Local Guide · Electricians

Solar Panels and Your Home's Electrical System: Panel Upgrades, the 120% Rule, Interconnection and Net Metering in Texas and Florida

A neutral, electrician's-eye guide for solar shoppers and owners: whether your panel can take solar, the 120% busbar rule and line-side taps, rapid shutdown, inspections and permission to operate, Florida's net metering rule, Texas buyback plans and Austin Energy's value of solar, licensing, and what to do with an orphaned system.

Solar ties into your electrical system, so your panel, the code and your utility all have a say. Many homes can add solar without a panel upgrade if the inverter's output fits the NEC's 120% busbar rule; otherwise the options are a smaller main breaker, a supply-side connection, or a new panel. You need a local inspection and the utility's permission to operate first. Florida investor-owned utilities must offer net metering under Rule 25-6.065; in Texas competitive areas, what you earn for exports depends on your retail plan.

Key facts

  • IAEI: the 120% rule lets inverter output connect to a panel busbar when 125 percent of the inverter output current plus the busbar's overcurrent device rating does not exceed 120 percent of the busbar rating, with the solar breaker at the opposite end from the main.
  • NEC 705.12(A) permits a power source to connect on the supply side of the service disconnect, as allowed by 230.82(6), according to IAEI.
  • Rapid shutdown (NEC 690.12) was added in the 2014 NEC so first responders can quickly de-energize PV circuits on buildings, per IAEI.
  • Florida Rule 25-6.065 sets three tiers for investor-owned utility interconnection: Tier 1 up to 10 kW, Tier 2 over 10 kW to 100 kW, Tier 3 over 100 kW to 2 MW.
  • Under Rule 25-6.065, excess solar credits roll forward for up to 12 months, and at year end the utility pays for unused credits at an average annual rate based on its COG-1 as-available energy tariff.
  • Under Rule 25-6.065, Tier 1 customers pay no added fees and cannot be required to carry liability insurance; Tier 2 and Tier 3 insurance is capped at $1 million and $2 million.
  • Austin Energy credits 100 percent of solar production at its Value of Solar rate: 12.89 cents per kWh for systems under 1 MW-AC, effective October 1, 2026.
  • Oncor says customers may not operate a solar system until the interconnection agreement is complete and Oncor has issued a Permission to Operate letter.
  • Since September 1, 2025, Texas residential solar sale and lease contracts must name the licensed electrical contractor and give a five-business-day right to cancel; retailer registration with TDLR starts September 1, 2026.
  • LBNL's August 2026 survey found solar PV had the highest median residential permit fee of eight categories: $200 (IQR $80 to $315).

How solar connects to your house

A typical rooftop system has panels on the roof, one or more inverters that turn the panels' DC power into AC, a connection to your electrical panel or service, disconnects and labels, and a meter that can measure power flowing both ways. Once connected, your home uses solar power first; any extra flows out to the grid, and at night or on cloudy days you draw from the grid.

Three groups must sign off before you can turn it on:

  1. Your local building department inspects the installation to the electrical and building codes. In Texas that is the 2026 NEC since September 1, 2026. In Florida it is the 2020 NEC under the 8th Edition Florida Building Code, until the 9th Edition (2023 NEC) takes effect on December 31, 2026 per the state (January 1, 2027 per Tampa).
  2. Your utility reviews and approves the interconnection and installs or reprograms the meter.
  3. Your HOA, if any, within the limits state law sets.

The electrical questions, covered below, are where most delays and surprise costs come from.

Do I need a panel upgrade to install solar? The 120% rule explained

Not always. The question is whether your panel's busbar (the metal bars inside the panel that breakers attach to) can safely carry current from both the utility and the solar inverter.

The 120% rule

IAEI explains the rule this way: inverter output can connect to a panelboard busbar if the sum of 125 percent of the inverter's output circuit current and the rating of the overcurrent device protecting the busbar (usually the main breaker) does not exceed 120 percent of the busbar's rating, and the solar breaker sits at the opposite end of the busbar from the main breaker. The rule now lives in NEC 705.12(B).

