Local Guide · AC and heating
AC Installation Day: Step-by-Step, Commissioning and What to Check Before You Pay
What a correct central AC or heat pump installation looks like, from removing the old system to nitrogen brazing, vacuum, charging and airflow testing, plus the paperwork Texas and Florida homeowners should have before the final payment.
A typical split-system AC replacement takes one day and follows a set order: recover the old refrigerant, remove the old units, set the new outdoor unit and indoor coil or air handler, braze the refrigerant lines while flowing nitrogen, pressure test, pull a deep vacuum measured with a micron gauge, release and adjust the charge using superheat or subcooling, then measure airflow and static pressure. Before paying, get the startup readings, permit number, AHRI certificate and warranty registration.
Key facts
- ACCA cites a NIST report finding that not following the ACCA 5 QI Quality Installation standard can increase annual energy consumption by 30% or more.
- Florida's energy code requires residential HVAC to be sized with ACCA Manual S based on Manual J (or another approved method) loads, and bans safety-factor oversizing (FBC-Energy R403.7.1).
- Florida cooling equipment capacity must be at least the calculated load but no more than 1.15 times it, or the closest size offered (R403.7.1.1).
- Florida replacements must use matched indoor and outdoor units verified by AHRI data or similar proof (FBC-Energy R501.7).
- Since January 1, 2025, new residential split AC and heat pump systems must use refrigerant with a GWP of 700 or less, such as R-454B (GWP 470) or R-32 (GWP 675), both rated A2L (mildly flammable).
- EPA's May 2026 rule, effective July 27, 2026, removed the installation deadline for residential split systems built before 2025, so remaining R-410A equipment can still be installed.
- Houston requires a mechanical permit and inspection for residential AC replacements, including condensers, evaporator coils, furnaces and duct alterations.
- The Florida Mechanical Code requires an auxiliary drain pan, overflow drain or water-level shutoff where a clogged condensate drain could damage the building (FMC 307.2.3).
- The federal 25C tax credit for AC and heat pump installs ended for property placed in service after December 31, 2025.
- Split ACs under 45,000 Btu/hr installed in Texas or Florida must meet at least 14.3 SEER2 under DOE's Southeast regional standard.
What happens during an AC installation? The full sequence
Here is the order a careful crew follows for a typical split system (outdoor condenser or heat pump plus an indoor coil and furnace or air handler) in a Texas or Florida home.
- Arrival and walk-through. The lead installer confirms the equipment matches the contract (model numbers), lays drop cloths, and checks where the work will happen: garage, closet, attic, roof or side yard.
- Power off and refrigerant recovery. The old refrigerant is recovered into a cylinder with a recovery machine. Federal law bans knowingly venting it.
- Removal. The old outdoor unit, indoor coil or air handler, and often the old drain pan and disconnect come out.
- Set the new equipment. Outdoor unit on a level pad or stand, secured as local code requires (important in hurricane zones). Indoor unit set with proper clearance and service access.
- Line set. The copper refrigerant lines are replaced or, if reused, flushed and checked. Line set size must match the new equipment's instructions.
- Brazing with nitrogen. Copper joints are brazed while nitrogen flows through the pipes.
- Pressure test. The system is pressurized with dry nitrogen and watched for drops.
- Evacuation. A vacuum pump pulls air and moisture out; a micron gauge proves the vacuum is deep and holding.
- Electrical. New disconnect and whip as needed, correct breaker size per the nameplate, low-voltage thermostat wiring.
- Condensate. Primary drain with a trap where required, plus overflow protection.
- Ductwork connections. Plenums attached and sealed with mastic or approved tape, not plain duct tape.
- Startup and charging. Refrigerant released, charge adjusted to the manufacturer's superheat or subcooling target.
- Airflow and static pressure check. Fan speed set for the duct system.
- Thermostat setup and controls test. Cooling, heat, heat pump defrost, auxiliary heat and any dehumidification settings.
- Cleanup, walk-through and paperwork.
Inspections follow. Houston's mechanical inspectors, for example, list cover, grill seal and final inspections for permitted mechanical work, and the contractor normally schedules them.
How long does it take to install a new AC system?
A like-for-like replacement of a split system in a single-family home is commonly done in one day by a two- or three-person crew. Plan for more time when the job includes:
- New or modified ductwork, or a new return.
- Moving the indoor unit or condenser to a new location.
- A new line set through finished walls.
- A new electrical circuit or panel work by an electrician.
- An attic platform, new drain pan, or a new air handler stand.
- Two systems in a two-story home.
- A package unit set by crane, or a rooftop unit.
- Switching from a gas furnace to a heat pump with electric backup heat.
Inspections may be on a different day. Some Florida jurisdictions allow virtual inspections, and Florida law lets a homeowner or contractor use a private provider for single-trade inspections such as HVAC replacements (§553.791). If a crew finishes a complex job in three hours, ask what was skipped. Vacuum and pressure tests alone take real time.
Do they need to go in my attic?
Often, yes. Many homes in Houston, Dallas, San Antonio, Austin, Tampa, Orlando and Jacksonville have the furnace or air handler in the attic, and supply ducts run there in most homes even when the air handler is in a closet or garage. Crews need safe access: clear the path to the attic hatch, move items under the hatch, and tell them about any weak spots or blown-in insulation that hides joists.
Things to check in the attic after the install:
- Drain pan and overflow protection. The Florida Mechanical Code requires, where an overflow could damage building parts, an auxiliary drain pan with a separate drain to a conspicuous spot, a secondary overflow drain, or a listed water-level switch that shuts the unit off before overflow (FMC 307.2.3). Downflow units and coils without secondary drain provisions need a water-level device inside the primary pan.
- Florida attic air handlers. Under Florida's energy code, air handlers may be in an attic only under the performance compliance path, with conditions including a failed-drain alarm or shutoff and a notice on the electrical panel (FBC-Energy R403.3.6). Ask your contractor how your install complies.
- Duct insulation. Florida requires attic supply and return ducts 3 inches or larger to be insulated to at least R-8 for new work (R403.3.1). On a change-out, existing ducts with R-6 insulation are considered sufficient (R501.7).
- Sealing. Connections sealed with mastic or metal tape. ENERGY STAR says never to use duct tape for duct sealing.
- Labeled drains. The termination of concealed condensate piping must be marked as primary or secondary (FMC 307.2.3.3).
Attic work in a Texas or Florida summer is dangerous for the crew. Morning starts are common for that reason.
What is a nitrogen pressure test and evacuation?
Brazing with nitrogen
When copper is heated to braze a joint, oxygen inside the pipe reacts with the hot copper and forms black flakes of copper oxide. Those flakes can later break loose and clog metering devices or damage the compressor. Flowing a small amount of nitrogen through the line while brazing pushes out oxygen and keeps the inside clean. Manufacturers' installation instructions generally call for it, and ACCA's Quality Installation standard is built around following them.
Pressure test
After brazing, the crew fills the system with dry nitrogen to a test pressure within the equipment's limits and watches a gauge. If pressure drops, there is a leak to fix now, before refrigerant goes in. This step matters more than ever because a leak in a new A2L system means paying for expensive new refrigerant and possibly a warranty dispute.
Evacuation and the micron gauge
Next, a vacuum pump removes air and moisture. Moisture mixed with refrigerant and oil can form acids that damage compressors over time. A micron gauge measures how deep the vacuum is (lower microns means less air and moisture). After the pump is isolated, the reading should hold steady; a rising reading points to a leak or remaining moisture. Follow the specific vacuum level and hold time in your equipment's installation manual.
Ask the installer to show you the micron gauge reading and note it on the startup sheet. A crew that "purges" lines with refrigerant instead of evacuating, or skips the micron gauge, is cutting a corner that can shorten the system's life.
How is the refrigerant charge set? Superheat and subcooling
New outdoor units ship with a factory charge meant for a certain line length. The installer adjusts it for your actual line set and confirms it under running conditions.
- Subcooling is used on most systems with a thermostatic or electronic expansion valve (TXV or EEV). It measures how far below its condensing temperature the liquid refrigerant has cooled. The manufacturer lists a target on the unit or in the manual.
- Superheat is used on systems with a fixed metering device. It measures how far above its boiling point the refrigerant vapor has warmed by the time it returns to the outdoor unit. Targets depend on indoor and outdoor conditions.
Both require accurate gauges or digital probes and temperature clamps. The installer should record pressures, line temperatures, the target and the actual value, plus outdoor and indoor temperatures at the time. Charging "by feel" or by matching an old pressure is not a substitute.
Why it matters: too much or too little refrigerant cuts efficiency, can freeze the coil, and can shorten compressor life.
A2L refrigerants (R-454B and R-32)
Most new systems installed since 2025 use R-454B or R-32. EPA lists both as acceptable, with use conditions, for new residential AC and heat pumps; both are classed A2L (mildly flammable). Installers need A2L-rated tools and must follow the manufacturer's rules, which can include refrigerant detection sensors and mitigation controls in the indoor unit. Texas contractors should confirm current TDLR guidance, since TDLR's older FAQ language describes comfort-AC refrigerants in terms of nonflammable (A1) types. See our refrigerant guide.
Static pressure and airflow: the step most installs skip
An AC can be perfectly charged and still perform badly if it does not move enough air. Total external static pressure is the resistance the blower fights from the filter, coil and ducts, measured in inches of water column with a manometer. Each air handler or furnace lists a maximum rated value and a fan table showing airflow at different pressures.
The installer should:
- Measure static pressure on the supply and return sides with the new filter in place.
- Compare it with the equipment's rating.
- Set the blower speed or airflow profile so airflow matches the system's design, including settings for humid climates where lower airflow can improve moisture removal.
- Note the values on the startup sheet.
High static pressure often comes from undersized return ducts, restrictive filters, or kinked flex duct in the attic. It causes noise, weak airflow at far rooms, frozen coils and shorter equipment life. ENERGY STAR says airflow problems can reduce efficiency by up to 15%. If your new system is louder or weaker than expected, ask for the static pressure reading. See duct leaks and attic ducts and air filters and MERV.
New ducts in Florida must be leak tested under the energy code (R403.3.3), with a prescriptive limit of 4 cfm per 100 square feet of conditioned floor area at 25 Pa. Extending existing ducts less than 40 linear feet in unconditioned space does not trigger testing (R503.1.2). On a straight change-out reusing old ducts, testing is not required, but a good contractor will still seal accessible connections.
What is AC commissioning?
Commissioning means proving, with measurements, that the system was installed and set up to the manufacturer's and design specifications. It is the difference between "it's blowing cold" and "it's working as designed." ACCA's standards include ANSI/ACCA 5 QI (Quality Installation) and Quality Installation Verification Protocols for checking that an install meets it.
A commissioning check usually covers:
- Equipment matches the design: a load calculation (Manual J), equipment selection (Manual S), and a matched AHRI-rated indoor and outdoor combination.
- Refrigerant charge within the manufacturer's tolerance, by subcooling or superheat.
- Airflow and total external static pressure within rated limits.
- Electrical: voltage, amperage draw, breaker and wire size per nameplate.
- Temperature split (the difference between return and supply air) as a sanity check, not as the only test.
- Gas furnaces: gas pressure, combustion check, venting and a carbon monoxide check.
- Heat pumps: reversing valve, defrost operation, auxiliary heat staging and lockout settings.
- Condensate drain and safety switch tested with water.
- Thermostat configured for the equipment type and stages.
Florida's statute on AC efficiency states the Legislature's intent that residential replacement systems be installed with quality installation procedures, including sizing analysis and duct inspection (§553.912).
What is a startup sheet?
A startup sheet (or commissioning report) is the written record of the readings taken when the system was first run. Ask for it before the crew leaves. A useful one shows:
| Item | Why it matters |
|---|---|
| Outdoor and indoor model and serial numbers | Warranty, AHRI match, future service |
| Refrigerant type and amount added or removed | Charge history; leak detection later |
| Micron reading and decay hold | Proves evacuation was done |
| Suction and liquid pressures and temperatures | Baseline for future service |
| Superheat or subcooling target and actual | Proves charge was set |
| Total external static pressure | Airflow health |
| Blower setting | Explains noise or humidity behavior |
| Voltage and amp draw | Electrical health |
| Supply and return temperatures | Sanity check |
| Outdoor temperature at startup | Context for the readings |
Keep it with your home records. A future technician can compare new readings with it to spot a leak or a failing part.
What paperwork should I get after install?
- Final invoice listing exact model numbers and any changes from the contract.
- AHRI certificate for the exact indoor and outdoor combination, showing SEER2 and, for heat pumps, HSPF2. Florida replacements must be matched and verifiable (FBC-Energy R501.7). In Texas and Florida, a split AC under 45,000 Btu/hr must meet at least 14.3 SEER2.
- Permit number and, later, the passed final inspection. In Jacksonville, the permit must be posted so it is visible from the street, and starting work without first applying is punishable by a $250 fine. Check your city's portal (Houston, DallasNow, Miami-Dade E-Permitting, Orlando, Jacksonville).
- Manual J and equipment selection, especially in Florida where Manual S sizing is required.
- Startup or commissioning sheet.
- Warranty registration confirmation from the manufacturer, plus the contractor's written labor warranty.
- Lien paperwork: in Texas, a final bills-paid affidavit on residential construction contracts (Prop. Code §53.259); in Florida, the contractor's final payment affidavit (§713.06). See our lien guide.
- Rebate forms if your utility offers one. CPS Energy rebates require a city permit number for installs inside San Antonio, and Austin Energy rebates require all city permits.
- Owner's manuals and filter size.
Tax note: the federal 25C Energy Efficient Home Improvement Credit ended for property placed in service after December 31, 2025, so a 2026 install does not qualify. See 25C in 2026.
Should the installer register my warranty?
Many manufacturers offer a longer parts warranty only if the equipment is registered within a set number of days after installation, and a shorter base warranty if not. Check your brand's terms; the window and coverage vary by manufacturer and by state.
Ask the contractor in writing to register the equipment and send you the confirmation. Then verify it yourself on the manufacturer's website using the serial numbers. If the contractor forgets and the window closes, you may lose years of coverage. Details: warranty registration guide.
How do I know the install was done right? A homeowner walk-through
- Outdoor unit: level, on a pad or stand, at least the manufacturer's clearance from walls and shrubs, disconnect installed, line set insulated (the larger suction line), service caps on.
- Coastal and hurricane areas: unit fastened as local code requires. Rooftop and exposed equipment in Florida must resist wind pressures under the Florida Building Code (FMC 301.15). See hurricane prep and coastal corrosion.
- Indoor unit: sealed connections, drain trapped where the manufacturer requires, safety switch or overflow pan in place, service access clear.
- Filter: correct size, arrow in the airflow direction.
- Thermostat: set up for your equipment; ask them to show you heat pump and fan settings.
- Run test: after 15 minutes, supply registers should feel noticeably cooler; no rattles or whistles.
- Paperwork: everything in the list above.
- Photos: ask for photos of brazed joints, the attic or closet work, and both nameplates.
- Cleanup: old equipment hauled away, no copper scraps or screws in the yard.
Hold back the final payment, if your contract allows, until the system runs and you have the startup sheet. Pay the balance after the final inspection passes where possible.
Why is my new AC not cooling as well as the old one?
The first week brings a lot of calls that turn out to be normal. Some are real problems.
Often normal
- It runs longer. Correctly sized and variable-speed systems run long, gentle cycles that remove more humidity. Florida's code bans oversizing beyond 1.15 times the calculated load, so a new properly sized system may run longer than an old oversized one.
- Air feels less icy at the vent. Variable-speed equipment may run at low speed most of the time.
- New smell for a day or two from coatings on new heat strips or a new furnace.
- A heat pump outdoor unit "steaming" in winter is defrost, not a fire.
Call the installer back
- The house cannot hold the set temperature on a normal summer day.
- Ice on the refrigerant lines or indoor coil.
- Water in the drain pan, ceiling stains, or a tripped float switch.
- New noise: whistling at the return (high static pressure) or rattling.
- Breaker trips.
- Indoor humidity stays above about 60%. EPA recommends keeping indoor humidity below 60%, ideally 30% to 50%.
- Rooms that were fine before are now hot, which can point to airflow or duct issues.
Write down dates, times, outdoor temperature and indoor readings before you call. Ask for the startup sheet and have the technician compare readings. See AC not cooling upstairs and humidity in Florida homes.
Before install day: how to prepare
- Clear a path to the indoor unit, the attic hatch and the outdoor unit. Move cars out of the driveway for the truck.
- Secure pets and tell the crew about alarm systems.
- Plan for heat: the AC will be off most of the day. In summer, older adults, infants and anyone with heart disease should be somewhere cool. CDC lists people 65 and older and young children among those at higher risk from heat. See heat safety without AC.
- Confirm the exact models, refrigerant, and AHRI number in writing one more time.
- Confirm who pulls the permit and when inspections will be scheduled.
- Ask whether an electrician is needed, especially for heat pumps with larger backup heat strips.
- Have a chair and outlet available for the crew near the indoor unit. Small courtesies help.
How to choose a provider
- Confirm model numbers, refrigerant type and AHRI certificate number in writing before install day.
- Confirm a permit will be pulled and who schedules inspections.
- Clear access to the indoor unit, attic hatch and outdoor unit.
- Ask the crew whether they will braze with nitrogen, pressure test and use a micron gauge.
- Ask to see the final micron reading and charge readings.
- Check the drain pan, overflow protection and labeled drain lines.
- Get the startup sheet with pressures, temperatures, superheat or subcooling, static pressure and amp draw.
- Get the AHRI certificate, permit number and Manual J.
- Confirm warranty registration in writing and verify it online.
- Get the final bills-paid affidavit (Texas) or contractor's final payment affidavit (Florida).
- Hold part of the payment until the system runs and paperwork is complete.
- Log indoor temperature and humidity for the first week.
Related ac and heating guides
- How to Choose an AC Contractor: Vetting, Reviews, Insurance and Questions to Ask
- What Size AC Do I Need? Manual J, Tonnage Myths and the Rule-of-Thumb Trap
- AC Warranties Decoded: Manufacturer Registration, Parts vs Labor and Why Claims Get Denied
- Do You Need a Permit to Replace an AC in Texas or Florida? Rules by City, Who Pulls It, and What Inspectors Check
- R-22, R-410A, R-454B and R-32: What Does the Refrigerant Transition Mean for You in 2026?
- Are Your Attic Ducts Leaking? How to Test, Seal or Replace Ductwork in Texas and Florida Heat
- How Do You Compare AC Replacement Quotes? A Line-by-Line Checklist for Texas and Florida
- How Much Does a New AC or Heat Pump Cost in 2026? What a Fair Texas or Florida Quote Includes
AC and heating by state and city
Questions people ask
Can I stay home during an AC installation?
Yes, most homeowners do. Expect noise, open doors, and the system off for most of the day. Keep children and pets away from the work areas, especially the attic hatch and outdoor unit. In summer, plan a cool room with a portable fan or a place to go during the hottest hours. The crew will usually need you at the start to confirm the plan and at the end for the walk-through and paperwork.
Do I need to replace my line set and indoor coil?
Usually the indoor coil, yes, because the indoor and outdoor units must be a matched, rated combination, and Florida requires that match to be verified. Reusing a line set is sometimes allowed if it is the right size, in good condition, and properly flushed, and if the manufacturer permits it for the new refrigerant. Ask your contractor to explain why it is reusing or replacing each part, and get it in writing.
Is a new thermostat required?
Not always, but many new systems work best with a thermostat that matches their stages and controls. Variable-speed and communicating systems may need the manufacturer's own control to deliver full features. Heat pumps need a thermostat configured for heat pump and auxiliary heat. If you keep your old thermostat, ask the installer to confirm it is compatible and set up correctly.
What if the inspector fails my install?
The contractor fixes the listed items and schedules a reinspection, normally at no extra cost to you if the failure was the contractor's fault. Get a copy of the inspection result from your city's portal. Do not make the final payment until the system passes. A failed inspection that is never corrected leaves an open permit, which can cause problems when you sell the home.
Can I install an R-410A system in 2026?
Yes, if the equipment was made or imported before January 1, 2025. EPA's May 26, 2026 rule, effective July 27, 2026, removed the earlier installation deadline for those pre-2025 residential split systems. New equipment built since 2025 uses lower-GWP refrigerants such as R-454B or R-32. R-410A for future repairs is expected to rise in price as the HFC phasedown continues, which EPA itself acknowledged.
Does the installer have to do a Manual J load calculation?
In Florida, the energy code requires residential heating and cooling equipment to be sized with ACCA Manual S using Manual J or another approved method, and many permit offices ask for the sizing data. In Texas, requirements depend on the energy code your city has adopted and enforces. Either way, ask for one. Replacing an old unit with the same size without checking often repeats past mistakes.
How soon should I change the filter after install?
Check it after the first week or two, especially if construction dust was stirred up or ducts were modified. After that, follow the manufacturer's schedule. ENERGY STAR recommends inspecting, cleaning or changing filters monthly, especially during heavy use. Write the filter size inside the air handler door or on your phone.
Should I pay the full amount on install day?
Your contract controls, but it is reasonable to pay the balance once the system runs, you have the startup readings and warranty registration, and the permit is in progress, or to hold a small final amount until the final inspection passes. Paying by credit card adds dispute rights. In Florida, ask for the contractor's final payment affidavit, and in Texas the final bills-paid affidavit, when you make the last payment.
Sources
- ACCA Quality Standards (ACCA 5 QI, ACCA 4 QM, QIVP)
- UpCodes: 2023 Florida Energy Conservation Code, Residential (R4)
- UpCodes: 2023 Florida Energy Conservation Code, Existing Buildings (R5)
- UpCodes: 2023 Florida Mechanical Code Ch. 3
- Fla. Stat. 553.912 (Air conditioners)
- Fla. Stat. 553.791 (Private provider inspections)
- 10 CFR 430.32 Energy conservation standards
- EPA Technology Transitions HFC Restrictions by Sector
- Federal Register: Technology Transitions Reconsideration Rule, May 26, 2026
- EPA SNAP: Residential and Light Commercial AC and Heat Pumps
- EPA Prohibition on Venting Refrigerants
- TDLR ACR FAQ
- Houston Permitting Center: Mechanical Inspections
- City of Jacksonville: Residential Permits
- CPS Energy HVAC Rebate Specifications
- Austin Energy AC Rebates
- ENERGY STAR Maintenance Checklist
- ENERGY STAR Duct Sealing
- EPA: A Brief Guide to Mold, Moisture and Your Home
- IRS: Energy Efficient Home Improvement Credit
- IRS: One Big Beautiful Bill Provisions
- Texas Property Code Ch. 53
- CDC: About Heat and Your Health
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.