Contractor Abandoned the Job or Stopped Showing Up: What Do You Do in Texas and Florida?
When a contractor walks off with your money and leaves the job half done, the order of your next moves matters. This guide covers documentation, demand letters, the Florida 90-day abandonment rule, lien deadlines that start at abandonment, permits, the Recovery Fund and criminal reports in both states.
If your contractor stops showing up, document the site and every payment, then send a written demand by certified mail, return receipt requested, giving a short deadline to return or refund. In Florida, 90 days without work while holding more money than the work is worth is prima facie evidence of a violation under s. 489.126(3), and a refund demand starts a 30-day clock. In Texas, abandonment starts the contractor's lien-filing deadline. Then report to the state or police, switch the permit and hire a replacement.
Key facts
- Florida s. 489.126(3) bars a contractor who holds residential project money in excess of the work performed from failing to perform any work for 90 days (or another period set in the contract) without just cause or proper notice of termination.
- Under s. 489.126, the owner's written demand to perform or refund must go by certified mail, return receipt requested, to the contractor's address in the contract; if the contractor does not act within 30 days, a lack of just cause may be inferred.
- Misusing residential project money under s. 489.126 is a crime in Florida, ranging from a first-degree misdemeanor under $1,000 to a first-degree felony at $200,000 or more, and it applies whether or not the person is licensed.
- Florida's licensing board may presume a project abandoned after 90 days without work or proper notice (s. 489.129(1)(j)) and can fine a licensee up to $10,000 per violation.
- A Texas original contractor on a residential project must file its lien affidavit by the 15th day of the third month after the month its work was completed, terminated or abandoned (Prop. Code s. 53.052).
- Texas's Residential Construction Liability Act does not apply to claims from a contractor's wrongful abandonment of a project before completion (Prop. Code s. 27.002(d)).
- Texas treats construction payments as trust funds, and since September 1, 2025 (S.B. 841) a residential property owner is a beneficiary; misapplying $500 or more is a Class A misdemeanor, or a third-degree felony with intent to defraud (Prop. Code ch. 162).
- To change contractors on a Florida job, the owner must record a new notice of commencement or a notice of recommencement (s. 713.13).
- For Florida contracts signed on or after July 1, 2024, the Homeowners' Construction Recovery Fund can pay up to $100,000 per Division I claim and $30,000 per Division II claim (s. 489.143).
First, is the job actually abandoned?
Not every quiet week is abandonment. Crews wait on inspections, back-ordered windows, engineering letters and weather. Abandonment means the contractor has stopped performing and does not intend to come back, or has gone silent long enough that the law treats it that way.
Signs that you are past an ordinary delay:
- No one has worked on site for weeks and nothing explains it (no pending inspection, no documented material delay).
- Calls, texts and emails go unanswered, or you get repeated promises with no dates.
- Equipment, dumpsters or portable toilets were removed.
- Subcontractors or suppliers start calling you, or you receive a notice saying someone has not been paid.
- The contractor asks for more money before returning, outside the payment schedule.
- The permit has gone inactive or is near expiration because no inspections were called.
Florida: the 90-day rule
Florida has a specific test. Under s. 489.126(3), a contractor who has received money for residential work in excess of the value of the work performed may not fail or refuse to perform any work for any 90-day period, or for a different period you both agreed on in the contract. If the contractor stops for 90 days without just cause, and the stop was not caused by your own termination or material breach, that is prima facie evidence (enough to prove the point unless rebutted) that the contractor holds more of your money than the work is worth. The licensing statute uses the same yardstick: under s. 489.129(1)(j), a project may be presumed abandoned after 90 days if the contractor terminates without just cause or without proper notice to the owner, or fails to perform work without just cause for 90 consecutive days.
The 90 days is not a waiting period you must sit through before acting. It is when a legal presumption kicks in. You can send a demand, talk to a lawyer and plan a replacement well before day 90. But if you want the strongest version of the Florida statutory case, count the days and keep proof of them.
