(5)).
  • The permit-office notice of commencement requirements in §713.135(1) do not apply to a direct contract to repair or replace an existing heating or AC system for less than $15,000.
  • A Florida owner can record a Notice of Contest of Lien, giving the lienor 60 days to sue or lose the lien (§713.22(2)).
  • Willfully filing a fraudulent lien is a third-degree felony in Florida (§713.31).

Can an HVAC company put a lien on my house?

Yes, in some cases. A mechanic's lien (called a construction lien in Florida) is a legal claim against real property by someone who improved it and was not paid. It clouds your title, which means you may not be able to sell cleanly until it is resolved. If the lien holder wins a lawsuit to foreclose it, a court can order the property sold to pay the debt.

A new central AC system, ductwork, an air handler or a heat pump is an improvement to real property, so lien laws apply. A simple service call with no permanent improvement is less likely to support a lien, but do not assume. Both states have detailed rules on who can claim a lien, how fast they must act, and what notices they must send. A lien that misses a step is often invalid.

This page explains the general rules for Texas Property Code Chapter 53 and Florida Statutes Chapter 713. It is general information, not legal advice. If a lien is filed on your home, talk to a real estate or construction attorney promptly, because some response windows are short.

Who can file a lien: contractor, subcontractor, supplier

Most AC jobs have more than one party. The company you hire is the original contractor (Texas) or the contractor in privity with you (Florida). It may buy equipment from a supplier (a distributor) and may hire a subcontractor for ductwork, electrical work or a crane lift.

The risk for homeowners: you pay your contractor in full, but your contractor does not pay its supplier. In both states, that supplier may be able to claim a lien on your home if it gives you the required notices on time. You could end up paying twice for the same AC system. The notice systems below exist so you learn about unpaid subs and suppliers early enough to protect yourself.

PartyTexas notice to ownerFlorida notice to owner
Your contractorNo pre-lien notice needed; file affidavit by deadlineNo Notice to Owner needed (in privity with you)
Subcontractor or supplierNotice of claim by the 15th day of the second month after labor or materials were provided (residential)Notice to Owner within 45 days of starting to furnish
Laborer (individual worker)Follows subcontractor rulesGenerally exempt from the Notice to Owner requirement

Texas: the homestead rules that protect most homeowners

Texas gives homesteads special protection. If the AC work is on your homestead (your primary residence), a lien is only valid if all of these are true (Prop. Code §53.254):

  • There is a written contract setting out the terms.
  • It was signed before any material was furnished or labor performed.
  • If you are married, both spouses signed it.
  • It was filed with the county clerk where the home is located.

A contract made by the original contractor also benefits its subcontractors and suppliers. A lien affidavit on a homestead must carry, at the top in at least 10-point bold, the notice: "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN."

Most quick AC replacements in Houston, Dallas, San Antonio or Austin are sold on a one-page proposal signed the day of sale, often by one spouse, and rarely recorded. That paperwork usually does not meet the homestead requirements. If the contract was not signed before work, not signed by both spouses, or not filed, the lien on your homestead may be invalid, and §53.160 lets you ask a court to remove it on that basis. Rental properties and commercial buildings are not homesteads and do not get this protection.

The 2022 overhaul (HB 2237)

Texas rewrote much of Chapter 53 through HB 2237 (2021), effective January 1, 2022. It simplified notice deadlines and forms. Contracts signed before 2022 may fall under the old rules. When you read older articles about Texas liens, check whether they predate 2022.

How long does an AC contractor have to file a lien in Texas?

Under the current Chapter 53, for residential construction projects:

  • Original contractor (your AC company): file the lien affidavit with the county clerk by the 15th day of the third month after the month its work was completed, terminated or abandoned (§53.052(a)(2)). Example: if the install was finished on June 10, the deadline is September 15.
  • Subcontractor or supplier: send you a notice of claim by the 15th day of the second month after the month it provided the labor or materials (§53.056(a-1)(2)), and file its own affidavit by the 15th day of the third month after the month it last provided labor or materials (§53.052(c)).
  • Anyone who files must send you a copy of the affidavit within 5 days after filing (§53.055).
  • A suit to foreclose generally must be filed by the first anniversary of the last day the claimant could have filed the affidavit (§53.158). If that deadline passes without a suit, the lien can be discharged (§53.157).

