Florida Owner-Builder Permits: Rules, the Disclosure Statement and the 1-Year Rule
Florida lets owners act as their own contractor on their own home, but the exemption in s. 489.103(7) comes with strict limits on use, supervision, hiring and resale. Here is what the statute and its 12-item disclosure statement require, plus the newer exemptions most guides miss.
Yes, a Florida property owner can be his or her own contractor under s. 489.103(7) when building or improving a one-family or two-family home or farm outbuilding for the owner's own use, or a commercial building the owner uses costing $75,000 or less. The owner must personally supervise all unlicensed work, sign the permit and a 12-item disclosure statement, and treat any unlicensed helpers as employees. Selling or leasing within 1 year after completion creates a presumption the work was done for sale, which violates the exemption.
Key facts
- Florida's owner-builder exemption is s. 489.103(7); electrical work has a parallel owner exemption in s. 489.503(6).
- Owner-builders may build or improve a commercial building for their own use only if the cost does not exceed $75,000.
- Sale or lease, or an offer to sell or lease, within 1 year after completion creates a legal presumption the work was done for sale or lease.
- The owner must provide direct, onsite supervision and may delegate it only to a licensed contractor within that contractor's license scope.
- Unlicensed workers must be the owner's employees, which brings income tax, FICA and workers' compensation duties.
- Florida workers' compensation covers construction employers with one or more employees (s. 440.02).
- Since the permit-completion exemption in s. 489.103(7)(a)4, an owner can finish a permit a contractor substantially completed without a 1-year occupancy duty.
- After a Governor-declared emergency, owners may re-shingle (shakes, asphalt or fiberglass shingles) their own 1 to 3 family home without a license.
- From July 1, 2026, single-family owners can request a permit exemption for work under $7,500, except in flood hazard areas and for electrical, plumbing, structural, mechanical or gas work.
- In 2025, U.S. owner-built new homes averaged 12.8 months from start to completion versus 10.5 months for contractor-built homes (Census Survey of Construction).
What is a Florida owner-builder permit?
Florida law starts from a simple rule: construction work is supposed to be done by a licensed contractor. Section 489.103 of the Florida Statutes then lists people who are exempt from that rule. Subsection (7) is the owner-builder exemption. It lets a property owner act as his or her own contractor and pull the building permit in his or her own name, without holding a state contractor license.
An owner-builder permit is not a different kind of permit. It is a normal building permit where the owner, not a licensed contractor, is listed as the responsible party. That one change moves every job a general contractor would normally carry onto your shoulders: scheduling inspections, meeting the Florida Building Code, hiring and checking trades, keeping workers safe, and paying everyone.
Electrical work has its own parallel exemption. Section 489.503(6) gives owners a similar right to do electrical work on their own single-family home or duplex, with the same own-use limits and its own disclosure statement. Florida's building code statute ties the two together: s. 553.79(16) says an owner may take on the owner-builder role when closing a permit "in accordance with ss. 489.103(7) and 489.503(6)."
Who it is for
- A homeowner remodeling, adding on to, or building a one-family or two-family home they will live in.
- An owner building or improving a farm outbuilding.
- An owner improving a small commercial building they will occupy, if the cost stays at or under $75,000.
- An owner finishing a job a licensed contractor substantially completed (a newer, separate rule, explained below).
- An owner re-shingling a storm-damaged home after a Governor-declared emergency (also explained below).
It is not for investors, flippers, landlords building rentals, or anyone who plans to sell soon after the work is done.
