Do You Need a Panel or Service Upgrade for an EV Charger? What It Involves, Permits and Utility Steps

Many homes need only a new breaker and wire for a Level 2 charger. Here is how to tell, what an upgrade involves, and which permits and utility steps apply in Texas and Florida.

Many homes do not need a new panel for a Level 2 charger. EPA says a home with 200 amp service and two open double-pole slots likely has room, and even 100 amp service is often enough. A panel upgrade swaps the box. A service upgrade enlarges the utility connection and needs a permit, an inspection and utility disconnect and reconnect. A load calculation shows which one you need.

Key facts

  • EPA (May 2026): a home with at least 200 amps of service and two open double-pole breaker slots likely has capacity for a Level 2 charger; 100 amp service is often enough, depending on other loads.
  • DOE says the NEC treats EV charging as a continuous load, so the wire and breaker are sized at 125 percent of the charger's continuous output (DOE, March 2026).
  • A 40 amp Level 2 charger needs a dedicated 50 amp circuit (EPA).
  • DOE lists cheaper capacity options before an upgrade: low-power chargers, meter collars, smart breakers and circuit sharing.
  • Texas adopted the 2026 NEC effective September 1, 2026 for non-exempt electrical work (TDLR).
  • Florida's permit application date decides the code edition (Fla. Stat. 553.73(7)(d)); the 9th Edition starts December 31, 2026.
  • Texas Occupations Code 1305.003(a)(6) lets an owner-occupant do work only if no municipal ordinance regulates it.
  • EPA (May 2026) lists charger equipment at $400 to $1,000 and installation at $300 to $2,000; we found no sourced Texas or Florida price for a panel or service upgrade.

Panel upgrade or service upgrade: what is the difference?

People use these two terms as if they mean the same thing. They do not, and the difference decides the cost, the paperwork and who has to show up at your house.

  • Service is the connection between the utility's wires and your home. It includes the wires from the pole or transformer (the service drop or lateral), the electric meter, the meter base, and the main disconnect. The size of the service, such as 100 amps or 200 amps, is the total electric current your home is set up to receive. The utility owns the meter and the wires on its side. You own the equipment on your side.
  • Panel (also called the breaker box or load center) is the box that splits that power into circuits for the kitchen, the air conditioner, the dryer and so on. A panel has a main breaker rating and a limited number of breaker slots.
  • Subpanel is a second, smaller panel fed from the main panel. It adds breaker slots, often in a garage, but it does not add any total power to the house.

A panel upgrade usually means replacing the box, or adding a box, so you have the right number of slots or a better main breaker. A service upgrade means increasing the size of the connection itself, for example from 100 amps to 200 amps. A service upgrade almost always includes a new panel, a new meter base and heavier wire. It also needs the utility to cut power and later reconnect it.

That is why a service upgrade is a bigger job than a panel swap. A panel swap on the same service size may only need your electrician, the city inspector and a short power outage. A service upgrade needs your electrician, the city inspector and the utility, in a set order.

The U.S. Environmental Protection Agency (EPA) says an electrician can tell you whether your existing electrical panel can handle an EV charger or whether you might need upgrades (EPA Green Vehicle Guide, last updated May 7, 2026). The U.S. Department of Energy (DOE) says some homes lack the capacity for Level 2 charging, but a qualified electrician can add circuits (DOE Alternative Fuels Data Center, AFDC).

Do I need a new panel for an EV charger?

Often, no. Many homes can add a Level 2 charger with one new breaker and one new wire run. EPA gives a simple rule of thumb: a home with at least 200 amps of service and two open double-pole breaker slots (a double-pole breaker is the wide breaker that takes two slots and supplies 240 volts) likely has the capacity for a Level 2 charger. EPA also says even 100-amp service is often enough, depending on how much power your other appliances use. EPA notes that older homes usually have 60 or 100 amps, and homes built from about the 1980s on tend to have 200 amps or more.

You can often find your service size by looking at the main switch at the top of the panel. The number printed on it is the total amps your home can receive. Do not open the panel cover yourself. Only read the label on the outside or the main switch handle.