Non-residential projects (an RTU on a strip center, for example) have a longer filing deadline: the 15th day of the fourth month.

Texas: the 10% retainage rule and why it matters

Texas owners must reserve (hold back) 10% of the contract price, or 10% of the value of the work done, during the work and for 30 days after the work is completed (§53.101). The reserved money secures claims by subcontractors and suppliers who give proper notice.

If you do not hold back the 10%, claimants who comply with the notice rules can have a lien at least up to the amount you should have reserved (§53.105). And if you receive a subcontractor's notice of claim, you are allowed to withhold enough from your contractor to cover it (Subchapter D). If you keep paying the contractor after that notice, you may be liable for those amounts too (§53.084).

For a $12,000 AC replacement, 10% is $1,200. In practice, many homeowners pay in full on install day. That is common, but it shifts the risk of an unpaid supplier to you. A middle ground: ask for the final bills-paid affidavit and lien releases at the time of final payment, as described below.

Texas: paperwork your contractor must give you

  • Disclosure statement (before signing). On a residential construction contract, the original contractor must give you a "Know Your Rights and Responsibilities" disclosure before you sign (§53.255). It warns, among other things, to get the description of work, timeline, cost and payment method in writing.
  • List of subcontractors and suppliers. Before work starts, the contractor must give you a written list of the subcontractors and suppliers it intends to use, with names, addresses and phone numbers, and update it within 15 days of changes, unless you sign a waiver (§53.256).
  • Final bills-paid affidavit. As a condition of final payment on a residential construction contract, the contractor must give you an affidavit stating it has paid everyone in full for labor and materials, or listing who is still owed and how much (§53.259). Making a false statement in it is a misdemeanor with a fine up to $4,000, up to a year in jail, or both.
  • Lien releases on request. Once a debt is paid in collected funds, the person who furnished the labor or materials must give a recordable release within 10 days of a written request (§53.152).

Whether a small AC replacement is treated as a "residential construction contract" for each of these rules can depend on the facts. Ask for the documents anyway. A professional company should have them ready.

Texas lien waivers and releases: the four statutory forms

Texas only enforces a waiver or release of lien rights in limited cases. A waiver is generally unenforceable unless it substantially complies with a statutory form, or the claimant has actually been paid in full in good funds (§53.282). A narrow exception allows a lien waiver written into an original contract or subcontract for a single-family house, townhouse or duplex, if made before labor or materials are provided, but it does not apply to material-only suppliers.

Section 53.284 sets out four forms:

FormWhen it is usedEffective when
Conditional Waiver and Release on Progress PaymentBefore you pay a progress paymentOnly once your payment actually clears
Unconditional Waiver and Release on Progress PaymentAfter the progress payment has clearedOn signing
Conditional Waiver and Release on Final PaymentBefore you pay the final amountOnly once your final payment clears
Unconditional Waiver and Release on Final PaymentAfter the final payment has clearedOn signing

Practical approach for an AC job: when you hand over the final check, ask for a conditional final waiver from your contractor and from any supplier who sent you a notice of claim. After your payment clears, ask for the unconditional versions. Keep them with your home records.

Florida: when the Construction Lien Law applies to AC work

Florida's Construction Lien Law is Part I of Chapter 713. The first question is the contract price.

  • $2,500 or less: exempt from most of the lien law, except §713.05 (§713.02(5)). Many AC repairs fall here.
  • Over $2,500: the lien law applies. A direct contract over $2,500 on a home of up to four units must include a 12-point bold, capitalized construction lien law warning that the owner signs (§713.015). The contract must also include a written notice of your rights under the Homeowners' Construction Recovery Fund (§489.1425).

If your AC replacement contract over $2,500 lacks the lien warning, ask why. It is a sign the contractor may be cutting other corners.

What is a Florida Notice of Commencement, and do I need one for an AC replacement?

A notice of commencement (NOC) is a form the owner records with the county clerk before starting an improvement. It names the owner, contractor, property and others (such as a lender or a person designated to receive copies of notices). It must be posted on the job site before the first inspection, and it expires one year after recording unless another date is stated (§713.13). The NOC sets the timeline that lien claimants rely on.

The AC-specific rule: the permit office's NOC requirements in §713.135(1) do not apply to a direct contract to repair or replace an existing heating or air-conditioning system for less than $15,000. In practice, most building departments will not ask you for a recorded NOC before issuing a permit for an AC change-out under $15,000. Jacksonville, for example, says a recorded NOC is required for improvements over $5,000, or over $15,000 for mechanical work.

Above $15,000, which is increasingly common for a variable-speed heat pump with new ductwork, expect to record an NOC. Your contractor usually prepares it; you sign it in front of a notary and record it. Note the warning printed on the form: payments made after an NOC expires are considered improper and can result in paying twice. If your job runs long, ask about extending the NOC.

Even without an NOC, the lien law still applies to jobs over $2,500. The $15,000 rule changes the permit paperwork, not the lien rights of an unpaid contractor or supplier.

What is a Notice to Owner in Florida?

A Notice to Owner (NTO) is a letter from a subcontractor or supplier telling you it is working on or supplying your job and could claim a lien if not paid. It is not a lien and it is not a sign of trouble by itself. Distributors send NTOs routinely to protect their rights.

Rules: anyone not in privity with you (except laborers) must serve the NTO before starting, or within 45 days after starting, to furnish labor, services or materials, and in any event before you make final payment after receiving the contractor's affidavit. Failure to serve it, or to serve it on time, is a complete defense to that party's lien (§713.06(2)(a)).

What to do when you get one: keep it. Before final payment, make sure each party that sent you an NTO has been paid, by asking for a release of lien from each one or paying with a joint check made out to the contractor and that supplier. Florida's NTO form itself warns that you could pay twice if your contractor does not pay those who sent notices.

What is a final payment affidavit?

In Florida, when final payment comes due, your contractor must give you a Contractor's Final Payment Affidavit stating that all lienors under its contract who served a Notice to Owner have been paid in full, or listing anyone who has not and how much is owed (§713.06(3)(d)). It must be sworn before a notary.

This document is powerful for homeowners. A contractor has no lien or right of action against you while in default for not giving the affidavit, and it must deliver the affidavit at least 5 days before suing to enforce its lien. Ask for it before you make the last payment. If it lists unpaid suppliers, pay them directly or by joint check and get releases.

Texas has its own version: the final bills-paid affidavit under §53.259, described above.

How long does a Florida contractor have to file a lien?

  • Record the claim of lien within 90 days after the lienor's final furnishing of labor, services or materials (§713.08(5)).
  • Lien lifespan: a lien lapses one year after it is recorded unless the lienor files a lawsuit to enforce it within that year (§713.22(1)).
  • Shorten it: you or your attorney can record a Notice of Contest of Lien. The lienor then has 60 days from service of the notice to sue, or the lien is extinguished automatically (§713.22(2)).

How do I remove an improper lien?

In Texas

  • Ask for a release. If the debt was paid, the claimant must furnish a recordable release within 10 days of a written request (§53.152).
  • Summary motion to remove. In a suit to foreclose or to declare a lien invalid, you can file a verified motion to remove it on limited grounds, such as late notices, a defective affidavit, failure to send you the affidavit copy, or, for a homestead, no contract signed and filed as §53.254 requires (§53.160).
  • Bond around it. You can file a bond to release the property from the lien (Subchapter H).
  • Wait out the deadline. If no foreclosure suit is filed on time, the lien can be discharged (§53.157, §53.158).
  • Fees. In a proceeding to declare a lien invalid, the court awards costs and reasonable attorney's fees as equitable and just, although on a residential contract the court is not required to order the homeowner to pay fees (§53.156).