Texas: no fixed day count
Texas does not set a statewide number of days. Whether a contractor abandoned the job is a question of fact under your contract and general contract law. Read your contract for a clause on delays, a notice-to-cure period, or a right to terminate after a set number of days without work. That clause is usually your clock. Texas law does attach consequences to the date work is "terminated or abandoned": it starts the contractor's own lien deadline under Prop. Code s. 53.052 and the 30-day retainage clock under s. 53.103, both discussed below.
How do I document an abandoned job?
Everything that happens next, from a demand letter to a Recovery Fund claim to a police report, runs on evidence. Build the file before you touch anything on site.
- Photograph and video the whole site the day you decide the contractor is gone. Shoot wide shots of each room, then close-ups of unfinished work, materials left on site and any damage. Turn on date stamps or keep the original files with their metadata.
- Make a timeline. List the contract date, start date, each payment, the last day anyone worked and every contact attempt (date, method, what was said).
- Gather the money trail. Contract, change orders, invoices, receipts, canceled checks, bank and card statements, and any payment app records.
- Save every message. Screenshot texts with the phone number visible. Export emails. Write a short note after each phone call.
- Pull the permit record from the city or county portal: permit number, status, inspections passed and failed, and who is listed as contractor.
- Look up the license. In Florida use the DBPR license search; note the license number, status and the address on file, because the statute tells you to mail your demand there if the contract has no address. In Texas, check city registration (Dallas and Austin register general contractors, San Antonio registers residential contractors, and Houston registers trade contractors but not general contractors) and any state trade licenses.
- Inventory materials on site, who paid for them, and whether they are installed or loose. Do not throw away or use the contractor's tools or equipment; list them and ask in writing that they be picked up.
- Collect lien paperwork. In Florida, gather any Notices to Owner you received and your recorded Notice of Commencement. In Texas, gather any notices of claim from subcontractors or suppliers, the subcontractor list and the disbursement statements the contractor was required to give you.
- Get an independent assessment. A different contractor, home inspector or engineer can write down what was completed, what it is worth, and what is defective. This is the number you will compare to what you paid.
The key figure in both states is simple: what you paid minus the fair value of work actually done. If you paid $48,000 on a $90,000 job and an estimator values the completed work at $27,000, the contractor is holding about $21,000 in excess of work performed. That gap drives the Florida criminal thresholds, the Recovery Fund claim and any lawsuit.
Should I send a demand letter, and what should it say?
Yes. A written demand is the step that turns a vague dispute into a record, and in Florida it is written into the statute.
Florida demand under s. 489.126
For residential work, the owner's demand must be a letter that demands the contractor perform the work or refund the money received in excess of the value of work performed. It must be sent by certified mail, return receipt requested, to the address listed in the contract. If the contract has no address for the contractor, or there is no written contract, mail it to the address the contractor lists with DBPR for licensing or with the local licensing board. If the contractor fails to perform or refund within 30 days after receiving the demand, the law allows an inference that the contractor had no just cause, and in a criminal case an inference of intent to deprive you of the money. The statute also says the contractor's claim that it meant to pay you back later is not a defense.
There is a parallel rule for jobs that never started. A contractor who takes more than 10% of the contract price as an initial payment must apply for permits within 30 days and start work within 90 days after permits issue, unless there is just cause or you agreed in writing to longer periods. The same certified-mail demand process applies (s. 489.126(2)).
Texas demand letters
Texas has no single abandonment demand statute, but several laws reward a written demand:
- DTPA notice. If you may sue under the Deceptive Trade Practices Act, you must give written notice at least 60 days before filing, describing your specific complaint and the economic damages, mental anguish damages and expenses, including attorney's fees, you claim (Bus. & Com. Code s. 17.505).
- Attorney's fees on a contract claim. To recover fees under Civ. Prac. & Rem. Code ch. 38, the claim must be presented to the other side and not paid within 30 days (s. 38.002).
- RCLA usually does not apply. The Residential Construction Liability Act's 60-day pre-suit notice covers construction defects, but the Act expressly does not apply to damages from a contractor's wrongful abandonment of a project before completion (Prop. Code s. 27.002(d)). If your claim mixes abandonment with defective work already done, a lawyer may still send an RCLA notice for the defect portion to be safe.
