Punch Lists, Final Walkthrough and Closeout: What Must You Have Before Final Payment?
The last 5% of a construction job decides whether you finish with clean title, working warranties and a closed permit, or with a lien and an open inspection. This guide covers the punch list, the final walkthrough, holdback math, Texas retainage and affidavits, Florida's final payment affidavit and notice of termination, and the documents to collect.
A punch list is the written list of unfinished or defective items at the end of a job. Walk through at substantial completion, and before final payment confirm: the final inspection passed and you have a certificate of occupancy or completion; every punch item is done or covered by a holdback; you have lien releases on your state's statutory forms; and you have warranties, manuals and as-built records. In Texas, hold 10% for 30 days after completion. In Florida, get the Contractor's Final Payment Affidavit first.
Key facts
- Texas owners must reserve 10% of the contract price, or of the value of the work, during the work and for 30 days after the work under the original contract is completed (Prop. Code s. 53.101).
- A Texas claimant's lien on those reserved funds requires a lien affidavit filed no later than the 30th day after the earliest of completion, termination or abandonment (Prop. Code s. 53.103).
- A Texas owner may file an affidavit of completion with the county clerk; it is prima facie evidence of the completion date, but if filed more than 10 days after completion, the filing date becomes the completion date (Prop. Code s. 53.106).
- At final payment on a Texas residential contract, the original contractor must sign a final bills-paid affidavit stating everyone was paid or listing who is owed (Prop. Code ch. 53).
- When final payment is due, a Florida contractor must give the owner a Contractor's Final Payment Affidavit listing any unpaid lienors who served a timely Notice to Owner, at least 5 days before suing on its lien (s. 713.06).
- Florida lien rights cannot be waived in advance, the statute provides progress and final payment waiver forms, and no one may require a different form (s. 713.20).
- A Florida owner may end a notice of commencement by recording a notice of termination, effective no earlier than 30 days after recording, which must be served on lienors and accompanied by the contractor's final payment affidavit (s. 713.132).
- A Florida notice of commencement expires 1 year after recording unless a different date is stated, and payments after expiration are improper payments (s. 713.13).
- In Florida, the 4-year limitations period and 7-year repose period for construction claims start at the earliest of a temporary CO, CO, certificate of completion or abandonment (s. 95.11(3)(b)).
What is a punch list?
A punch list (also written punchlist) is a written list of work that is incomplete, damaged or not built to the contract, made near the end of a project. Typical items: a missing cabinet pull, a scratched window, paint touch-ups, a door that rubs, a GFCI outlet that does not trip, caulk gaps at the tub, a missing transition strip, a sprinkler head that sprays the new siding.
A punch list is for small items. It assumes the job is substantially complete, meaning you can use the space for its intended purpose. If major systems are not working, a room is unfinished or the final inspection has not been scheduled, you are not at the punch-list stage yet, and you should not let the contractor treat big unfinished work as "punch list" to justify asking for final payment.
Who makes it
On most homeowner jobs, the contractor walks the job first and fixes what it finds, then walks it with you. You add anything you see. On larger jobs the architect or owner's representative may prepare it. Either way, the list should be written, dated and signed or acknowledged by both sides.
What a good punch list entry looks like
| No. | Location | Item | Responsible | Due | Done / initials |
|---|---|---|---|---|---|
| 14 | Primary bath, left of vanity | Grout missing 6 inches along tub deck; recaulk inside corner | Tile sub | [date] | |
| 15 | Kitchen | Dishwasher door hits island panel; adjust or shim | GC | [date] | |
| 16 | Exterior, rear | Hose bib loose; secure to framing and seal penetration | Plumber | [date] |
Attach a photo for each item. Number them so nobody argues later about which "scratch on the floor" was meant.
When should I do the final walkthrough?
Schedule it after three things have happened:
- The contractor tells you in writing the work is substantially complete.
- The final inspection has passed, or is scheduled and the contractor has finished everything the inspector will check.
- Cleaning is done, so you can actually see finishes. Dust hides scratches.
Go in daylight, then come back at night with all lights on. Bring the contract, plans, change orders, a tape measure, a level, painter's tape to flag items, a phone charger (to test outlets with a plug-in tester) and a flashlight.
Walkthrough checklist by area
- Everything that moves: open and close every door, window, drawer and cabinet. Check locks and latches.
- Everything that flows: run every faucet hot and cold, fill and drain every tub and sink, flush every toilet, look under sinks with a flashlight. Run the dishwasher and washer for a cycle if they were installed.
- Everything electrical: every switch, outlet, light, fan, GFCI and AFCI test button, smoke and carbon monoxide alarm, doorbell and garage opener.
- HVAC: run heating and cooling. Check every register for airflow and that the thermostat programs. Ask for the equipment model and serial numbers.
- Finishes: look at walls and ceilings at a low angle with a flashlight, floors for scratches, lippage in tile, gaps at trim, paint coverage.
- Exterior and roof: grading slopes away from the house, gutters and downspouts discharge away from the foundation, flashing and sealant at windows and penetrations, debris removed, landscaping repaired.
- Things you cannot see later: ask for photos of in-wall work, insulation and waterproofing taken before cover-up.
Anything not on the punch list at signoff becomes a warranty claim instead, which is slower. Be thorough now.
How long does a contractor have to finish the punch list?
Whatever the contract says. Neither Texas nor Florida sets a general statewide deadline for punch-list work on a private home job. Many contracts say punch items must be finished within a set number of days after the walkthrough (14 or 30 days is common) and let the owner hire others and deduct the cost if the contractor does not finish. If your contract is silent, put a date in writing when you sign the punch list: "All items below to be completed by [date]. Items not completed by then may be completed by others and the cost deducted from the final payment."
Punch list work and lien deadlines in Florida
In Florida, a claim of lien must be recorded within 90 days after the lienor's final furnishing of labor, services or materials (s. 713.08). Contractors sometimes argue that a late punch-list visit restarts that clock. Whether minor corrective or warranty work counts depends on the facts and the contract, so do not rely on old work dates to protect you. Get lien releases instead, and see the Florida lien law guide.
Texas completion date
In Texas, the completion date drives the 30-day retainage period and lien deadlines. An owner can fix that date on the public record by filing an affidavit of completion (below).
Should I hold back money for the punch list? Holdback math
Yes, within the limits of your contract. A holdback is money you keep from the final payment until specific items are done. A retainage is a percentage kept from each payment throughout the job. Texas requires a form of retainage by statute; elsewhere both come from your contract.
Texas statutory retainage
During the work and for 30 days after the work under the original contract is completed, the owner must reserve 10% of the contract price, or 10% of the value of the work done measured against the contract price (s. 53.101). The reserved funds secure payment of subcontractors, laborers and suppliers who give the required notices. A claimant has a lien on them only if it sends the required notices and files a lien affidavit within 30 days after the earliest of completion, termination or abandonment (s. 53.103). If you do not reserve, complying claimants have a lien on your property at least up to the amount you should have reserved (s. 53.105).
Example: a $90,000 Texas remodel. You hold back $9,000 across the job. The work is complete on May 10. You keep the $9,000 through June 9. If no one has filed a retainage lien affidavit by then and you have no unresolved notices of claim, you can release the retainage against a final bills-paid affidavit and final lien waivers. If a subcontractor sent you a notice of claim for $4,200, you keep that amount until it is resolved.
Punch list holdback
A common approach is to hold the cost to finish each open item, often with a cushion the contract specifies, because a contractor brought in just to do punch work charges more per item. Example for a Florida job whose contract has no retainage clause:
| Open item | Estimated cost to complete |
|---|---|
| Regrout and recaulk tub deck | $350 |
| Replace scratched sliding door glass panel | $1,100 |
| Adjust and re-hang two doors | $300 |
| Paint touch-up, three rooms | $450 |
| Total | $2,200 |
| Holdback at 150% (if your contract allows a multiplier) | $3,300 |
Release it item by item as work is finished and verified, or all at once when the list is signed off. Put the method in writing.
What not to do
- Do not withhold far more than the open items are worth. A big, unexplained holdback can be a breach that lets the contractor claim interest or fees.
- Do not pay the final balance before you have lien paperwork, even if the punch list is done.
- In Texas, do not release the 10% retainage before the 30 days after completion run.
Final inspection, certificate of occupancy and certificate of completion
The final inspection is the building department's last inspection under the permit. Passing it is how the permit is closed.
- A certificate of occupancy (CO) is issued for new buildings, additions or changes of use and says the space may be legally occupied. A temporary CO lets you occupy before some items are finished.
- A certificate of completion (CC) is typically issued for work that does not need a new CO, such as many remodels, and confirms the permitted work passed final inspection.
- Some remodel permits simply show "final passed" or "closed" in the permit portal with no separate certificate.
Which one you get depends on the city or county and the permit type. Ask the building department or check the portal for your permit number.
Why it matters
- Selling or insuring: an open or expired permit can show up in a buyer's or insurer's search and may require re-permitting.
- Florida legal clocks: the 4-year limitations period and 7-year repose period for construction claims run from the earliest of a temporary CO, CO or certificate of completion (s. 95.11(3)(b)), and ch. 558 treats a CO as "completion" (s. 558.002(4)). Note the date.
- Florida permit expiration: a single-family dwelling permit expires 1 year after issuance or on the effective date of the next Florida Building Code edition, whichever is later, unless extended, and local governments may send a written expiration notice at least 30 days before (s. 553.79).
- Who is responsible: in Austin, the general contractor on a permit is responsible for scheduling inspections, including the final, and obtaining the certificate of occupancy or completion. Dallas's single-family remodel checklist requires an energy code certificate to be submitted to the electrical inspector before final inspection. Expect similar duties in Houston, San Antonio and Florida jurisdictions.
Make passing the final inspection and delivery of the CO or CC (or a printout showing the permit closed) a condition of final payment in your contract. See building inspections explained.
What is a final lien release, and what does each state require?
A lien release (or lien waiver) is a signed document in which a contractor, sub or supplier gives up its right to place a lien on your property for work paid for. A final release covers all work on the job. Here is what to collect at closeout.
Texas
- Statutory forms only. Texas lien waivers are unenforceable unless they substantially comply with one of four statutory forms: conditional and unconditional waiver and release on progress payment, and conditional and unconditional waiver and release on final payment. They must be signed by the claimant, and a conditional waiver is effective only with evidence of payment (Prop. Code ch. 53, Subchapter L).
- Sequence: collect a conditional waiver on final payment from the contractor and each sub or supplier being paid, make payment, then collect the unconditional version. No one may be required to sign an unconditional waiver before actually receiving the payment in good funds.
- Final bills-paid affidavit: at final payment on a residential contract, the original contractor must sign an affidavit that everyone has been paid in full, or listing who is unpaid and how much.
- Disbursement statements and the sub list: on residential contracts, the contractor must give you a list of subs and suppliers before work starts (unless you signed the statutory waiver) and a disbursement statement with each payment request. Use them to check who should be giving you waivers.
More: Texas lien waivers and releases.
Florida
- Contractor's Final Payment Affidavit: when final payment is due, the contractor must give you an affidavit stating that all lienors under contract with it who served a timely Notice to Owner have been paid in full, or listing each unpaid lienor and the amount. It must be given at least 5 days before the contractor sues to enforce its lien, and the contractor has no lien or right of action against you while it is in default of giving it (s. 713.06).
- Releases from Notice to Owner senders: you have no obligation to lienors (other than laborers) who had not served a Notice to Owner at the time of payment. For everyone who did, get a Waiver and Release of Lien Upon Final Payment in the statutory form. Nobody may require a different form, waivers cannot be given in advance, and a lienor may make its waiver conditional on a check clearing (s. 713.20).
- False affidavits are crimes: knowingly giving a false affidavit or release about payment of subs or suppliers to induce final payment is a third-degree felony (s. 713.35), and false statements that subs were paid are a licensing violation (s. 489.129(1)(k)).
More: Florida construction lien law for homeowners.
Texas: the affidavit of completion
A Texas owner may file an affidavit of completion with the county clerk where the property is located (s. 53.106). It must contain:
- The owner's name and address.
- The original contractor's name and address.
- A legal description of the property.
- A description of the improvements under the original contract.
- A statement that the improvements are complete and the date of completion.
- A conspicuous statement that a claimant may not have a lien on retained funds unless it files a lien affidavit in the time and manner the chapter requires.
Send copies to the original contractor and to each claimant who sent you a notice of claim, no later than the 3rd day after filing or the 10th day after you received the notice, whichever is later. Anyone who furnished labor or materials and asks in writing must also get a copy.
Why it helps: a filed affidavit is prima facie evidence of the completion date, which starts the 30-day retainage period. If you file it more than 10 days after completion, the filing date becomes the completion date for that subchapter. So file promptly: within 10 days of actual completion.
Florida: closing out the notice of commencement
Your recorded Notice of Commencement (NOC) stays in effect for 1 year after recording unless it states another date. Payments made after it expires are improper payments, which can expose you to paying twice (s. 713.13). At closeout you can either let the NOC run its course after the job is paid off, or end it early.
To end it early, record a notice of termination under s. 713.132. It must contain:
- The same information as the NOC, plus the NOC's official records book and page or instrument number and recording date.
- The date the NOC is terminated, which may not be earlier than 30 days after the notice of termination is recorded.
- Which property it applies to.
- A statement that all lienors have been paid in full.
- A statement that, before recording, you served a copy on each lienor with a direct contract with you or who served a timely Notice to Owner, and that you will serve any lienor who serves a timely Notice to Owner after recording.
It must be accompanied by the contractor's final payment affidavit, and you may record it any time after all lienors are paid in full or pro rata. You need not serve lienors who already signed a final payment waiver. An owner or contractor who makes a fraudulent statement in it is liable to any lienor harmed. A notice of termination matters most when you plan new work on the property soon, or are selling the property. See the notice of commencement guide.
What documents should I get at closeout?
| Document | Why you need it |
|---|---|
| Final inspection approval and CO or certificate of completion | Proves the permit is closed; starts Florida claim periods |
| Final lien waivers (statutory forms) from the contractor and every sub and supplier who gave notice | Clears lien risk |
| Texas: final bills-paid affidavit; Florida: Contractor's Final Payment Affidavit | Contractor's sworn statement of who is paid |
| Signed punch list with completion initials | Shows items accepted |
| Contractor's written workmanship warranty | States what is covered and for how long |
| Manufacturer warranties and registrations (roof, windows, HVAC, water heater, appliances) | Many require registration within a set time |
| Operation and maintenance manuals | Required maintenance often conditions warranties |
| As-built drawings or marked-up plans | Shows where pipes, wires and structure really are |
| Photos of in-wall work before cover-up | Helps future repairs and defect claims |
| Equipment model and serial numbers; HVAC startup or test report | Warranty and service |
| Paint colors, tile, grout and flooring product names and lot numbers; leftover stock | Matching repairs |
| Any engineer letters, special inspection reports, product approvals | Needed for insurance, resale and later permits |
| Keys, remotes, codes and passwords for smart devices | Security |
| Final accounting: contract price, change orders, payments, credits | Confirms the final number |
What are as-built drawings?
As-built drawings are plans updated to show what was actually built: moved walls, rerouted ducts, added blocking, where plumbing and electrical lines run, and any field changes. On small jobs they may be a marked-up copy of the permit plans. Ask for them in the contract, because they are hard to recreate later.
Closeout sequence, step by step
- Contractor gives written notice of substantial completion.
- Final inspection passes; get the CO or CC or permit-closed record.
- Walkthrough; sign a numbered punch list with a completion date.
- Agree in writing on the holdback amount for open items.
- Texas: file an affidavit of completion within 10 days of completion and send required copies; calendar the 30-day retainage date.
- Collect manuals, warranties, as-builts and product information.
- Punch items completed and initialed.
- Collect conditional final waivers (Texas) or the final payment affidavit and final waivers from Notice to Owner senders (Florida).
- Make final payment, by check or traceable payment, matched to the waivers.
- Collect unconditional final waivers (Texas) once funds clear, and the final bills-paid affidavit.
- Texas: release retainage after the 30 days if no valid claims are pending.
- Florida: optionally record a notice of termination of the NOC.
- Register warranties and store all documents together.
Commercial build-outs and condos
- Commercial tenants: many leases require a CO or certificate of completion, final lien waivers and as-builts before the landlord releases a tenant improvement allowance. Check your lease's closeout list.
- Texas non-residential projects have longer lien deadlines (the 15th day of the fourth month), so final waivers matter even more.
- Florida condominium units: get the association's final signoff if its rules require one, and keep records for future milestone inspections. For new condos, developer and contractor warranties under s. 718.203 run from completion of the building or improvement, defined by issuance of a CO.
This guide is general information, not legal advice. If a lien has been recorded, the contractor refuses to provide the affidavits, or the holdback is disputed, talk to a construction attorney. Local guides: Houston, Dallas, San Antonio, Austin, Miami, Tampa, Orlando, Jacksonville.
How to choose a provider
- Get written notice of substantial completion from the contractor.
- Confirm the final inspection passed and obtain the CO, CC or permit-closed record.
- Walk the job in daylight and at night; test every fixture, outlet and system.
- Sign a numbered, photographed punch list with a completion date.
- Agree in writing on a holdback for open items.
- Texas: file an affidavit of completion within 10 days and keep 10% retainage for 30 days after completion.
- Florida: get the Contractor's Final Payment Affidavit before final payment.
- Collect statutory-form lien waivers from the contractor and every sub or supplier who gave notice.
- Collect warranties, manuals, as-builts, product information and leftover materials.
- Pay by a traceable method matched to the waivers; then collect unconditional waivers (Texas).
- Florida: consider recording a notice of termination of the NOC.
- Register product warranties and file everything in one place.
Related general and residential contractors guides
- What Are the Texas Statutory Lien Waiver Forms, and When Should a Homeowner Ask for Each?
- How Does Florida Construction Lien Law Work, and How Do Homeowners Avoid Paying Twice?
- What Is a Florida Notice of Commencement, When Do You Need One, and How Long Does It Last?
- Building Inspections Explained: What Inspectors Check at Each Stage
- What Warranty Comes With a New Home or Remodel in Texas and Florida, and How Long Does It Last?
- Contractor Deposits and Payment Schedules: How Much to Pay and When
- How Do You Fire a Contractor Without Getting Sued or Liened?
General and residential contractors by state and city
Questions people ask
What should I check before final payment?
Before final payment confirm that the final inspection passed and you have a certificate of occupancy, certificate of completion or permit-closed record; the punch list is complete or covered by a written holdback; you have lien releases on your state's statutory forms from the contractor and from every sub or supplier who gave notice; and you have warranties, manuals and as-built information. In Florida, also get the Contractor's Final Payment Affidavit.
What is the difference between a certificate of occupancy and a certificate of completion?
A certificate of occupancy says a new building, addition or space with a change of use may legally be occupied. A certificate of completion typically confirms that permitted work which does not need a new CO, like many remodels, passed final inspection. Practices vary by city and county, and some remodel permits simply show final passed. Ask your building department which applies.
How long does a contractor have to finish the punch list?
Whatever your contract says. Neither Texas nor Florida sets a general statewide deadline for punch-list work on private home jobs. If the contract is silent, write a completion date on the signed punch list and state that unfinished items may be completed by others with the cost deducted from the final payment. Keep the holdback until the items are done.
How much should I hold back for the punch list?
Hold enough to finish the open items if the contractor does not, because a new contractor charges more for small jobs. Many contracts set a multiplier on the estimated cost. In Texas you must also keep 10% of the contract price, or of the value of work done, until 30 days after completion under Property Code s. 53.101. Do not hold back far more than the items are worth.
How do I close my permit?
The contractor of record usually schedules the final inspection and any required certificates, and in Austin that is expressly the general contractor's job. Check the permit portal for the status, make sure all required reports are submitted (Dallas, for example, wants an energy code certificate before final inspection), and get the CO or certificate of completion. In Florida, single-family permits expire 1 year after issuance unless extended.
What is a Texas affidavit of completion?
It is a document the owner files with the county clerk stating that the original contract work is complete and the completion date. It must include specific information and a warning about retainage liens, and copies must go to the contractor and anyone who sent a notice of claim. Filed within 10 days of completion, it is prima facie evidence of the completion date that starts the 30-day retainage period.
Do I need a notice of termination in Florida?
Not always. Your notice of commencement expires on its own after 1 year unless it says otherwise. A notice of termination lets you end it earlier, effective at least 30 days after recording, after all lienors are paid. It must be served on lienors who contracted with you or served a Notice to Owner and be accompanied by the contractor's final payment affidavit. It is most useful before new work or a sale.
What warranties and manuals should I receive?
Ask for the contractor's written workmanship warranty, manufacturer warranties and registration instructions for roofing, windows, doors, HVAC, water heaters, appliances and fixtures, and operation and maintenance manuals for each system. Many manufacturer warranties require registration within a set time or proof of maintenance. Keep model and serial numbers and the HVAC startup report together with the warranties.
Sources
- Texas Property Code ch. 53, Mechanic's, Contractor's, or Materialman's Lien
- Florida Statutes s. 713.06 (2026)
- Florida Statutes s. 713.08 (2026)
- Florida Statutes s. 713.13, Notice of commencement (2026)
- Florida Statutes s. 713.132, Notice of termination (2026)
- Florida Statutes s. 713.20, Waiver or release of liens (2026)
- Florida Statutes s. 713.35, False information (2026)
- Florida Statutes s. 489.129 (2026)
- Florida Statutes s. 95.11 (2026)
- Florida Statutes s. 558.002 (2026)
- Florida Statutes s. 553.79, Permits (2026)
- Florida Statutes s. 718.203, Warranties (2026)
- City of Austin, Contractor Registration
- City of Dallas, Single Family Dwelling Remodel checklist
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.