In Florida

  • Get a release or satisfaction recorded by the lienor (§713.21).
  • Notice of Contest of Lien to force a lawsuit within 60 days (§713.22(2)).
  • Order to show cause. After you file a complaint, the clerk issues a summons requiring the lienor to show cause within 20 days why the lien should not be enforced. If the lienor fails to show cause or fails to sue before the return date, the court orders the lien canceled (§713.21(4)).
  • Transfer to a bond or cash deposit so the title is cleared while the dispute continues.
  • Fraudulent lien. A lien is fraudulent if the lienor willfully exaggerated the amount or included work not performed or materials not supplied. Fraud is a complete defense, the owner may sue for damages including attorney's fees and capped punitive damages, and willfully filing a fraudulent lien is a third-degree felony (§713.31).

For any of these, an attorney can tell you which tool fits and how to avoid paying the other side's fees.

Should I pay my HVAC contractor upfront?

A deposit is normal for AC replacements, mainly so the contractor can order equipment. Paying the full price before install is not normal, and it raises your risk.

Payment stageWhat is commonWhat protects you
DepositA modest share for equipment; Florida treats over 10% as triggering permit and start deadlinesWritten contract, license check, card payment
Install dayBalance after the system runsStartup readings, permit number, walk-through
FinalAfter the final inspection passesFinal bills-paid affidavit (TX) or final payment affidavit (FL); lien releases

Florida law sets a clear marker: a contractor who takes more than 10% of the contract price as a down payment on residential work must apply for permits within 30 days and begin work within 90 days after permits issue, unless there is just cause or a written agreement (§489.126(2)(a)). Texas does not set a deposit cap for AC work, but the 10% retainage rule in §53.101 assumes you will hold back money until 30 days after completion.

Pay with a credit card where possible. It adds federal dispute rights you lose with cash or app transfers. See how to dispute an HVAC bill.

A homeowner's lien-proof payment routine

  1. Verify the license (TDLR in Texas, DBPR in Florida) and the company's legal name.
  2. Sign a written contract that lists equipment model numbers, price, payment schedule, permit and warranty registration.
  3. Texas homestead: understand that a valid homestead lien requires a contract signed before work by both spouses and filed with the county clerk. Read anything you sign carefully.
  4. Texas: ask for the subcontractor and supplier list. Florida: keep every Notice to Owner you receive.
  5. Florida over $15,000: record the notice of commencement if required, and post it on site.
  6. Pay the deposit by card. Keep the receipt.
  7. Before final payment, get the final bills-paid affidavit (Texas) or final payment affidavit (Florida).
  8. Get conditional lien waivers from your contractor and from any supplier who gave you notice. Swap for unconditional waivers after your payment clears.
  9. Confirm the permit was finaled on your city's portal.
  10. Keep all of it with your closing documents. You will need it if you sell. See buying or selling a home with AC issues.

For HVAC contractors: protecting your own lien rights

Contractors read this page too. The same rules cut the other way. In Texas, residential homestead work without a written contract signed before work by both spouses and filed with the county clerk leaves you with weak lien rights. Give the §53.255 disclosure, the §53.256 subcontractor list (or get a signed waiver), and track the 15th-day-of-the-month deadlines.

In Florida, include the §713.015 lien warning and the §489.1425 recovery fund notice in residential contracts over $2,500, prepare the final payment affidavit, and calendar the 90-day recording deadline. Remember that an unlicensed contractor cannot enforce its contract (§489.128), and that the CILB can fine a licensee up to $10,000 per violation (§489.129).