Sample wording (adapt it; this is not legal advice)
"Re: Contract dated [date] for work at [address], Permit No. [number]. No work has been performed since [date]. As of today you have been paid $[amount]. Based on [inspection or estimate], the work performed is worth approximately $[amount]. Demand is made that you either (1) resume work on or before [date] and complete it per the contract, or (2) refund $[excess amount], the money received in excess of the value of the work performed. [Florida: This demand is made under section 489.126, Florida Statutes.] If you do neither by [date], I will treat the contract as terminated for cause, hire another contractor to complete the work, and pursue all available remedies, including complaints to the licensing authority and law enforcement."
Keep the tone factual. Do not threaten criminal charges to get paid; state that you will report to the proper agencies. Keep the green return receipt card or the USPS tracking record with your file.
Notice to cure, then termination for cause
Many written contracts require a notice to cure before you can terminate: a written notice that names the default and gives the contractor a set number of days (often 7 to 10) to fix it. If your contract has one, follow it exactly, including the delivery method it requires. Skipping it can turn your termination into a breach by you.
| Step | What it does | Typical content |
|---|---|---|
| 1. Notice of default / notice to cure | Puts the contractor on notice and starts the contract's cure period | Contract date, the default (no work since a date), the cure required (crew back on site, schedule), the deadline, the contract clause you rely on |
| 2. Statutory demand (FL s. 489.126) | Starts the 30-day statutory clock | Demand to perform or refund the excess, certified mail, return receipt |
| 3. Notice of termination for cause | Ends the contractor's right to keep working | Effective date, reason, demand for refund and documents, instructions to remove equipment, request for lien waivers and a list of unpaid subs |
You can combine steps 1 and 2 in one letter in Florida. If the contract is silent on termination, a lawyer can tell you whether the contractor's conduct is a material breach that lets you end the contract anyway. For a fuller walk-through of termination, see how to fire a contractor.
Termination for cause means you end the contract because the contractor breached it. It usually lets you recover the extra cost to finish with someone else. Termination for convenience means you end it without fault, if the contract allows it, and you typically owe for work done plus certain costs. With an abandoned job you want the termination to be clearly for cause and documented that way.
Can the old contractor still file a lien after abandoning the job?
Possibly, which is why the lien rules belong in your plan from day one. A contractor who walks away may still claim it is owed for work it did, and unpaid subcontractors and suppliers may have their own rights even if you paid the contractor.
Texas
- Original contractor deadline. On a residential project, the original contractor must file its lien affidavit with the county clerk no later than the 15th day of the third month after the month its work was completed, terminated or abandoned (s. 53.052(a)(2)). If the contractor walked off in March, its deadline is June 15. On non-residential projects it is the fourth month.
- Subcontractors and suppliers on residential projects file by the 15th day of the third month after the month they last provided labor or materials (s. 53.052(c)), and must have sent you a notice of claim by the 15th day of the second month.
- Retainage. Texas owners must keep 10% of the contract price, or of the value of work done, during the work and for 30 days after completion (s. 53.101). A claimant's lien on those reserved funds requires a lien affidavit no later than the 30th day after the earliest of completion, termination of the original contract, or abandonment by the original contractor (s. 53.103). If you did not retain the 10%, complying claimants have a lien at least up to the amount that should have been reserved (s. 53.105).
- Homestead rules. For a lien on a homestead, the contract must have been signed before work began and filed with the county clerk, and both spouses must have signed if the owner is married. A homestead lien affidavit must carry the warning "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN." (Prop. Code ch. 53, Subchapter K).
Florida
- A claim of lien must be recorded no later than 90 days after the lienor's final furnishing of labor, services or materials (s. 713.08). For a contractor that walked off, the last day it furnished work usually starts that clock.
- The contractor must give you a Contractor's Final Payment Affidavit at least 5 days before suing to enforce its lien, and has no lien or right of action against you while it is in default of giving it (s. 713.06).
- Subcontractors and suppliers who served a timely Notice to Owner can lien your property for unpaid amounts. Total liens under a direct contract may not exceed the direct contract price, but paying your contractor in full does not by itself protect you from subs who served notice (ss. 713.06, 713.015).
- A lien lasts 1 year unless a foreclosure suit is filed, and you can shorten that to 60 days by recording a Notice of Contest of Lien (s. 713.22). A willfully exaggerated lien is a fraudulent lien and a complete defense, with fees to the prevailing party (s. 713.31).
- An unlicensed contractor whose contract is unenforceable under s. 489.128 has no lien rights at all (s. 713.02).
Practical move in both states: before paying anyone to finish, find out who the old contractor owed. Call the subs and suppliers who sent you notices, ask what is unpaid, and get lien waivers when anything is paid.
Can I hire another contractor to finish? What happens to the permit?
Yes, once the first contractor's right to work has been ended properly. Hiring a replacement while the original contract is still in force is a common way owners end up being sued. Send the termination notice first.
Changing the contractor on the permit
A building permit is tied to the contractor of record, so the new contractor usually cannot simply call inspections under the old permit. Procedures are set by each building department:
- Houston handles a "Change of Contractor Applicant on building permits" through the Houston Permitting Center's permit office, following its name change procedures.
- Austin has the registered contractor assigned to a permit changed through its Modify a Permit process with Building and Trade Contractor Services, and the general contractor on a permit is responsible for scheduling inspections and obtaining the certificate of occupancy or completion.
- Dallas, San Antonio and Florida cities and counties each have their own change-of-contractor or contractor-substitution form. Call the building department, give the permit number and ask exactly what it needs: often a signed form from the new contractor, proof of license and insurance, and sometimes a letter or affidavit about the old contractor.
Expect the new contractor to want the permit history, approved plans and inspection results, and to inspect the existing work before taking responsibility for it. Many will not sign onto a permit until they have opened walls or ceilings to see work done by someone else.
Florida: record a new Notice of Commencement
In Florida, to change contractors the owner must record a new notice of commencement or a notice of recommencement. An amendment to the old notice is not enough, because amendments may only extend the period or correct or add information (s. 713.13). The new notice must be posted on site and filed with the building department before the first inspection when the contract exceeds $5,000 (s. 713.135). See the Florida notice of commencement guide.
Finishing it yourself
Florida lets an owner finish a one- or two-family home, townhome, accessory structure or condo unit as an owner-builder when the local permitting agency determines the permitted contractor substantially completed the project, and in that case the owner does not have to live there for a year afterward (s. 489.103). Texas cities have their own homeowner-permit rules; Dallas, for example, lets a homeowner pull certain permits on a homestead after signing an affidavit. See the Florida owner-builder and Texas owner-builder guides before you take this on.
Pricing the completion
Expect a replacement contractor to charge more than the remaining contract balance. They take on unknown work, may have to fix or redo parts, and are pricing a smaller job. Keep every completion invoice: the difference between your original contract price and what it actually cost you to finish is usually the core of your damages claim.
How do I get my deposit or overpayment back?
Recovery usually comes from one of five places. Work them in roughly this order.
| Source | Texas | Florida |
|---|---|---|
| Direct negotiation after demand | Demand letter; DTPA 60-day notice if claiming under the DTPA | Certified-mail demand under s. 489.126; 30-day clock |
| Surety bond | Ask whether the contractor carried a surety bond under its contract or any registration, and claim on it | Claim against any bond first; the Recovery Fund requires you to exhaust bonds and insurance |
| Lawsuit | Justice court up to $20,000; county or district court above that | Small claims up to $8,000; county or circuit court above that |
| State fund | No state homeowner recovery fund | Florida Homeowners' Construction Recovery Fund (licensed contractors only) |
| Criminal restitution | Trust Fund Act prosecution; theft or fraud referral | s. 489.126 or s. 713.345 prosecution; restitution can be ordered |
Florida Homeowners' Construction Recovery Fund
If you hired a licensed Florida contractor, the Recovery Fund can pay part of your loss. You generally need a final judgment, an arbitration award or a Construction Industry Licensing Board restitution order based on specified violations, including abandonment (s. 489.129(1)(j)) and financial mismanagement (s. 489.129(1)(g)); you must exhaust any bond or insurance first; and you must try to collect, usually by having a writ of execution returned unsatisfied (s. 489.141). The claim must be filed within 1 year after the underlying case ends. For contracts signed on or after July 1, 2024, the per-claim cap is $100,000 for Division I contractors (general, building, residential) and $30,000 for Division II, with aggregate caps of $2 million and $600,000 per licensee (s. 489.143). Note: s. 489.143(2) still says payment is limited to the judgment amount "or $25,000, whichever is less," while subsection (3) sets the higher caps; ask DBPR's Recovery Fund office how it applies to your claim. The fund does not cover contracts with someone who was unlicensed when the contract was signed. Details are in the Recovery Fund guide.
Small claims
Many deposit losses fit small claims. Texas justice courts hear claims up to $20,000; Florida small claims covers up to $8,000, excluding costs, interest and attorney's fees. See suing a contractor in small claims.
Is abandonment a crime? Reporting the contractor
Walking off a job is usually a contract problem. Keeping your money without doing the work can be a crime in both states.
Florida
- s. 489.126 makes it a crime to violate the deposit and abandonment rules. The penalty depends on the money involved: under $1,000 is a first-degree misdemeanor; $1,000 to under $20,000 is a third-degree felony; $20,000 to under $200,000 is a second-degree felony; and $200,000 or more is a first-degree felony. For abandonment cases, the amount is the money received in excess of the value of the work. The law applies to anyone promising contractor work, licensed or not.
- s. 713.345, misapplication of construction funds, applies when someone receives payment for improving real property and knowingly and intentionally fails to use it to pay what is then owed for labor and materials on the job. It is a felony at every dollar level.
- Unlicensed contracting is itself a crime under s. 489.127, and a felony if committed during a declared state of emergency.
Report to your local police or sheriff, or the State Attorney's economic crimes unit, with your file and the certified-mail receipt. File a licensing complaint with DBPR's Construction Industry Licensing Board (2601 Blair Stone Road, Tallahassee, FL 32399-0791; 850-487-1395) or online through DBPR. Many counties also have local licensing or code enforcement offices that can cite unlicensed contractors.
Texas
- Construction Trust Fund Act (Prop. Code ch. 162). Money paid to a contractor under a construction contract for improving specific Texas real property is held in trust. The contractor and its officers, directors or agents who control the money are trustees. Since September 1, 2025 (S.B. 841), Section 162.003(b) has expressly made a property owner a beneficiary of trust funds under a residential construction contract. Intentionally or knowingly diverting $500 or more without paying current or past-due obligations to beneficiaries is a Class A misdemeanor, and a third-degree felony with intent to defraud. On homestead contracts over $5,000, the contractor must keep the money in an account labeled a "construction account". See the Trust Fund Act guide.
- Theft or fraud. If the contractor took money with no intent to do the work, a police report for theft may be appropriate. Bring the contract, payment proof and your demand letter.
Texas has no statewide general contractor license, so there is no state licensing board complaint for a general contractor. You can complain to the city where the contractor is registered, to the Texas Department of Licensing and Regulation or the plumbing board if a licensed trade was involved, and to the Texas Attorney General's Consumer Protection Division. See how to file a complaint against a contractor.
What not to do
- Do not stop paying subs or suppliers who served notices without checking the lien rules. In Texas, a notice of claim tells you to withhold from future payments to the contractor to cover the debt. In Florida, an unpaid sub who served a Notice to Owner can lien even after you paid the contractor.
- Do not pay the old contractor anything more without a signed lien waiver in the statutory form and proof the money will reach the subs.
- Do not throw out or sell the contractor's tools or materials. List them, ask in writing for pickup, and keep them safe.
- Do not let your Florida Notice of Commencement lapse without a plan. Payments made after it expires are improper payments, which can mean paying twice (s. 713.13).
- Do not miss limitations periods. In Florida the four-year period for construction claims runs from the earliest of a certificate of occupancy, certificate of completion or the date of abandonment if construction was not completed (s. 95.11(3)(b)). DTPA claims in Texas must generally be filed within two years (Bus. & Com. Code s. 17.565).
- Do not hire the replacement before ending the first contract in writing.
Texas and Florida side by side
| Issue | Texas | Florida |
|---|---|---|
| Statutory abandonment test | None statewide; contract controls | 90 days without work while holding excess money (s. 489.126(3)); 90-day presumption for discipline (s. 489.129(1)(j)) |
| Owner demand | Written demand; DTPA 60-day notice (s. 17.505); ch. 38 30-day presentment | Certified mail, return receipt, to contract or license address; 30-day clock |
| Criminal law | Trust Fund Act, ch. 162 (owner is a beneficiary on residential jobs) | s. 489.126 tiers; s. 713.345 misapplication |
| Contractor lien deadline after abandonment | 15th day of 3rd month after month abandoned (residential) | 90 days after final furnishing |
| Change contractors | City change-of-contractor process on the permit | City or county permit change plus new NOC or notice of recommencement |
| State fund | None | Recovery Fund, $100,000 (Division I) / $30,000 (Division II) per claim for contracts on or after July 1, 2024 |
| Licensing complaint | City registration office; TDLR for licensed trades | DBPR / CILB; local licensing boards |
City specifics: Houston, Dallas, San Antonio, Austin, Miami, Tampa, Orlando and Jacksonville.
When to call a lawyer
This page is general information, not legal advice. Talk to a construction or consumer attorney when the money at stake is more than you are willing to lose, when a lien has been recorded, when the contract has an arbitration clause, when the contractor claims you breached first, or when you are unsure whether your termination is valid. A State Bar lawyer referral service in either state can connect you with someone. In Florida, a lawyer can also tell you whether to pursue a CILB restitution order instead of, or as well as, a civil judgment for Recovery Fund purposes.
How to choose a provider
- Photograph and video the entire site with dates before anything changes.
- Write a timeline of payments, last work date and every contact attempt.
- Pull the permit status and the contractor's license or city registration record.
- Get an independent estimate of the value of the work completed and the cost to finish.
- Calculate money paid minus value of work done.
- Send a certified-mail, return-receipt demand to perform or refund (Florida: cite s. 489.126).
- Follow any notice-to-cure clause in your contract, then send a written termination for cause.
- Contact subs and suppliers who sent notices; get statutory lien waivers before paying anyone.
- Change the contractor on the permit; in Florida, record a new Notice of Commencement or notice of recommencement.
- File licensing and law enforcement reports if money was kept without work.
- Calendar lien and limitations deadlines that run from the abandonment date.
- Keep every completion invoice to prove the extra cost to finish.
Related general and residential contractors guides
- How Do You Fire a Contractor Without Getting Sued or Liened?
- What Is the Florida Homeowners' Construction Recovery Fund, Who Qualifies, and How Much Can You Recover?
- What Is the Texas Construction Trust Fund Act, and What Can I Do if My Contractor Misused My Money?
- How Do I File a Complaint Against a Contractor in Texas or Florida?
- How Do You Sue a Contractor in Small Claims: Texas Justice Court and Florida County Court?
- What Is a Florida Notice of Commencement, When Do You Need One, and How Long Does It Last?
- How Do Mechanic's Liens Work in Texas, and How Do Homeowners Avoid Paying Twice?
- Contractor Dispute: Should You Negotiate, Mediate, Arbitrate or Go to Court?
General and residential contractors by state and city
Questions people ask
How long before a job is considered abandoned in Florida?
Florida uses 90 days. Under s. 489.126(3), a contractor holding money in excess of the work performed may not fail to perform any work for a 90-day period or a different period set in the contract, and a 90-day stoppage without just cause is prima facie evidence of a violation. The licensing board may also presume abandonment after 90 days without work or proper notice. You do not have to wait 90 days to send a demand or seek legal help.
How long before a job is considered abandoned in Texas?
Texas has no statewide day count. Your contract usually decides, through a delay clause, a notice-to-cure period or a termination clause. If the contract is silent, whether the contractor abandoned the work is judged on the facts: how long work stopped, whether the contractor communicated, and whether there was a legitimate reason. Send a written notice with a firm deadline so the record is clear.
Can I hire another contractor to finish the job?
Yes, after you have ended the first contract in writing, ideally following any notice-to-cure clause. The new contractor will need to be put on the permit through the building department's change-of-contractor process. In Florida you must also record a new notice of commencement or a notice of recommencement. Keep every invoice from the replacement, because the extra cost to finish is part of your damages.
Can the contractor who abandoned my job still file a lien?
Possibly. In Texas, the original contractor on a residential job has until the 15th day of the third month after the month its work was terminated or abandoned to file a lien affidavit. In Florida, a claim of lien must be recorded within 90 days after the lienor last furnished labor or materials. Subs and suppliers may have their own rights. Unlicensed Florida contractors have no lien rights.
Is it a crime for a contractor to abandon a job in Florida?
Abandonment alone is mainly a licensing and contract issue, but keeping money in excess of the work performed can be a crime under s. 489.126, with penalties from a first-degree misdemeanor under $1,000 up to a first-degree felony at $200,000 or more. If the contractor does not refund within 30 days of a certified-mail demand, intent may be inferred. Report it to local law enforcement and DBPR.
Will the Florida Recovery Fund pay me back?
It may, if your contractor was licensed when you signed and your loss comes from covered violations such as abandonment or financial mismanagement. You generally need a judgment, arbitration award or board restitution order, must exhaust bonds and insurance, must try to collect, and must claim within 1 year after the case ends. For contracts on or after July 1, 2024, the cap is $100,000 per Division I claim and $30,000 per Division II claim.
Does the Texas RCLA notice apply to an abandoned job?
Not to the abandonment itself. The Residential Construction Liability Act says it does not apply to damages from a contractor's wrongful abandonment of a project before completion, or to Trust Fund Act violations. If part of your claim is about defective work that was completed, the RCLA's 60-day certified-mail notice may still be needed for that part. A lawyer can help you split the claims correctly.
What if I never signed a written contract?
You still have rights. In Florida, s. 489.126 tells you to mail your demand to the address the contractor lists with DBPR or the local licensing board when there is no written agreement. In Texas, oral contracts can be enforced, though they are harder to prove, and a lien on a homestead requires a written contract signed before work began. Use texts, payment records and witnesses to prove the deal.
Sources
- Florida Statutes s. 489.126, Moneys received by contractors (2026)
- Florida Statutes s. 489.129, Disciplinary proceedings (2026)
- Florida Statutes s. 489.141, Recovery Fund conditions (2026)
- Florida Statutes s. 489.143, Recovery Fund payments (2026)
- Florida Statutes s. 489.103, Exemptions (2026)
- Florida Statutes s. 489.127, Prohibitions; penalties (2026)
- Florida Statutes s. 713.13, Notice of commencement (2026)
- Florida Statutes s. 713.135, Notice of commencement and permits (2026)
- Florida Statutes s. 713.06, Liens of persons not in privity (2026)
- Florida Statutes s. 713.08, Claim of lien (2026)
- Florida Statutes s. 713.22, Duration of lien (2026)
- Florida Statutes s. 713.345, Misapplication of construction funds (2026)
- Florida Statutes s. 95.11, Limitations (2026)
- Texas Property Code ch. 53, Mechanic's, Contractor's, or Materialman's Lien
- Texas Property Code ch. 27, Residential Construction Liability
- Texas Property Code ch. 162, Construction Trust Funds
- Texas Business and Commerce Code ch. 17 (DTPA)
- Texas Civil Practice and Remedies Code ch. 38, Attorney's Fees
- Florida DBPR, Construction Industry Licensing Board
- Houston Permitting Center, Permits
- City of Austin, Contractor Registration
- City of Dallas, Homeowner's Exemption from Registration as a Contractor
- Houston Permitting Center, One-Stop Residential Projects training (February 26, 2026)
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.