Who qualifies: the core rules of s. 489.103(7)
The statute's main conditions, read against the 2026 Florida Statutes, are these:
| Rule | What the statute says | What it means in practice |
|---|---|---|
| Type of building | Farm outbuildings, one-family or two-family residences, or commercial buildings costing no more than $75,000 | A triplex or a larger commercial job needs a licensed contractor. |
| Own use | For the owner's occupancy or use and not offered for sale or lease | You cannot build to rent or to sell. |
| 1-year presumption | Proof of sale or lease, or offering for sale or lease, within 1 year after completion creates a presumption the work was done for sale or lease | Listing the house within 12 months of finishing is evidence against you. |
| Supervision | Owner must provide direct, onsite supervision of all work not performed by licensed contractors | You have to be there. You cannot hand supervision to an unlicensed friend or foreman. |
| Delegation | Supervision may be delegated only to a person registered or certified under part I of ch. 489, and only for work within that person's license | A licensed roofer can run the roofing, not the framing. |
| Personal appearance | Owner must personally appear and sign the permit application and meet any local requirements proving understanding of the law | Expect to sign at the counter, or follow your county's verification method. |
| Disclosure statement | Owner signs the statutory disclosure statement before the permit issues; a driver license copy, notarized signature or other accepted verification is required | A 12-item acknowledgment of your duties, covered in the next section. |
The statute also says the term "owners of property" includes the owner of a mobile home on a leased lot. And it does not protect anyone who works for you or contracts with you and "acts in the capacity of a contractor." If you hire an unlicensed person who actually runs the job, that person is still unlicensed contracting, and you may be pulled into it.
The owner-builder disclosure statement, item by item
Section 489.103(7)(c) requires the local permitting agency to hand you a disclosure statement "in substantially the following form." It has 12 numbered items. Most counties use the statutory text with their own header. Here is what each item commits you to, in plain English.
- License law. State law requires a licensed contractor, and you are using an exemption to act as your own.
- Who signs permits. Owners only sign permits when they are responsible for the work and are not hiring a licensed contractor to take that responsibility.
- You are the responsible party of record. You can lower your financial risk by hiring a licensed contractor and putting the permit in that contractor's name. Licensed contractors must show license numbers on permits and contracts.
- What you may build. A one-family or two-family home or a farm outbuilding, or a commercial building up to $75,000, for your own use. Selling or leasing within 1 year raises the presumption you built it for sale or lease.
- Supervision. You must provide direct, onsite supervision.
- No unlicensed contractor. You may not hire an unlicensed person to act as your contractor or to supervise workers, and you must make sure the people you hire hold the licenses state and local law require.
- The classic scam warning. Unlicensed people often ask owners to pull an owner-builder permit. You may be liable for injuries to unlicensed workers, and your homeowner's insurance may not cover them.
- Employer duties. Unlicensed workers must work under your supervision and be your employees. That means withholding federal income tax and FICA (Social Security and Medicare) and providing workers' compensation.
- Follow every law. You will follow the laws for owner-builders and employers, and the building codes, ordinances and zoning rules.
- Where to learn more. The IRS, the U.S. Small Business Administration, the Florida Department of Financial Services, the Florida Department of Revenue, and the Construction Industry Licensing Board.
- Consent. You agree the permit is in your name and you are legally and financially responsible for the work at the listed address.
- Updates. You will tell the permitting agency right away about any changes to the information you gave.
The statement ends with a warning that matters more than any single item: if you hire someone without a license, the Construction Industry Licensing Board and the Department of Business and Professional Regulation (DBPR) "may be unable to assist you" with your loss, and "your only remedy against an unlicensed contractor may be in civil court."
Read it slowly. If any item describes a situation you are not ready to handle, that is your sign to hire a licensed contractor instead.
Can I sell or rent the house afterward?
Yes, eventually. The exemption does not ban a sale forever. It says that if you sell, lease, or even offer the property for sale or lease within 1 year after completion, the law presumes you built it for sale or lease. A presumption is a legal starting point. You can try to rebut it with facts (a job transfer, a death in the family, a divorce), but the burden shifts toward you.
What happens if the exemption is violated
- Under s. 489.103(7)(c), the local permitting agency "shall withhold final approval, revoke the permit, or pursue any action or remedy for unlicensed activity" against the owner and anyone doing licensed work under the permit.
- Acting as a contractor without a license is a first-degree misdemeanor for a first offense under s. 489.127. A repeat offense, or one committed during a Governor-declared state of emergency, is a third-degree felony.
- Local code enforcement can cite unlicensed contracting. Citation penalties may not exceed $2,000, and a local board or special magistrate may impose up to $2,500 per day per violation (s. 489.127).
- No final approval means no certificate of occupancy or completion, which can stall a sale, new insurance coverage, or a move-in.
Renting a room or a guest unit
The statute's words are "not offered for sale or lease." Building a duplex where you live in one side and rent the other, or adding a unit you plan to rent, sits uneasily with that language. Ask the building department how it reads your plan before you apply, and get the answer in writing. If renting is the goal, the safer path is a licensed contractor.