The signs that point toward an upgrade

  • The panel has no open slots and no way to free up space.
  • The service is 60 amps, or 100 amps with an electric range, electric water heater, electric dryer and central air conditioning all in use.
  • The panel is a brand or type that the electrician cannot add breakers to, or it shows burn marks, rust or water damage.
  • A load calculation (the math the electrician does to add up your home's maximum demand) shows the home would go over its limit with a charger added.
  • You plan to add more than one charger, a heat pump, an induction range or solar panels in the next few years.

The key point is that a charger is a continuous load. DOE states that the National Electrical Code (NEC) treats EV charging as a continuous load, meaning it runs for three hours or more. The NEC requires the wire and breaker to be sized at 125 percent of the charger's continuous output (DOE Multifamily EV Charging Guide, March 2026). EPA gives an example: a 40-amp Level 2 charger needs a dedicated 50-amp circuit. A charger that pulls 40 amps for eight hours is a heavy, steady draw. Your air conditioner in a Texas or Florida summer can add to that at the same time.

Use our guide on whether your panel can handle an EV charger for a walkthrough of the load math, and the NEC load calculation page for the formulas.

Cheaper ways to avoid a service upgrade

An upgrade is not the only answer. EPA and DOE both list options to try first. They are worth asking your electrician about before you accept a quote for a new service.

OptionWhat it doesWho says so
Lower-power chargerA 16-amp Level 2 charger may suit you if the panel is tight. DOE lists low-power chargers, which use 25 to 50 percent less power than a standard Level 2 unit, as the first and cheapest capacity strategy.EPA; DOE (March 2026)
Load management or circuit sharingA device that balances the charger against other big loads so the total stays under the limit. DOE describes smart breakers and energy management devices that pause or reduce charging when draw could exceed limits.EPA; DOE (March 2026)
Meter collar deviceA device that fits between the meter and the meter base and can control a charger without a panel change. DOE lists meter collars among its capacity strategies. Utility rules decide whether one is allowed at your address.DOE (March 2026)
Subpanel in the garageAdds slots near the charger. It does not add power, so it only helps if the problem is slot count or wire distance.General electrical practice
Level 1 chargingA standard 120-volt outlet on a dedicated circuit. DOE says many drivers meet their daily needs charging overnight this way.DOE AFDC

The 2026 NEC also adds rules for power control systems. According to EC&M's summary of the 2026 NEC, new section 120.7(B) says that when a power control system is used in a load calculation, its control setting cannot exceed 80 percent of the rating of the protected circuit breaker, and 120.7(C) covers how controlled loads are counted. These are trade press summaries, so your electrician should confirm the final text in NFPA 70-2026. Our page on load management and smart panels covers these devices in detail.

What a smaller charger really costs you in time

DOE says Level 2 charging adds roughly 25 miles of range per hour at typical power. A 16-amp charger delivers well under half of what a 40-amp unit does. For a driver who covers 30 to 40 miles a day, an overnight session of 8 to 10 hours still refills the day's driving. A driver who needs a full battery in a few hours, or who has two EVs, may find the small charger too slow.

What an electrician checks before recommending an upgrade

A good electrician walks the house first, then recommends. Expect these steps.

  1. Read the main breaker and the panel label. This gives the service size and the panel's maximum rating.
  2. Count open slots and look for tandem (half-size) breakers that can free space.
  3. Run a load calculation. This is the NEC method for adding up lights, outlets, appliances, heating and cooling to see the home's maximum demand. In Texas and Florida the air conditioner is often the biggest single load.
  4. Measure the distance from the panel to the charger spot. Long runs need thicker wire, which raises cost.
  5. Look at the panel's condition and whether grounding and bonding are correct.
  6. Check the meter base and service entrance for age and damage.
  7. Ask about future plans such as a second EV, a pool pump, a heat pump or solar.

In 2026 NEC, load calculation rules moved from Article 220 into new Article 120. The optional method for dwellings counts the EV charger at 100 percent of its nameplate rating with no reduction (section 120.82(D), per EC&M). The same article changes the optional method to count the first 8 kVA at 100 percent and the rest at 40 percent, and reduces the general lighting and receptacle load from 3 to 2 volt-amperes per square foot. The new numbers may change the result for some homes, but Texas and Florida use different code editions on different dates, so ask which edition your permit falls under. See our page on the 2026 NEC changes.

Ask for the load calculation in writing. A homeowner is allowed to ask why an upgrade is needed, and a clear answer should show the numbers.