How to choose a provider

  • Check whether your job is over $2,500 (Florida lien law threshold) and over $15,000 (Florida AC notice of commencement threshold).
  • Texas homestead: know that a valid lien requires a written contract signed before work, by both spouses if married, and filed with the county clerk.
  • Ask for the Texas subcontractor and supplier list before work starts.
  • Keep every Notice to Owner (Florida) or notice of claim (Texas) you receive.
  • Hold back money until the system passes final inspection, or at minimum get affidavits and waivers at final payment.
  • Get the final bills-paid affidavit (Texas) or contractor's final payment affidavit (Florida).
  • Get conditional lien waivers at payment and unconditional waivers after payment clears.
  • Pay suppliers who sent notices by joint check if the contractor's affidavit lists them as unpaid.
  • If a lien is filed, calendar the deadlines and call a real estate or construction attorney.
  • In Florida, consider a Notice of Contest of Lien to force a lawsuit within 60 days.
  • Store all lien documents with your home records for a future sale.

Related ac and heating guides

AC and heating by state and city

Questions people ask

Can a supplier lien my house if my contractor didn't pay them?

Yes, in both states, if the supplier follows the notice rules. In Texas, a supplier on a residential project must send you a notice of claim by the 15th day of the second month after it furnished materials, and your 10% retainage helps cover these claims. In Florida, the supplier must serve a Notice to Owner within 45 days of starting to furnish, or it loses its lien. Paying the supplier directly, or by joint check, and getting a release closes this gap.

What is a lien release and should I get one?

A lien release, also called a lien waiver, is a signed document in which a contractor, subcontractor or supplier gives up its lien rights to the extent it has been paid. Yes, you should get one at final payment from your contractor and from every party that gave you notice. In Texas, use the statutory forms in Property Code §53.284; a conditional release becomes effective only once your payment clears. In Florida, get a release from each party that served a Notice to Owner.

Does a small AC repair create lien rights?

In Florida, a direct contract of $2,500 or less is exempt from most of the lien law. In Texas, there is no similar dollar exemption, but a homestead lien still requires a written contract signed before work and filed with the county clerk, which small repairs rarely have. A service call with no permanent improvement is also harder to lien. That said, an unpaid company can still sue you for the debt even without lien rights.

Can a lien stop me from selling my house?

It can delay a sale. A title company will usually find a recorded lien and require it to be released, bonded off, or paid from your sale proceeds before closing. If the lien is invalid, you can use the removal tools described above, but that takes time. That is why keeping your lien releases and final affidavits from every AC job matters when you sell.

I paid my contractor in full. Am I safe?

Not automatically. If a subcontractor or supplier gave you proper notice and was not paid, it may still have lien rights. In Texas, your exposure is generally tied to the 10% you should have retained and to payments you made after receiving a notice of claim. In Florida, payments made without getting releases from parties who served a Notice to Owner can leave you exposed. If you paid in full, ask your contractor now for the final affidavit and releases.

What if the lien amount is inflated?

Dispute it in writing and talk to an attorney. In Florida, a lien that willfully exaggerates the amount or includes work not performed is fraudulent under §713.31, which makes it unenforceable and can expose the lienor to damages, attorney's fees and criminal charges. Minor errors and good-faith disputes over the amount are not fraud, though. In Texas, a lien that does not comply with Chapter 53 can be removed by summary motion on the grounds listed in §53.160.

Do Texas lien rules apply to my rental or commercial property?

Yes, but without the homestead protections. Rental homes, second homes and commercial buildings are not homesteads, so the special written-contract-and-filing rule in §53.254 does not apply. Non-residential projects have a later lien affidavit deadline, the 15th day of the fourth month after completion. Commercial owners replacing rooftop units should be especially careful with retainage and supplier releases. See our commercial RTU guide.

Where do I look up whether a lien was filed on my home?

Liens are recorded in the county's official records. In Texas, search the county clerk's records (for example, Harris, Dallas, Bexar or Travis County Clerk). In Florida, search the clerk of court's official records (for example, Miami-Dade, Hillsborough, Orange or Duval). Search by your name and your property's legal description. A title company can also run a search.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration