Pool Builder Deposits and Payment Schedules: How Much to Pay and When
How to keep the deposit small, tie each draw to an inspected milestone, collect the right lien waivers, and use Florida's and Texas's statutes to protect your money.
Keep the deposit modest and pay the rest in draws tied to completed, inspected stages, with lien waivers at each payment and the last payment after final inspection. In Florida, a deposit over 10% legally obliges the contractor to apply for permits within 30 days and start within 90 days after permits issue (489.126). In Texas, owners should hold back 10% during the work and for 30 days after completion (Property Code ch. 53), and payments are trust funds for subcontractors (ch. 162).
Key facts
- Florida contractors taking more than 10% upfront on residential work must apply for permits within 30 days and start within 90 days after permits issue, absent just cause or a written agreement (489.126).
- Violating 489.126 ranges from a first-degree misdemeanor under $1,000 to a first-degree felony at $200,000 or more.
- Florida subcontractors and suppliers without a direct contract must serve a Notice to Owner before or within 45 days of starting work (713.06).
- Florida lien waivers cannot be given in advance, and statutory forms exist for progress and final payments (713.20).
- Texas owners must retain 10% of the contract price during the work and for 30 days after completion to protect against subcontractor claims (Property Code ch. 53).
- Texas construction payments are trust funds; misapplying $500 or more is a Class A misdemeanor, or a third-degree felony with intent to defraud (Property Code 162).
- Texas contractors on residential homestead contracts over $5,000 must deposit trust funds in a separate 'construction account' (162).
- Texas lien waivers are enforceable only if they substantially follow the statutory forms, and unconditional waivers may not be required before payment is received (53.281 to 53.284).
How much deposit should a pool builder ask for?
There is no single legal maximum in Texas or Florida, but the smaller the deposit, the less you can lose if the builder never starts. A deposit should roughly match what the builder must spend before work begins: design, engineering, permit fees and, for fiberglass, a shell order.
Florida. Florida law does not ban large deposits, but it attaches duties to them. Under 489.126, if a contractor receives more than 10% of the contract price as an initial payment on residential work, it must:
- Apply for the necessary permits within 30 days after the payment, and
- Start the work within 90 days after the permits are issued,
unless it has just cause or you agreed in writing to longer periods. If it misses these, you must send a written demand by certified mail, return receipt requested, asking it to apply for permits, start work or refund the payment. If it does not do so within 30 days of the demand, that supports an inference that it had no just cause.
Texas. No statute caps the deposit. Protection comes from the contract, the trust fund law (Property Code ch. 162) and the lien law retainage rule (ch. 53).
Is a 50% deposit for a pool normal?
It is a red flag. A 50% deposit puts half the job's value in the builder's hands before a shovel hits the ground. If the builder has cash trouble, your deposit may pay for someone else's pool. Ask why so much is needed and what it will be spent on. Offer instead to pay for specific costs as they come due, for example a shell order paid on proof of the order, or permit fees on proof of filing.
In Florida, any initial payment over 10% triggers the 489.126 deadlines, and you should not sign a clause extending them without a real reason. Misusing funds under 489.126 is a crime graded by amount: a first-degree misdemeanor under $1,000, a third-degree felony from $1,000 to under $20,000, a second-degree felony from $20,000 to under $200,000 and a first-degree felony at $200,000 or more.
What is a typical pool payment draw schedule?
A "draw" is a payment released when a stage is done. A sound schedule pays for completed, inspected work, not for dates on a calendar. Here is an example structure for a concrete pool. The percentages are illustrations, not a legal standard; what matters is that each payment follows the work.
| Draw | Released when | Proof to collect |
|---|---|---|
| Deposit | Contract signed | Signed contract with required notices |
| Excavation | Hole dug to plan, permit posted | Photos; permit number |
| Steel, plumbing and bonding | Pre-shell inspection passed | Inspection result; pressure test photo |
| Shell | Gunite or shotcrete placed | Photos; lien waivers from shotcrete crew if they sent notice |
| Tile, coping, equipment | Installed and matches contract | Equipment label photos; waivers |
| Deck | Poured or laid, any deck inspection passed | Photos; inspection result; waivers |
| Final | Final inspection passed, barrier in place, plaster done, startup complete, punch list finished | Final inspection result; final affidavit; final waivers |
For fiberglass, typical milestones are: contract, shell delivered and set, plumbing and electrical inspected, bond beam and deck, final. See concrete pool stages and fiberglass installation.
Worked example: a $70,000 pool payment schedule
Here is how the rules above can fit together for a $70,000 concrete pool. The split is an illustration we built for this guide, not a legal standard or a survey of what builders charge.
| Payment | Amount | Released when |
|---|---|---|
| Deposit (10%) | $7,000 | Contract signed with required notices |
| Excavation and steel | $14,000 | Pre-shell steel and bonding inspection passed |
| Shell | $14,000 | Shell placed and curing plan started |
| Tile, coping and equipment | $10,500 | Installed, matching the contract list |
| Deck | $10,500 | Deck complete, any deck inspection passed |
| Final | $7,000 | Final inspection passed, plaster and startup done, punch list complete, final affidavit and waivers delivered |
| Retainage | $7,000 | In Texas, 30 days after completion with no unresolved notices of claim |
In Florida, a deposit of exactly 10% stays at the threshold in 489.126, which applies to initial payments of more than 10%. In Texas, the $7,000 retainage line reflects the 10% the statutory disclosure tells owners to reserve during the work and for 30 days after completion. Adjust stage amounts to match the value of each stage in your contract; the goal is that you have never paid much more than the value of the work in the ground.
Should I pay the final payment before the pool passes inspection?
No. Hold the final payment until the pool has passed final inspection, the barrier is in place, the startup is done, punch-list items are fixed, and you have the final affidavit and lien releases. Final inspection is a code check, not a quality check, so do your own walk-through too.
Florida. When final payment under a direct contract becomes due, the contractor must give you a final payment affidavit stating that all lienors who served a Notice to Owner have been paid, or listing those who have not and the amounts (713.06(3)(d)). The contractor cannot enforce its own lien while it is in default on giving this affidavit, and must deliver it at least 5 days before suing to enforce a lien.
Texas. As a condition of final payment on a residential construction contract, the original contractor must give you a final bills-paid affidavit stating that everyone has been paid in full, or listing who is still owed (Property Code 53.259). Keep the 10% retainage for 30 days after completion.
What is a lien waiver, and should I get one at each draw?
A lien waiver (also called a release) is a signed document from a contractor, subcontractor or supplier giving up lien rights for the amount it has been paid. Yes, get them at each draw, from the builder and from every subcontractor or supplier who has notified you.
Florida
- Florida's statutory forms are the "Waiver and Release of Lien Upon Progress Payment," which covers work through a stated date but not retention or later work, and the "Waiver and Release of Lien Upon Final Payment" (713.20).
- A lien right cannot be waived in advance; an advance waiver is unenforceable. You also may not require a waiver that differs from the statutory forms.
- A lienor may make a waiver conditional on a check clearing. If so, you may hold back the amount of that unpaid check until it clears, unless there is a payment bond.
Texas
- Waivers are enforceable only if they substantially follow one of four statutory forms: conditional or unconditional, for progress or final payment (Property Code 53.281 to 53.284).
- No one may require an unconditional waiver unless the claimant actually received that payment in good funds (53.283).
- A contract clause that waives the right to file or enforce a lien in advance is void, except as the statute allows (53.286).
Practical approach: exchange a conditional waiver for your check, and collect the unconditional waiver once the payment clears.
How do I make sure subcontractors and suppliers are paid?
- Know who they are. In Texas, the contractor must give you a list of subcontractors and suppliers before work starts and update it within 15 days of changes, unless you waive it (53.256). In Florida, the Notices to Owner you receive tell you who is on the job.
- Collect waivers from each one with each payment that covers their work.
- Use a joint check or direct payment for a large supplier if your contract allows it.
- Keep retainage. In Texas, hold 10% during the work and for 30 days after completion. In Florida, retainage is a contract matter; it is common in commercial work and can be negotiated for residential.
- Get the final affidavit before the last payment, in either state.
Texas also requires that, each time the contractor asks for payment, it give a disbursement statement listing who it intends to pay from the funds, according to the statutory disclosure statement in 53.255. Ask for it.
What is a Notice to Owner, and why did I get one from a supplier?
In Florida, subcontractors and suppliers who do not have a contract directly with you must serve a Notice to Owner before starting, or within 45 days after starting, to keep their lien rights, and before your final payment after the contractor gives the final affidavit (713.06). Failing to serve it is a complete defense to their lien. Getting one is normal and does not mean anything is wrong. It means: before you pay for that company's work, get its waiver.
Florida's recorded Notice of Commencement (713.13) is the document that starts this process for most improvements over $2,500. It lists the owner, contractor and property. It is void if work does not begin within 90 days of recording and expires 1 year after recording unless a different date is stated. A claim of lien must be recorded no later than 90 days after the lienor's final furnishing of labor or materials (713.08), and a lien expires 1 year after recording unless a foreclosure suit is filed (713.22).
In Texas, the equivalent warning is a notice of claim. On residential projects, an unpaid subcontractor or supplier must send you and the contractor a "NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS" by the 15th day of the second month after the month it furnished the work. If you get one, withhold the claimed amount from your next payment to the contractor until the dispute is resolved, as the statutory disclosure explains.
What is retainage?
Retainage is a portion of each payment held back until the job is complete, to cover unpaid subcontractors, suppliers or unfinished work.
- Texas: owners must retain 10% of the contract price, or 10% of the value of the work, during the work and for 30 days after completion. If you do not, and a valid claim is timely made, you may be personally liable and your property may be subject to a lien up to the amount you should have retained.
- Florida: no fixed residential retainage rule applies; it is a contract term. Many owners hold back the final payment as practical retainage until final inspection and the final affidavit.
Can I withhold payment for defects?
Generally, your contract controls. Florida 713.345 notes that a contractor's duty to apply payments to labor and materials does not stop anyone from withholding payment under the contract terms or because of a bona fide dispute. Practical steps:
- Write down the defect with photos and dates, and send it to the builder in writing.
- Withhold an amount reasonably related to the defect, not the whole draw, unless the contract says otherwise.
- Keep paying for undisputed, completed work so you are not the party in breach.
- In Texas, if a subcontractor sends a notice of claim, withhold the claimed amount.
- For a significant dispute, get legal advice before withholding large sums.
See pool builder disputes and complaints.
What happens if my builder takes the deposit and never starts?
Florida. If the deposit was over 10% and the builder has not applied for permits within 30 days, or not started within 90 days after permits issue, send the certified-mail demand described in 489.126. Keep the return receipt. If there is no permit application, start or refund within 30 days, that supports an inference of no just cause. You can also file a complaint with DBPR, and talk to law enforcement about a possible 489.126 violation. If the builder was licensed and you obtain a judgment, arbitration award or CILB restitution order, the Homeowners' Construction Recovery Fund may pay up to $30,000 per Division II claim for contracts on or after July 1, 2024 (489.143). It cannot pay if the contractor was unlicensed when you signed (489.141).
Texas. Send a written demand. Payments to a contractor are trust funds, and misapplying $500 or more is a crime (Property Code 162). Consider a DTPA notice, which generally must be given at least 60 days before filing suit (Bus. and Com. Code 17.505), and talk to a construction attorney.
Should I pay by card, check or wire?
- Check (from your account, payable to the builder's company name): leaves a clear record, and works well with conditional lien waivers.
- Card payment: may give you a dispute process through your card issuer for the deposit; check your card's terms. Some builders add a fee.
- Wire or electronic transfer: fast but very hard to reverse. Confirm wiring instructions by phone with a number you already know, because email instructions can be faked.
- Cash: avoid. It leaves no record.
Always pay the company named in the contract, never an individual's personal account. In Texas, a contractor with a written homestead improvement contract over $5,000 must deposit the funds in a separate account labeled a construction account (Property Code 162); you can ask where your payment is deposited.
How to choose a provider
- Keep the deposit small and tied to real upfront costs.
- In Florida, track the 30-day permit and 90-day start deadlines if the deposit is over 10%.
- Tie each draw to a completed, inspected stage.
- Collect conditional waivers with checks and unconditional waivers after they clear.
- Get waivers from every sub or supplier who sent a Notice to Owner or notice of claim.
- In Texas, keep 10% retainage until 30 days after completion.
- Hold the final payment until final inspection, punch list and startup are done.
- Get the final payment affidavit (FL 713.06) or bills-paid affidavit (TX 53.259).
- Pay the company named in the contract, by traceable method.
- Keep every receipt, waiver and notice in one file.
Related swimming pool builders and contractors guides
- Pool Construction Contract Checklist: What Must Be in Writing Before You Sign
- How Long Does It Take to Build a Pool in Texas and Florida?
- How to Choose a Pool Builder in Texas or Florida: 25 Questions to Ask
- What Can You Do If Your Pool Builder Abandons the Job or Does Bad Work in Texas or Florida?
- How a Concrete (Gunite) Pool Is Built: Step-by-Step From Layout to First Swim
- Do Pool Builders Need a License in Florida? Commercial, Residential, Servicing and Specialty Licenses Explained
Swimming pool builders and contractors by state and city
Questions people ask
Is it legal in Florida for a contractor to take more than 10% upfront?
Yes, but it triggers duties. Under Fla. Stat. 489.126, a contractor that receives more than 10% of the contract price as an initial payment on residential work must apply for permits within 30 days and start work within 90 days after permits issue, unless there is just cause or you agreed in writing to longer periods. Missing them, and then ignoring a certified-mail demand for 30 days, supports an inference of no just cause.
Do I need a Notice of Commencement for my pool in Florida?
For most improvements over $2,500, yes. Fla. Stat. 713.13 requires the owner or the owner's agent to record a notice of commencement and post a copy before starting the improvement. Builders often prepare it for your signature. It is void if work does not start within 90 days of recording. Paying before the notice is recorded, or after it expires, can expose you to paying twice.
What is a final bills-paid affidavit in Texas?
Texas Property Code 53.259 requires the original contractor, as a condition of final payment under a residential construction contract, to give you an affidavit stating it has paid everyone in full for labor and materials, or listing the amount owed and the name and contact information of each unpaid person. Get it before you release the final payment and keep it with your lien waivers.
Can a pool builder put a lien on my house?
Yes, if it is not paid and follows the lien statute's steps and deadlines. In Florida, a claim of lien must be recorded within 90 days after the lienor's final furnishing and expires after 1 year without a foreclosure suit. In Texas, a residential original contractor generally must file its lien affidavit by the 15th day of the third month after its work was completed, terminated or abandoned, and homestead liens need a signed, filed contract.
Can a pool builder charge me for a draw before the stage passes inspection?
The contract decides what triggers each payment, which is why it should tie draws to completed, inspected stages. If your contract says a draw is due on a date or on a stage being started, you may have agreed to pay early. Before signing, rewrite triggers to name the inspection or the completed work. If a builder demands a draw early, ask in writing which contract clause it relies on.
What should I do if a supplier says it was not paid?
Do not ignore it. In Florida, a Notice to Owner or a claim of lien means you should get that supplier's waiver before paying for its materials. In Texas, if you receive a notice of claim, withhold the claimed amount from your contractor until the dispute is resolved. Tell your contractor in writing, ask for proof of payment, and talk to a construction attorney if the amount is large.
Sources
- Fla. Stat. 489.126 (2026): Moneys received by contractors
- Fla. Stat. 713.06 (2026): Liens of persons not in privity; notice to owner; final payment affidavit
- Fla. Stat. 713.08 (2026): Claim of lien
- Fla. Stat. 713.13 (2026): Notice of commencement
- Fla. Stat. 713.20 (2026): Duration of liens; waivers and releases
- Fla. Stat. 713.22 (2026): Duration of lien
- Fla. Stat. 713.345 (2026): Misapplication of construction funds
- Fla. Stat. 489.141 (2026): Recovery fund claim conditions
- Fla. Stat. 489.143 (2026): Recovery fund payment limits
- Florida DBPR: File a Complaint
- Texas Property Code Chapter 53: Mechanic's, Contractor's, or Materialman's Liens
- Texas Property Code Chapter 162: Construction Trust Funds
- Texas Business and Commerce Code Chapter 17 (Deceptive Trade Practices Act)
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.