Investors and flippers
An owner-builder permit is not a tool for flips. Flipping is building or improving for sale, which is exactly what the exemption excludes. Federal lead rules also change for flippers: EPA says its Renovation, Repair and Painting (RRP) rule generally does not apply to homeowners working on their own pre-1978 home, but it does apply if they rent out all or part of it or flip houses for profit.
Can I hire helpers or subcontractors?
Yes, but there are only two legal ways to bring other people onto an owner-builder job.
| Who | How they work for you | Your duties |
|---|---|---|
| Licensed contractors (electrician, plumber, roofer, HVAC and so on) | Hired as independent contractors under their own license | Verify the license and its scope on DBPR's license search, confirm workers' compensation coverage, have them pull any trade permit their license requires |
| Unlicensed workers (laborers, a handy friend, a framing crew without a license) | Your employees, working under your direct supervision | Withhold federal income tax and FICA, provide workers' compensation, follow employer laws |
What you may not do is hire an unlicensed person or crew as an independent "contractor" who runs the work. The disclosure statement says this plainly in items 6 and 8.
Workers' compensation for owner-builders
Florida's workers' compensation law, ch. 440, covers private construction employment "in which one or more employees are employed by the same employer" (s. 440.02). Outside construction, the threshold is four or more employees. So on an owner-builder job, one paid helper can be enough to make you a construction employer who needs coverage. Talk to an insurance agent licensed in Florida and the Department of Financial Services, Division of Workers' Compensation, before anyone starts work.
When you hire a licensed contractor, check that contractor's coverage. DBPR's construction industry page points to the Division of Workers' Compensation's Construction Policy Tracking Database, which shows the coverage status of contractors and can send automatic notices if that status changes.
Can I let a licensed general contractor supervise for me?
Only within that person's license. Section 489.103(7)(b) says you may not delegate supervision "unless that person is registered or certified under this part and the work being performed is within the scope of that person's license." If you want a licensed general contractor to run the whole job, the cleaner choice is to let that contractor pull the permit. Then the contractor, not you, is the responsible party of record.
Can an owner-builder do electrical and plumbing work?
Under the statute, generally yes, if it is your own home. The owner-builder exemption in s. 489.103(7) covers work regulated by part I of ch. 489, which includes plumbing, mechanical, roofing and the other Division II trades. Electrical contracting is regulated by part II of ch. 489, and its owner exemption is s. 489.503(6). That exemption covers an owner "making application for permit, supervising, and doing the work" on a single-family home or duplex for his or her own use, with the same personal-appearance rule and a separate disclosure that begins: "State law requires electrical contracting to be done by licensed electrical contractors."
Three practical limits apply:
- Local requirements. The statute lets local agencies require proof that you understand your obligations. Some building departments add steps such as an interview or a written test before issuing a trade permit to a homeowner. Ask before you plan your schedule.
- Code compliance. Owner work is inspected to the same Florida Building Code as a licensed contractor's work. Many failed inspections on owner-builder jobs are electrical or plumbing.
- Utility and gas work. Service changes, meter work and gas lines often involve the utility's own rules and a licensed trade. Check before you buy materials.
Note that the new $7,500 permit exemption (below) never applies to electrical, plumbing, structural, mechanical or gas work, so those trades still need a permit even on small jobs.
Newer exemptions most guides miss
1. Finishing a permit your contractor substantially completed
Section 489.103(7)(a)4 lets an owner complete the requirements of a building permit when the contractor listed on the permit substantially completed the project, as determined by the local permitting agency. It covers a one-family or two-family home, a townhome, an accessory structure of those homes, or an individual condominium or cooperative unit.
- You must get approval from the local permitting agency first, and the agency must decide the contractor substantially completed the work.
- An owner using this path is not required to occupy the home or unit for at least 1 year afterward. The disclosure statement's item 4 makes the same carve-out from the sale-or-lease presumption.
- Section 553.79(16) confirms an owner may take on the owner-builder role when closing a permit.
This is the fix when a contractor walks off near the end, retires or dies, and only the final inspections and paperwork remain. If the job is far from done, the agency is unlikely to call it substantially complete. Then you either hire a new licensed contractor to take over the permit or apply as a regular owner-builder for your own home. Changing contractors also has lien-law steps: under s. 713.13, the owner must record a new notice of commencement or a notice of recommencement. See our guide to the Florida notice of commencement and what to do when a contractor abandons a job.
2. Re-shingling after a declared emergency
Section 489.103(7)(a)2 lets an owner repair or replace wood shakes or asphalt or fiberglass shingles on a one-family, two-family or three-family residence without a license when:
- the home is for the owner's occupancy or use, or a tenant of the owner;
- it is not offered for sale within 1 year after the work is completed; and
- the damage came from natural causes during an event the Governor declared a state of emergency by executive order.
Notice what is not covered: tile, metal, flat roofs and structural roof repairs. And the exemption is from licensing, not from the building code. Roof replacement still needs to meet code and pass inspection. After a storm, also watch for roofers who ask you to pull an owner-builder permit for them. That is the scam described in item 7 of the disclosure. Our post-storm hiring guide covers Florida's roof-contract cancellation rights under s. 489.147.
3. Rooftop solar in participating jurisdictions
Section 489.103(7)(a)3 covers installing, uninstalling or replacing solar panels on 1 to 3 family homes where the local government participated in a U.S. Department of Energy SunShot Initiative Rooftop Solar Challenge grant. Even then, a licensed electrical contractor must do the wiring and interconnection. Ask your building department whether this applies where you live; most owners will need a licensed solar or electrical contractor.
Do I even need a permit? The 2026 changes
Two Florida changes that took effect July 1, 2026 (Ch. 2026-63, CS/CS/HB 803) affect small owner projects:
- $7,500 permit exemption. Under s. 553.79(1)(g), local governments must exempt an owner of a single-family dwelling, or the owner's contractor, from getting a building permit for work valued under $7,500. It does not apply in flood hazard areas, and it does not apply to any electrical, plumbing, structural, mechanical or gas work. You must submit a written exemption request with a copy of the contract or other documents showing the nature and value of the work. Splitting one project into smaller ones to dodge the limit is not allowed. The local government has no legal duty to you for exempted work.
- Faster decisions on small permits. Under s. 553.792, local governments must decide complete applications within 5 business days for listed permit types (including structural, electrical, plumbing, mechanical and roofing) on existing single-family homes when the work is under $15,000.
The minor-work licensing exemption in s. 489.103(9) is different. It covers casual, minor or inconsequential work under $2,500 in aggregate, and it is about who may do the work, not whether a permit is needed. It does not apply when a job is split to evade the limit or is part of a larger project.
For a full rundown, read Do I need a permit in Florida?
How to apply for an owner-builder permit in Florida
- Confirm you qualify. Own the property, plan to use it yourself, and stay inside the building types and the $75,000 commercial cap.
- Call or visit the building department. Ask for its owner-builder packet. Ask whether it requires an appointment, an in-person signing, a notarized signature, a test or an interview, and which trades you may do yourself.
- Prepare plans. Many projects need drawings, and some (additions, structural changes, new homes) need plans sealed by a Florida-licensed architect or engineer. Florida's product approval and wind-load rules are strict, especially in Miami-Dade and Broward, which are in the High-Velocity Hurricane Zone under the Florida Building Code.
- Sign the application and disclosure statement in person (or by the method your agency accepts), with your driver license or other verification.
- Record the notice of commencement if required. For a direct contract over $5,000, a copy of the recorded notice must be filed with the permitting agency before the first inspection (s. 713.135), and Florida permit cards warn that failing to record it may result in paying twice.
- Consider a private provider. Under s. 553.791, an owner may hire a private provider (a licensed engineer, architect or qualified inspector) for plans review or inspections, pay that provider directly, and get a reduced local permit fee. Notice to the building official is due at permit application or by 2 p.m., 2 business days before the first scheduled inspection.
- Schedule and pass every inspection. You, not a contractor, call in inspections and fix failures. See building inspections explained.
- Close the permit. Get final approval and keep the closed-permit record. Open permits can delay a future sale or insurance.
A single-family building permit in Florida expires 1 year after issuance or on the effective date of the next Florida Building Code edition, whichever is later, and local governments may extend it (s. 553.79). Owner-built homes take longer than contractor-built ones, so plan for extensions.
Local variations: Miami, Tampa, Orlando, Jacksonville
The exemption is state law, but each building department runs its own process. The statute lets local agencies require proof that you understand the law, so expect differences in paperwork, appointments and trade rules. Common local differences include:
- whether the owner must sign in person or may use a notarized signature;
- whether a homeowner trade permit (electrical or plumbing) requires a test or interview;
- what plans must be sealed by a design professional;
- whether the jurisdiction is in a flood hazard area, which removes the $7,500 permit exemption;
- hurricane product approval and HVHZ rules in Miami-Dade and Broward.
Before you apply, check the building department for your city or county. Our city pages collect the local permit offices and rules: Miami, Tampa, Orlando and Jacksonville. If your property is in a homeowners association or condo, you will usually need association approval too; see HOA architectural approval and renovating a Florida condo unit.
Insurance, risk and time: is owner-building worth it?
Insurance
Item 7 of the disclosure warns that your homeowner's insurance may not cover injuries to workers on your property. Policies also differ on coverage for a home under heavy construction, theft of materials, and damage during a remodel. Before you start, ask your insurer in writing how the policy treats an owner-managed construction project, whether you need a builder's risk policy for a new build or addition, and whether you need general liability coverage. Get answers before the first delivery.
Time
The U.S. Census Bureau's Survey of Construction reports that in 2025 the average new single-family home took 10.5 months from start to completion when built by a contractor and 12.8 months when built by the owner. In the South region, the 2025 averages were 9.0 months (contractor-built) and 10.8 months (owner-built). Those are national and regional averages for new homes, not remodels, but they show that owner-builders usually finish later.
Legal protection
When a licensed contractor holds the permit, Florida gives you tools: DBPR discipline, the Florida Homeowners' Construction Recovery Fund for qualifying losses, the deposit rules of s. 489.126, and lien protections. As your own contractor, you take on the responsibility, and if you hire unlicensed people the disclosure statement warns your only remedy may be civil court. On the other hand, a contract by an unlicensed contractor is unenforceable by that contractor and gives no lien rights (s. 489.128). Read more about the recovery fund and unlicensed contractors.
Quick decision table
| Your situation | Owner-builder permit? |
|---|---|
| Remodeling the home you live in and you can be on site daily | Possible fit |
| Building your own primary home with licensed trades | Possible fit, with a long schedule |
| Fixing up a house to sell or rent | No. Hire a licensed contractor. |
| A contractor wants you to pull the permit "to save time" | No. This is the warning in item 7. |
| Contractor finished almost everything and disappeared | Ask about the permit-completion exemption |
| Commercial space you use, under $75,000 | Possible fit |
How to choose a provider
- Confirm the building type, own-use and $75,000 commercial limits fit your project.
- Ask your building department for its owner-builder packet and local requirements.
- Read all 12 items of the disclosure statement before you sign.
- Decide which trades you will do yourself and which licensed contractors you will hire.
- Verify every contractor's license and scope on DBPR's license search.
- Check each contractor's workers' compensation status.
- Set up payroll, tax withholding and workers' compensation before any paid helper starts.
- Ask your insurer in writing about coverage during construction and for workers.
- Record and post the notice of commencement when required, and file it before the first inspection.
- Schedule every inspection and do not cover work before it passes.
- Track the permit expiration date and request extensions early.
- Close the permit and keep the final approval for your records.
- Do not list the property for sale or rent within 1 year of completion.
Related general and residential contractors guides
- Do I Need a Building Permit in Florida? What Needs One, the New $7,500 Exemption, and How Permits Work in Miami-Dade, Tampa, Orlando and Jacksonville
- What Is a Florida Notice of Commencement, When Do You Need One, and How Long Does It Last?
- Hired an Unlicensed Contractor? Risks, Rights and What to Do in Florida and Texas
- Building Inspections Explained: What Inspectors Check at Each Stage
- Building or Remodeling Your Own Home in Texas as an Owner-Builder
- Contractor Abandoned the Job or Stopped Showing Up: What Do You Do in Texas and Florida?
- Which Florida Contractor License Does Your Project Need? General vs. Building vs. Residential vs. Specialty
- How Do You Hire a Contractor After a Hurricane, Flood or Hailstorm in Florida or Texas?
General and residential contractors by state and city
Questions people ask
Can I be my own contractor in Florida?
Yes, in limited cases. Section 489.103(7) lets an owner act as his or her own contractor on a one-family or two-family home or farm outbuilding for the owner's own use, or on a commercial building the owner uses if the cost is $75,000 or less. You must personally supervise the work, sign the permit application in person or by the local agency's accepted method, and sign the statutory disclosure statement. The property may not be built for sale or lease.
Can I sell my house after an owner-builder permit in Florida?
Yes, but timing matters. If you sell, lease, or offer the property for sale or lease within 1 year after the work is completed, Florida law presumes you built it for sale or lease, which violates the exemption. The local permitting agency can then withhold final approval, revoke the permit or pursue unlicensed-activity remedies. Owners who used the permit-completion exemption, where a contractor substantially completed the job, are not required to occupy the home for a year.
Do I need workers' comp as an owner-builder in Florida?
If you pay anyone who is not a licensed contractor to work on the job, that person must be your employee, and the disclosure statement says you must provide workers' compensation and withhold income tax and FICA. Florida's workers' compensation law covers construction employment with one or more employees. Confirm your duties with the Florida Division of Workers' Compensation and a licensed insurance agent before work starts.
Can an owner-builder pull a permit for a rental property?
No. The exemption covers buildings for the owner's own occupancy or use and "not offered for sale or lease." A rental house, a flip, or a spec home needs a licensed contractor. If you plan to live in part of a duplex and rent the other part, ask the building department for its reading in writing before applying, or use a licensed contractor to avoid the risk.
Can I finish a permit my contractor abandoned?
Sometimes. Since the permit-completion exemption in s. 489.103(7)(a)4, an owner may complete a permit for a home, townhome, accessory structure, or condo or co-op unit if the local permitting agency approves and decides the listed contractor substantially completed the project. If the job is not substantially complete, you would need a new licensed contractor or a regular owner-builder permit for your own home, plus a new notice of commencement or recommencement.
Can I hire an unlicensed handyman on my owner-builder job?
Only as your employee, working under your direct supervision, with tax withholding and workers' compensation. You may not hire an unlicensed person to act as your contractor or to supervise others. Small jobs under $2,500 that are truly casual or minor fall under a separate exemption in s. 489.103(9), but it does not apply when the work is part of a larger project or split to avoid the limit.
Does homeowners insurance cover an owner-builder project?
Not reliably. The statutory disclosure warns that your homeowner's insurance may not cover injuries to unlicensed workers on your property. Coverage for theft, fire and damage during construction also varies by policy. Ask your insurer in writing before work starts, and ask whether you need a builder's risk policy, general liability coverage or workers' compensation for the project.
Who do I call with owner-builder questions?
Start with your local building department, which issues the permit and the disclosure statement. For licensing questions and to check a contractor's license, use DBPR's online license search or call DBPR's customer contact center at 850-487-1395. For employer questions, the disclosure lists the IRS, the U.S. Small Business Administration, the Florida Department of Financial Services and the Florida Department of Revenue.
Sources
- Florida Statutes s. 489.103 (2026), Exemptions
- Florida Statutes s. 489.503 (2026), Electrical contracting exemptions
- Florida Statutes s. 489.127 (2026), Prohibitions; penalties
- Florida Statutes s. 489.128 (2026), Contracts entered into by unlicensed contractors unenforceable
- Florida Statutes s. 440.02 (2026), Workers' compensation definitions
- Florida Statutes s. 553.79 (2026), Permits; applications; issuance; inspections
- Florida Statutes s. 553.792 (2026), Building permit application to local government
- Florida Statutes s. 553.791 (2026), Alternative plans review and inspection
- Florida Statutes s. 713.13 (2026), Notice of commencement
- Florida Statutes s. 713.135 (2026), Notice of commencement and applicability of lien
- Laws of Florida Ch. 2026-63 (CS/CS/HB 803)
- Florida DBPR, Construction Industry Licensing Board
- U.S. EPA, Lead Renovation, Repair and Painting Program
- U.S. Census Bureau, Survey of Construction: Average Length of Time from Start to Completion (annual, through 2025)
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.