Note: 2026 NEC section numbers in this guide come from published trade summaries and may be renumbered in the final adopted text. Confirm them in NFPA 70-2026 or with your electrician and local inspector before relying on them.

What does a panel or service upgrade cost?

We could not load a named, dated study that gives panel or service upgrade prices for Texas or Florida, so we are not going to print a dollar range for the upgrade itself. Cost pages on the internet often show wide ranges with no year or source. Treat those with caution.

What we can say, with sources and years:

  • EPA (Green Vehicle Guide, May 2026) lists Level 2 charger equipment at $400 to $1,000 and installation at $300 to $2,000, and says installation cost rises with higher amperage, longer distance from the panel, tricky locations and whether electrical upgrades are needed.
  • The National Renewable Energy Laboratory (NREL, September 2024) says installing a Level 2 charger at a single-family home may cost between $400 and $1,000, varying with equipment, labor and the need for electrical upgrades.
  • The NREL 2030 National Charging Network report (2023) assumed $500 to $1,700 to install a residential Level 2 port, in 2022 dollars.
  • DOE's AFDC says labor is the largest expense in a typical installation and that costs depend on trenching, existing wiring and required electrical upgrades.

These studies measure the charger install, not a service upgrade. They differ by study and year, so do not add them together. When a job needs a panel or service upgrade, ask at least two licensed electrical contractors for written quotes that separate three items: the charger circuit, the panel or service work, and permit and inspection fees. Our installation cost guide explains how to compare quotes.

Utility charges are a separate item. In Texas the wires company (called a transmission and distribution service provider, or TDSP) such as Oncor or CenterPoint owns the meter and the lines. Oncor says it owns the poles, wires and meters that deliver electricity. Whether any fee applies to a residential service change depends on the utility's tariff, so ask the utility directly.

Permits and inspections for a panel or service upgrade

A panel or service upgrade is electrical work that needs a permit almost everywhere in Texas and Florida. The EV charger circuit may be covered in the same permit or may need its own. Ask the city or county building department.

Texas

  • Who may do the work. TDLR says anyone who performs or offers to perform non-exempt electrical work in Texas must be licensed and must work through a licensed electrical contractor. Verify a license on the TDLR electricians page.
  • Owner exemption is narrow. Texas Occupations Code 1305.003(a)(6) exempts work in a dwelling by a person who owns and lives in it, but only if the work is not specifically regulated by a municipal ordinance. Many cities regulate it. Service upgrades also involve the utility, and the utility may ask for proof of inspection before it reconnects power.
  • Code edition. Texas adopted the 2026 NEC effective September 1, 2026 for all non-exempt electrical work, inside a city or out in the county (TDLR, 16 TAC 73.100). Houston says permit applications on or after September 1, 2026 are reviewed against the 2026 NEC.
  • Fees. Under Occupations Code 1305.201(f) a city may not collect a permit or registration fee from a licensed electrician but may still charge a building permit fee. Ask your city how it handles this.

Florida

  • Who may do the work. Florida Statutes chapter 489, part II, governs electrical contractors. The Department of Business and Professional Regulation (DBPR) licenses them and you can check a license at MyFloridaLicense.com.
  • Owner-builder. Section 489.503(6) lets an owner do electrical work on a single-family or duplex residence for their own use, if they personally appear, sign the permit application and receive the disclosure statement. The owner may not hire an unlicensed person to do the work, and the work must meet the code. We do not suggest homeowners do service work themselves.
  • Code edition. Florida Statutes 553.73(7)(d) says the Florida Building Code edition in effect on the date of permit application governs. The 8th Edition (2023) applies through December 30, 2026 and the 9th Edition (2026) from December 31, 2026. The 9th Edition adopts the 2023 NEC, according to the International Code Council.

After the work, the building department inspects it. When the inspection passes, the city or county notifies the utility, or the electrician does, depending on the local process. Do not assume this step is automatic. Ask your electrician who is responsible for sending the release.

The utility steps in Texas and Florida

We could not load a utility document that lays out the step by step for a residential service upgrade in Texas or Florida. The steps below are the typical order. Confirm each one with your utility, because details differ.