Worked example

Panel120% of busbarMinus main breakerRoom for 125% of inverter currentMaximum inverter output current
200 A busbar, 200 A main240 A240 - 200 = 40 A40 A40 / 1.25 = 32 A
200 A busbar, 175 A main240 A240 - 175 = 65 A65 A65 / 1.25 = 52 A
100 A busbar, 100 A main120 A120 - 100 = 20 A20 A20 / 1.25 = 16 A

At 240 volts, 32 amps of inverter output is roughly a 7.7 kW AC system. A system larger than the rule allows needs another approach.

Options when the 120% rule does not fit

  • Reduce the main breaker (for example, 200 A to 175 A), if a load calculation shows the house can live with the smaller main.
  • Supply-side (line-side) connection, which connects the solar ahead of the main breaker (see below).
  • Replace the panel with one that has a higher-rated busbar, or upgrade the service. LBNL's August 2026 survey found a median main panel replacement cost of $3,500 in single-family homes (IQR $2,100 to $5,000).
  • Load management or meter-collar devices, where the utility allows them, which an LBNL presentation for ENERGY STAR lists among alternatives to panel upgrades.

Center-fed panels have special rules; IAEI notes that a 2014 NEC change allowed the 120% rule on dwelling center-fed panels with the solar breaker at either end, but not both.

What is a line-side tap (supply-side connection)?

A supply-side connection attaches the solar output to the service conductors between the meter and the main disconnect, instead of to a breaker in the panel. NEC 705.12(A) permits it, pointing to 230.82(6), which allows equipment such as solar to be connected on the supply side of the service disconnect, according to IAEI.

Because those conductors have no overcurrent protection from the utility side, IAEI advises treating supply-side conductors like service conductors, with proper grounding and bonding and a new service-rated disconnect, labeled so first responders know it exists. IAEI also points to UL's line-side tap installation guidelines.

What to ask:

  • Does the panel or meter-main manufacturer allow a tap at that point, or is there a listed connection kit?
  • Does the utility have rules about connections in or near the meter can?
  • Where will the new solar disconnect go, and how will it be labeled?

A line-side tap is not DIY work and should be done by a licensed electrician.

What is rapid shutdown?

Rapid shutdown is a safety function that lets firefighters quickly reduce voltage on solar wiring on or in a building. IAEI explains that it came into the 2014 NEC as section 690.12, "Rapid Shutdown of PV Systems on Buildings," after an NFPA task group focused on firefighter safety. In the 2014 version, the controlled conductors were those more than 5 feet inside a building or more than 10 feet from the array, and controlled circuits had to drop to a low voltage within a set time. Later editions tightened the requirements, and rooftop systems today commonly use module-level shutdown. Your installer should design to the edition your jurisdiction enforces.

How systems comply:

  • Microinverters or listed AC modules shut down when utility power is lost, so the service disconnect can act as the initiator, IAEI notes.
  • String inverters usually pair with module-level shutdown devices on the roof and a labeled initiator switch near the service.

For you as an owner: know where your rapid shutdown switch is, keep its label intact, and do not let anyone remove module-level devices during a repair without replacing them with compatible ones.

Who inspects a solar install, and what is permission to operate (PTO)?

Local inspection

Florida's rule requires every investor-owned utility's standard interconnection agreement to require that customer-owned renewable generation be inspected and approved by local code officials before it operates in parallel with the utility (FAC 25-6.065(5)(a)). In Texas, the city or county building department inspects where it has jurisdiction. Austin Energy goes further in its territory: it requires an Auxiliary Power electrical permit from Austin Development Services and a final solar inspection before any solar system can be turned on, with rough inspections for any wiring that will be covered.

Utility approval and PTO

PTO is the utility's written OK to turn the system on. Oncor says customers may install their system at any time, but are not authorized to operate it until the interconnection agreement is complete and Oncor has provided a Permission to Operate letter. Oncor follows PUCT Substantive Rule 25.211 timelines for processing applications.

Florida timelines under Rule 25-6.065

StepDeadline
Utility confirms it has all documents, or explains what is missing10 business days after receiving the application
Utility executes the standard interconnection agreement30 calendar days after a complete application (90 days if a Tier 3 study is needed)
Customer returns the signed agreementAt least 30 days before parallel operation, and within one year
Utility completes any physical inspection30 calendar days after receiving the signed agreement
Customer notifies utility before first operationAt least 10 days before

Do not switch your system on early. Operating without PTO can violate your agreement and create safety problems for line crews.

How does solar interconnection work with FPL, Duke or TECO? Florida's net metering rule

Florida's Public Service Commission rule 25-6.065, Florida Administrative Code, applies to investor-owned utilities, which include FPL, Duke Energy Florida and Tampa Electric. Municipal utilities such as JEA and rural electric co-ops must have their own standardized interconnection agreement and net metering program under s. 366.91(6), Florida Statutes.

The three tiers

TierSystem size (gross power rating)FeesLiability insurance the utility may require
Tier 110 kW or lessNo fees beyond those other customers pay, including no application feeNone (utility may only recommend it)
Tier 2Over 10 kW to 100 kWPSC-approved application feeNo more than $1 million
Tier 3Over 100 kW to 2 MWPSC-approved application fee and possible interconnection study chargeNo more than $2 million

To qualify for expedited interconnection, the system's gross power rating also may not exceed 90 percent of your utility distribution service rating. For inverter systems, the rule calculates AC rating as DC nameplate times 0.85.

How net metering credits work

  • The utility installs, at no added cost, a meter that measures the difference between what it supplies and what you send to the grid.
  • If you export more than you use in a billing cycle, the excess becomes a credit on next month's energy usage.
  • Credits roll forward for up to 12 months. At the end of each calendar year, the utility pays you for unused credits at an average annual rate based on its COG-1 as-available energy tariff, which is generally lower than the retail rate.
  • You still pay the customer charge and any applicable demand charge.
  • If you leave the utility's system, unused credits are paid out at the same as-available rate.

Manual disconnect

Florida utilities may require a lockable, visible-break manual disconnect next to the meter, but inverter-based Tier 1 systems are exempt unless the utility pays to install it. Utilities may open it for emergencies, hazards, power quality problems, or lapsed insurance, and must leave a door hanger if they do so without notice.

Does Texas have net metering?

Not in the Florida sense for most of the state. Texas has three different situations:

Where you liveWho approves interconnectionHow exports are credited
Competitive areas (for example, Oncor, CenterPoint and AEP Texas service areas)The wires company (for example, Oncor)Your retail electric provider's plan. Oncor measures surplus generation and sends it to your REP, and points customers to Power to Choose to compare buyback plans.
Austin EnergyAustin EnergyValue of Solar rate on 100 percent of production
CPS Energy (San Antonio) and other city utilities and co-opsThe utilityThe utility's own rate or rider; check current terms

We did not find a statewide Texas rule that sets a net metering credit rate the way Florida's Rule 25-6.065 does, so compare plans carefully. A "buyback" plan can credit exports at a rate very different from what you pay for power.

Austin Energy's Value of Solar

  • Austin Energy meters your total solar production and credits 100 percent of it at the Value of Solar rate, while charging you for all the energy you consume.
  • Effective October 1, 2026, the rate is 12.89 cents per kWh for systems under 1 MW-AC and 10.22 cents for larger systems, subject to change.
  • Excess credit carries over month to month, is non-transferable, and applies only to electric charges, not water or other city services.
  • The rate is recalculated every three years as the average of the five previous years' assessments. The residential rate was 9.91 cents from fiscal 2023 through 2026.
  • Austin Energy recommends sizing the system to your annual consumption.

Oncor's interconnection basics

  • Installers submit the application through Oncor's installer portal; DIY customers contact dg@oncor.com.
  • For small inverter-based systems certified to UL 1741, Oncor says there are generally no fees, but customers pay for any needed distribution upgrades, such as a larger transformer.
  • Oncor requires a visible, lockable, labeled AC disconnect and asks that it be within 10 feet of the meter.
  • If you buy a home that already has solar, email Oncor to transfer the interconnection agreement into your name.

Can my solar work during a power outage?

Only with a battery and backup equipment. Grid-tied inverters must stop exporting when the grid goes down. Florida's rule requires a utility-interactive inverter or other certified device that automatically isolates the system from the grid when the grid loses power, and IAEI notes that all utility-interactive inverters cease energizing their output on loss of utility power. This protects lineworkers repairing the lines.

A battery with a backup gateway disconnects your home from the grid during an outage and lets the solar and battery run your backed-up circuits. See home battery backup.

What license does a solar installer need in Texas and Florida?

Florida

  • Florida defines a solar contractor as one who installs, alters, repairs, maintains, relocates or replaces solar panels for solar water heating, pool heating and photovoltaic systems and related equipment (s. 489.105). Solar contractors are licensed under chapter 489 part I.
  • Electrical contractors certified (EC) or registered (ER) under part II can do electrical work on PV systems within their scope. Section 489.105 also says a contractor certified or registered under that chapter does not need to become a solar contractor to provide services within the scope it is already allowed to perform.
  • Verify any license on DBPR's license lookup or call (850) 487-1395.

Texas

  • Electrical work on solar systems requires a TDLR-licensed electrician working through a licensed electrical contractor.
  • The Residential Solar Retailer Regulatory Act (Occupations Code ch. 1806), enforced by TDLR, applies to most residential solar sales and leases. Since September 1, 2025, contracts must state that installation will be done by a licensed electrical contractor and give that contractor's name and license number, say who obtains permits and utility interconnection approval, and allow the buyer or lessee to cancel without penalty by written notice on or before the fifth business day after signing.
  • Starting September 1, 2026, people and companies who sell or lease most residential solar systems must be registered with TDLR. Licensed electrical contractors who sell solar are exempt from registration but must follow most of the Act.
  • The Act exempts some systems, including those on multifamily buildings with four or more units or stories, nonresidential property, temporary or emergency systems, single-appliance systems, and very small systems under 1 kW.

Can my HOA stop me from installing solar?

Texas: Property Code 202.010

A property owners' association may not prohibit or restrict solar energy devices, and a provision that does is void. The HOA may still prohibit devices in certain cases: on HOA or common property, in locations other than the roof or a fenced yard or patio, roof-mounted devices that extend higher than or beyond the roofline, devices whose frames or visible wiring are not silver, bronze or black, devices taller than the fence line in a yard, devices that void material warranties, and devices installed without required prior approval. An HOA's designated roof area can be overridden if another location increases estimated annual production by more than 10 percent, using a public NREL modeling tool.

Florida: s. 163.04

Deed restrictions, covenants and declarations may not prohibit solar collectors or other renewable energy devices from being installed on buildings, and owners may not be denied permission. The approving entity may decide the specific roof location within an orientation to the south or within 45 degrees east or west of due south, as long as that does not impair the system's effective operation. The prevailing party in litigation under this section is entitled to costs and reasonable attorney's fees.

Why is my solar not producing?

Start with the simple checks, and never open the inverter or combiner boxes yourself. Solar wiring can be energized whenever the sun is up.

  1. Is the grid down? Without a battery, grid-tied solar shuts off in an outage.
  2. Check the solar breaker and AC disconnect. A tripped solar breaker or a disconnect left off after a repair is common.
  3. Check the rapid shutdown switch. If someone pressed it, the system stays off until it is reset as the manual describes.
  4. Look at the inverter display or app for fault codes. Write them down for the service call.
  5. Check monitoring. A dead internet connection can make a working system look offline.
  6. Did you get PTO? New systems should not be producing until the utility approves.
  7. Shading, dirt or damage. New tree growth, debris after a storm, or broken panels.
  8. Meter issues. If production looks normal but bills do not, ask the utility to verify the meter and your account setup. In Texas competitive areas, Oncor says it can take up to one full billing cycle after approval to update your load profile so surplus generation reaches your REP.

If a breaker trips repeatedly, or you smell burning near equipment, leave it off and call a licensed electrician or your installer.

Can an electrician fix my solar if the installer went out of business?

Yes. "Orphaned" systems, whose installer has closed, are common. A licensed electrician (or, in Florida, a licensed solar contractor) can troubleshoot and repair them. To make that easier:

  • Gather documents: permit and inspection records from the building department, the interconnection agreement and PTO from the utility, the equipment list (panel, inverter and optimizer or microinverter models and serial numbers), and the single-line diagram.
  • Go to the manufacturers directly for warranty claims. Equipment warranties usually come from the manufacturer, not the installer, though labor coverage may have ended with the installer.
  • Get monitoring access transferred to your account.
  • Ask for a full system check, including rapid shutdown function, grounding, labels, roof penetrations and the point of connection.
  • Keep the utility in the loop. Adding or changing equipment can require a new interconnection application; Oncor requires one when equipment is added.

Expect a diagnostic fee. Some electricians decline work on equipment they did not install, so ask up front whether they service your inverter brand.

Avoiding solar sales problems

  • Read the whole contract. In Texas, it must name the licensed electrical contractor and give a five-business-day cancellation right under the Residential Solar Retailer Regulatory Act.
  • In Florida, a sale over $25 solicited and agreed to at your home generally can be canceled until midnight of the third business day after signing under the home solicitation law (ss. 501.021, 501.025), unless you initiated the request for the specific goods or services.
  • Ask whether your panel passes the 120% rule, and get any panel upgrade in writing before signing.
  • Ask who pays if the utility requires a transformer or service upgrade.
  • Ask for a production estimate in writing and how it was calculated.
  • Check the installer's license on TDLR or DBPR, and in Texas check the retailer's TDLR registration once that requirement applies.
  • Report deceptive practices to the Texas Attorney General or Florida's DBPR and local consumer agencies.

How to choose a provider

  • Photograph your main panel label showing the busbar rating and main breaker size.
  • Ask the installer to show the 120% rule math, or the alternative connection they propose.
  • Confirm who pulls the building permit and who submits the utility interconnection application.
  • Check HOA rules against Texas Property Code 202.010 or Florida s. 163.04.
  • Verify licenses: TDLR electrical contractor (Texas) or DBPR solar or electrical contractor (Florida).
  • In Texas, confirm the contract names the licensed electrical contractor and states the five-business-day cancellation date.
  • In Florida, confirm your tier under Rule 25-6.065 and any fees or insurance required.
  • In Texas competitive areas, compare REP buyback plans before PTO.
  • Do not operate the system until you have the final inspection and the utility's permission to operate.
  • Keep the permit, inspection, interconnection agreement, PTO and equipment list together for future service or sale.

Related electricians guides

Electricians by state and city

Questions people ask

Does a new main panel come with solar automatically?

No. Many systems connect to an existing panel under the 120% rule or through a supply-side connection. A panel replacement is needed only if the busbar and main breaker cannot accept the inverter's output, the panel is full or obsolete, or other upgrades are planned. If an installer says you need a new panel, ask them to show the busbar rating, the inverter output current and the 120% rule math, and get the panel work itemized in the contract.

How long does it take to get permission to operate?

It varies. Florida's rule gives investor-owned utilities 10 business days to respond to an application, 30 calendar days to execute the interconnection agreement after a complete application (90 for a Tier 3 study), and 30 days to complete inspections after receiving the signed agreement. Oncor follows PUCT Substantive Rule 25.211 timelines. Local permit and inspection scheduling adds time. Ask your installer for a realistic timeline for your utility.

Will my Florida utility pay me for extra solar power?

Yes, but mostly as bill credits. Under Rule 25-6.065, excess energy in a billing cycle becomes a credit toward the next month's energy usage, credits roll forward for up to 12 months, and at the end of the calendar year the utility pays for unused credits at an average annual rate based on its as-available energy tariff, which is generally lower than retail. You still pay the customer charge. Municipal utilities and co-ops set their own programs.

Do I need to tell my homeowners insurance about solar?

It is a good idea. A Florida investor-owned utility cannot require liability insurance for a Tier 1 system, but your homeowners insurer may want to know about rooftop equipment for property coverage, and Tier 2 and Tier 3 systems can require liability insurance of up to $1 million and $2 million. Ask your agent how panels are valued and whether wind or hail damage to panels is covered.

Can I install solar panels myself in Texas or Florida?

Texas allows an owner who lives in the home to do work not regulated by a city ordinance, and Oncor has a process for DIY customers through dg@oncor.com, but most cities require permits and licensed electricians for the electrical connection. Florida's owner-builder exemption allows an owner to do electrical work on their own home under a permit. You still need inspection and utility approval before operating. The connection to the panel or service is the riskiest part.

What happens to my solar agreement if I sell my house?

The buyer takes over the system, but paperwork has to move. In Oncor's area, the new owner emails dg@oncor.com to transfer the interconnection agreement, and Oncor sends a new agreement for signature. Leased systems and solar contracts have their own transfer terms. Give the buyer the permit and inspection records, PTO, warranties and monitoring access. In Florida, the buyer's utility account also needs net metering set up.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration