A change order is a written agreement that modifies a contract’s scope, price or time after signing, approved by the parties under the contract’s change procedure.
A change order is a written agreement that modifies a contract’s scope, price or time after signing, approved by the parties under the contract’s change procedure.
What change order means
A change order is the formal document that alters an existing construction contract. It records what changes, the effect on price, and any adjustment to the completion date, and it is signed by the parties named in the contract.
Changes can come from owner requests, design revisions, unforeseen conditions or regulatory input.
A plain example
An owner asks for an extra door opening after framing is ordered. The contractor prices the revision, including re-fabrication and any delay, and submits it. Once signed, the contract sum and schedule are updated. Figures in any sample are placeholders for the real project.
Why it matters
Work done without an agreed change order is a classic source of unpaid claims. Keeping the paper trail current also keeps the project cost report honest. A late design freeze raises the likelihood of changes.
Common confusion
A change order is not an RFI, which only seeks clarification, nor a purchase order revision, which sits at the supplier level. Contracts often split notice, pricing and approval steps, so follow the specific clauses and take legal advice when stakes are high.
Practical checklist
Handling change orders well mostly comes down to timing and records.
- Give notice as soon as a possible change is identified, following the contract’s notice clause.
- Price the direct work and describe any time effect separately.
- Keep supporting records, such as quotes, drawings and correspondence.
- Do not proceed on disputed items without understanding the payment risk.
- Update the schedule of values and programme after each approval.
Related terms
Questions people ask
Who can approve a change order?
The people the contract authorises, usually the owner and the contractor, sometimes via the design team.
Can I start work before it is signed?
It is risky. Many contracts require written approval first, so check the clause.
Do change orders always add cost?
No. They can reduce cost or time as well.
Sources and further reading
Have a project outline or drawings?
Organize your scope, then contact Digital Oro through its official channel. Availability, engineering, pricing and delivery terms need project-specific confirmation.
Text Digital Oro on WhatsApp Explore Digital Oro →+52 1 984 452 3553 · the WhatsApp number Digital Oro lists publicly
Digital Oro International advertises on The Company Chronicle. This guide was written by our editorial team from public sources and general professional practice; it does not describe a guarantee, quote or offer from Digital Oro International. Confirm current terms, prices and availability with the operator before you decide.