  1. Tell the utility early. DOE's AFDC advises engaging the utility early to identify service upgrade needs and costs. Use the number on your bill or the utility's new service or service change page.
  2. Get the permit. Your licensed electrician applies at the city or county.
  3. Schedule the outage. The utility usually has to disconnect power at the meter or pole so the old meter base and wire can be replaced. Some utilities schedule this with the electrician. Plan for a power outage that day, and for refrigerated food and medical equipment.
  4. Install the new equipment. The electrician installs the meter base, main breaker, panel and service wire.
  5. Pass the inspection. The building inspector looks at the new service.
  6. Reconnect. After the release, the utility restores power and may install or reset the meter.

In Texas, utilities that deliver power in the competitive market include Oncor, CenterPoint Energy Houston Electric, Texas-New Mexico Power and AEP Texas. Austin Energy and CPS Energy are city-owned. Your retail electric provider (the company you pay for energy) is not part of the service work. In Florida, the main utilities are FPL, Duke Energy, Tampa Electric, JEA and Orlando Utilities Commission.

We could not confirm a published timeline for a house in either state. The permit, the inspection and the utility visit each add waiting time, so do not plan around a date until the electrician and the utility confirm one in writing.

Sequence of events and who does what

StepTexasFlorida
License checkTDLR electrician or electrical contractor licenseDBPR electrical contractor license (certified or registered)
PermitCity or county building or electrical officeCity or county building department, under the Florida Building Code
Code in effect2026 NEC for applications from Sept. 1, 20268th Edition FBC through Dec. 30, 2026, then 9th Edition
UtilityOncor, CenterPoint, TNMP, AEP Texas, Austin Energy, CPS Energy or a co-opFPL, Duke, Tampa Electric, JEA, OUC or a municipal or co-op utility
Inspection releaseCity inspector to utilityBuilding department to utility

Our permit pages cover the local details: Texas, Florida, Houston, Dallas, San Antonio, Austin and Miami.

Hurricane, flood and weather points for Texas and Florida homes

Service equipment sits outside, so weather matters. If you live in a flood zone, ask whether the meter and service equipment must be raised. Local floodplain rules in Harris County, Miami-Dade and coastal cities can affect where the equipment goes. Our guide on EV chargers, floods and hurricanes goes deeper. After a storm, a damaged meter base needs an electrician and utility sign-off before the utility restores power, which is a separate process from a planned upgrade. DOE says outdoor charging equipment and use in the rain are safe, but outdoor installations need outdoor-rated equipment.

If you are planning other electric upgrades at the same time, such as a heat pump, do one load calculation for all of them. Doing the service upgrade once costs less in time and permits than doing it twice.

Questions to ask before you sign

  • Is my current service size enough, and can you show me the load calculation?
  • Could a lower-power charger or load management device avoid an upgrade?
  • Will the quote include the permit, the inspection and the utility coordination?
  • What is your Texas (TDLR) or Florida (DBPR) license number, and who pulls the permit?
  • Who schedules the power shutoff, and how long will the power be off?
  • What happens if the inspection fails, and who pays for the re-inspection?
  • Does the quote say which code edition (2026 NEC or 2023 NEC) applies?

This page is general information, not legal or engineering advice. Your electrician and building department decide what your house needs.

How do I read my panel and meter before I call anyone?

You can learn a lot in ten minutes with the panel door open and a flashlight. This does not replace an electrician's load calculation, but it helps you ask better questions and spot a quote that does not match your house.

  1. Find the main breaker. It is usually the largest breaker, at the top or bottom of the panel. The number printed on its handle is the main rating in amps. Common residential ratings run from 100 amps to 200 amps, and older homes may be lower.
  2. Read the panel label. The inside of the door or the side of the enclosure usually shows the maximum rating, the manufacturer's name and a list of approved breaker types. Breakers must match the panel they sit in.
  3. Count open spaces. Look for blank slots where a breaker could be added. A charger needs a two-pole breaker, which takes two slots side by side. Some panels allow special thin breakers that fit more circuits in the same space, but only where the label permits them.
  4. Note anything that looks wrong. Scorch marks, rust, a hot smell, loose or double-lugged wires, or breakers that trip often are reasons to have a licensed electrician look at the panel before you add a large load.
  5. Photograph the meter and the service mast. Send clear photos with your quote request. They help an electrician see whether the service is overhead or underground and where the meter sits compared with your garage.
  6. Estimate the distance. Measure roughly how far the panel is from where the charger will go. Longer runs raise labor and wire cost and can change the quote more than the panel itself.

Do not remove the panel cover's inner dead-front panel yourself. The wires behind it can stay live even with the main breaker off, because the utility side of the main is still energized. Leave that work to a licensed electrician.

Panel upgrade, subpanel or load management: how do the options compare?

An upgrade is one of several ways to make room for a charger. The right choice depends on how much spare capacity the load calculation finds, how long the wire run is, and what else you plan to add to the house in the next few years.

OptionWhat it doesGood fit whenWatch out for
Do nothing to the panelAdds one two-pole breaker and a new circuitThe load calculation shows enough spare capacity and the panel has open slotsA calculation that was guessed rather than done
Low-power or lower-amp chargerDraws less current so it fits the capacity you haveThe car's daily miles are modest and the panel is tightSlower charging on long trips or after heavy use
Load management or energy management systemLimits or pauses charging when the home is busyThe service is adequate most of the day but peaks at certain timesNeeds listed equipment, inspector acceptance and sometimes utility approval
SubpanelAdds slots by feeding a second panel from the firstThe main service has capacity but the panel has no roomCapacity is shared, so a subpanel does not create amps that the main service lacks
Panel replacementSwaps the panel for a newer or larger one on the same service sizeThe old panel is worn, full or no longer supportedDoes not raise the service size by itself
Service upgradeRaises the amps the home receives from the utilityThe calculation shows the home needs more capacity than it hasNeeds utility coordination, a permit and an inspection, and may take longer

The key point is the difference between slots and amps. A subpanel or a new panel can fix a shortage of slots. Only a service upgrade, or a control system that limits the load, fixes a shortage of amps. Ask your electrician which problem your house actually has, and ask to see the calculation that shows it.

What should I plan for beyond the first charger?

A service upgrade is usually a once-per-house decision, so it is worth thinking past this one charger. Several common projects add large loads, and they all draw from the same service.

  • A second EV. Two chargers on one service can be managed with a load management device so they share capacity, or each can have its own circuit if the service allows it.
  • Air conditioning. In Texas and Florida, cooling is often the largest load in the house in summer. If you replace or add an air conditioner, tell your electrician, because it changes the calculation.
  • Heat pump water heaters, electric ranges and induction cooktops. These are all efficient, and all add to the connected load.
  • A pool pump or pool heater. These are common in both states and can be large loads.
  • Rooftop solar or a home battery. These change how the service is configured and may need their own permits and utility approval. See solar and EV charging and vehicle-to-home charging.

If you expect several of these within a few years, ask the electrician whether it makes sense to size the service for them now, since opening the wall and coordinating with the utility twice is usually more disruptive than doing it once. If you expect none of them, a smaller fix may be enough. Either way, get the reasoning in writing.

What do people commonly get wrong about panel upgrades?

These misunderstandings come up often, and each one can lead to paying for work you do not need or skipping work you do.

  • "My panel is full, so I need a bigger service." A full panel may only need a subpanel, tandem-capable breakers where the label allows them, or a load management device. Fullness of slots is not the same as lack of amps.
  • "A bigger main breaker means more capacity." Swapping the main breaker for a larger one does not change the wire, the meter or the utility's equipment. The main breaker must match what the service and the panel are rated to carry. Only a licensed electrician should decide this.
  • "The charger's label amps are the only number that matters." Continuous loads such as EV charging are treated with extra margin in the code, which is why a circuit is sized above the charger's rated current. See wire size and breaker rules.
  • "The utility will always approve a bigger service quickly." Utilities have their own application steps and scheduling. In storm season, crews may be busy with restoration. Ask the utility for current timelines rather than relying on a contractor's guess.
  • "A panel replacement does not need a permit." In Texas cities and Florida jurisdictions, panel and service work normally needs an electrical permit and an inspection. See the Texas permit guide and the Florida permit guide.
  • "I can skip the inspection if the charger works." A charger that works can still be unsafe. The inspection checks connections, grounding, labeling and breaker sizing that you cannot see from the outside, and your insurer may ask for proof it passed.

How long does a service upgrade usually take, and what can delay it?

We did not find a single published timeline that applies across Texas and Florida utilities, and we will not invent one. What we can describe are the steps that create waiting time, so you can ask about each one.

  1. Quotes and the load calculation. Electricians need to visit, photograph the panel and run the numbers. Busy seasons stretch this out.
  2. Permit review. Each city or county sets its own review speed. See your city's page, such as those for Houston, Miami, Tampa and the other cities listed in our guides.
  3. Utility coordination. A service upgrade often needs the utility to disconnect and reconnect power, inspect a new meter base or release a meter. Ask the electrician who schedules this and whether the utility needs a passed inspection first.
  4. Equipment availability. Panels, meter bases and breakers may be on back order at times, and that can stretch the schedule.
  5. Inspection scheduling. A failed inspection adds a correction and a second visit.
  6. Weather. Heavy rain, heat or a hurricane watch can push outdoor work, and a declared storm can pause non-emergency work in affected areas.

Ask your electrician for a written schedule with the steps above, who is responsible for each, and what happens if the utility date slips. A good plan states what the homeowner must do, such as removing items near the meter or granting access, so there are no surprises on the day.

How to choose a provider

  • Read the main breaker rating on your panel (do not open the cover).
  • Count open double-pole slots.
  • Ask your electrician for a written load calculation.
  • Ask whether a lower-power charger or load management device avoids an upgrade.
  • Verify the electrician's TDLR (Texas) or DBPR (Florida) license.
  • Get at least two written quotes that separate charger, panel or service work and permit fees.
  • Confirm who pulls the permit and which code edition applies.
  • Call the utility early and ask about shutoff and reconnect scheduling.
  • Confirm who notifies the utility after the inspection passes.
  • Plan for a power outage on the day of the work.
  • Keep the permit, final inspection record and load calculation for your files.
  • Ask your homeowners insurer if a new service changes anything on your policy.

Related home ev charger installation guides

Home EV charger installation by state and city

Questions people ask

Does an EV charger need a service upgrade?

Not always. EPA says a home with 200 amps and two open double-pole slots likely has capacity, and 100 amp service is often enough depending on other loads. A load calculation by a licensed electrician decides it. Homes with 60 amp service, a full panel or several large electric appliances are more likely to need an upgrade or a load management device.

What is the difference between a panel upgrade and a service upgrade?

A panel upgrade replaces or adds the breaker box inside the home. A service upgrade increases the size of the connection from the utility, such as 100 amps to 200 amps, and usually includes a new meter base, new service wire and a new panel. A service upgrade needs the utility to disconnect and reconnect power.

Can I add a subpanel in my garage for the charger?

Often yes. A subpanel adds breaker slots and shortens the wire run to the charger. It does not add total power to the house, so the main service must still have enough capacity. It needs a permit and inspection like other electrical work.

Does the utility have to turn off my power?

For a service upgrade, usually yes. The utility typically disconnects power so the meter base and service wire can be replaced, then reconnects after the inspection. We could not load a Texas or Florida utility procedure, so call your utility to learn how it schedules this.

Who pays for the meter or service drop work?

It depends on who owns the equipment and on the utility's tariff. In Texas, the delivery utility owns the poles, wires and meters, and the homeowner owns the meter base and the equipment on the house side. Ask the utility in writing what it charges, if anything, before work starts.

Does a panel upgrade need a separate inspection?

Yes in most places. The permit for the panel or service work is inspected by the city or county. The EV charger circuit may be included in the same permit or inspected separately. Ask the building department how it handles combined jobs.

How long does a service upgrade take?

We could not find a published Texas or Florida timeline for a house. The work itself is often a day, but the permit, the inspection and the utility visit each add waiting time. Ask the electrician and the utility for dates in writing.

Does the 2026 NEC change panel upgrade rules?

The 2026 NEC moved load calculations into Article 120, counts a charger at 100 percent in the dwelling optional method, and changes some other numbers. Texas uses the 2026 NEC from September 1, 2026. Florida uses the 2023 NEC from December 31, 2026. Your permit date decides the edition.

Is a subpanel cheaper than a main panel replacement?

Often it is, but we could not load a sourced Texas or Florida price for either, so get written quotes. A subpanel only helps if the main service has spare capacity.

How do I find a licensed person for a service upgrade?

In Texas, check the electrician or electrical contractor license on the TDLR website. In Florida, check the contractor on MyFloridaLicense.com. Ask for the license number in writing and confirm the contractor pulls the permit.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration