How Do Small Businesses Plan, Permit and Hire for a Commercial Tenant Build-Out in Texas or Florida?
A plain-English guide to leasing and building out office, retail and restaurant space: TI allowances and work letters, delivery conditions, contractor licensing, certificates of occupancy in Houston and Dallas, and the Texas TDLR accessibility review most small businesses miss.
A tenant build-out is the construction that turns leased commercial space into your working business. The lease and its work letter decide who designs, builds and pays, often through a tenant improvement allowance. You need permits and a certificate of occupancy before opening, and a change of use can trigger fire, restroom and accessibility upgrades. In Texas, projects of $50,000 or more must be submitted to TDLR before the permit and inspected within a year. Florida requires a licensed building or general contractor.
Key facts
- Texas requires plans for privately funded public accommodations and commercial facilities to be submitted to TDLR when estimated construction cost is at least $50,000 (Gov. Code s. 469.101).
- In Texas, the owner may not apply for a building permit or start construction before the plans are submitted to TDLR (Gov. Code s. 469.102).
- Texas projects subject to TDLR review must be inspected for accessibility no later than one year after completion (Gov. Code s. 469.105).
- TDLR says projects under $50,000 need not be registered but must still comply with the Texas Accessibility Standards.
- Under federal ADA rules, both the landlord and the tenant of a public accommodation are responsible, and they may allocate duties by lease (28 CFR 36.201(b)).
- ADA path-of-travel costs above 20% of the primary function alteration are deemed disproportionate (28 CFR 36.403(f)).
- Houston requires every commercial tenant or owner to have a valid certificate of occupancy before occupying a space.
- Dallas requires a new certificate of occupancy for a change of use, a change of tenant, or a change in floor area; the general CO fee is $375.
- In Florida, a residential contractor license does not cover commercial buildings; commercial work needs a building or general contractor.
- Florida's s. 713.10 can protect a landlord's interest from tenant-improvement liens if the lease prohibits them and is properly recorded before the notice of commencement.
What is a commercial tenant build-out?
A tenant build-out (also called a tenant improvement, TI, or finish-out) is the construction that turns leased commercial space into a working office, store, clinic, salon or restaurant. It can be as small as new paint, carpet and a reception desk, or as large as new walls, restrooms, plumbing, ductwork, a storefront and a commercial kitchen.
Build-outs are different from home remodeling in four ways that catch small-business owners off guard:
- The lease controls almost everything: who designs, who builds, who pays, what you must remove when you leave.
- The building code treats your use as an "occupancy." Changing from one occupancy type to another (say, retail to restaurant, or office to medical) can trigger new fire, plumbing, restroom and exit requirements.
- Accessibility law applies. Commercial spaces open to the public must meet federal ADA rules, plus the Texas Accessibility Standards or the Florida Accessibility Code.
- You need a certificate of occupancy (CO), or the local equivalent, before you open.
This guide is for small-business tenants, landlords and property managers in Texas and Florida. It is general information, not legal advice. Have a real estate attorney review your lease and work letter before you sign.
Shell, vanilla shell and second-generation space: what are you actually leasing?
The condition of the space when the landlord hands you the keys (the "delivery condition") decides how much you have to build. The terms below are common in Texas and Florida listings, but they have no legal definition. Your lease should spell out exactly what is included.
| Term | What it usually means | What you usually still build |
|---|---|---|
| Cold dark shell (or gray shell) | Structure, roof, exterior walls, a slab, utilities stubbed to the space. Often no ceiling, no HVAC distribution, no restrooms | Nearly everything inside: walls, HVAC, electrical distribution, restrooms, ceilings, lighting, finishes |
| Warm shell | Shell plus some base systems, such as HVAC unit, electrical panel, sometimes restrooms and fire sprinkler mains | Interior walls, distribution of HVAC and power, finishes |
| Vanilla shell (white box) | Finished, painted perimeter walls, a ceiling grid and lights, HVAC, restrooms, basic electrical, concrete floor ready for flooring | Your layout, flooring, specialty systems and branding |
| Second-generation space | A space already built out by a previous tenant, often the same type of business | Repairs, cosmetic updates, and anything the code requires because of your use or your alterations |
| Turnkey | The landlord builds the space to an agreed plan and delivers it ready for you | Furniture, equipment, signage and anything outside the agreed plan |
A second-generation restaurant can save months and a large share of the cost if the grease trap, hood and walk-in cooler work for you. It can also hide problems: an old hood that does not meet current code, a grease trap that is too small, or restrooms that were never brought up to accessibility standards. Have your contractor and, if needed, a design professional walk the space before you sign. See restaurant build-out guide and medical office build-out.
Who pays for tenant improvements? TI allowances and turnkey deals
The lease decides. The three common structures are:
| Structure | How it works | Watch out for |
|---|---|---|
| Tenant improvement (TI) allowance | The landlord agrees to pay up to a set amount, often stated per square foot, toward your build-out. You or your contractor build it, and the landlord pays or reimburses against invoices and lien releases | What costs the allowance covers (design fees, permits, cabling, signage, furniture); when it is paid; what happens to unused allowance; deadlines to use it |
| Turnkey | The landlord designs and builds to an agreed plan at its cost, and you move in | The plan and specifications must be detailed; changes you request are usually at your cost; delivery date and penalties for late delivery |
| As-is | You take the space in its current condition and pay for all work | Hidden code problems, landlord approval rights over your plans, restoration obligations at move-out |
A larger TI allowance is not free money. Landlords often recover it through higher rent over the lease term. If the lease ends early, the lease may require you to repay the unamortized part. Compare offers on total occupancy cost over the full term, not just the allowance.
What is a work letter?
A work letter is the lease exhibit that governs the build-out. A good one answers:
- Delivery condition of the space, with a list of base building items the landlord provides
- Who hires the architect and contractor, and whether you must use the landlord's approved list
- Plan approval process and response times for the landlord
- The TI allowance amount, eligible costs, draw procedure and documents required for each payment (invoices, lien waivers)
- Who pays for cost overruns and code-required upgrades discovered during design
- Landlord supervision or management fees on tenant-managed work
- Construction rules: work hours, freight elevator use, noise, roof access, shutdowns of building systems
- Insurance and indemnity required from your contractor
- The rent commencement date and what happens if permits or construction run late
- Which improvements stay and which you must remove when the lease ends
Can I use my own contractor, or must I use the landlord's?
It depends on the lease. Many landlords allow tenants to hire their own contractor but require landlord approval, proof of license and insurance, and use of the landlord's designated contractors for work that touches building systems such as the fire alarm, fire sprinkler, roof or energy management. Some landlords require their own general contractor for all work, especially in office towers and malls.
Typical landlord contractor requirements
- A current state license (Florida) or city registration and state trade licenses (Texas)
- Certificates of insurance for commercial general liability, workers' compensation and auto, often naming the landlord and property manager as additional insureds
- Building rules acknowledgment and a pre-construction meeting
- Lien waivers with each payment and a final release before the allowance is paid
- Closeout documents: as-built drawings, permits, inspection sign-offs, warranties, and the certificate of occupancy
Ask for the landlord's contractor rules before you sign the lease, not after. They can add cost and time. See contractor insurance requirements.
Do I need a licensed contractor for a commercial build-out?
Florida
Yes. Commercial work in Florida requires a contractor licensed under chapter 489 for that scope. A residential contractor's license is limited to one-, two- and three-family residences, so it does not cover a store or office. A building contractor may work on commercial buildings and residential buildings up to three stories, and may do non-structural remodeling of any size building. A general contractor's license has the broadest scope. Electrical, plumbing, mechanical (HVAC), roofing and fire protection work need their own licensed contractors. An owner-builder exemption exists for a commercial building the owner uses, but only when the cost is $75,000 or less (s. 489.103). Verify any Florida license on DBPR's lookup; see Florida contractor license lookup and Florida licensing scope of work.
Texas
Texas has no state license for general contractors. Cities require registration: the City of Austin, for example, says anyone can be a general contractor in Texas without a state license, but general and trade contractors must register with the city before work tied to a permit begins, and the general contractor is responsible for activating the permit, scheduling inspections and obtaining the certificate of occupancy. Electrical, plumbing and air conditioning work require state licenses (Occupations Code s. 1305.151, s. 1301.351 and s. 1302.251). Houston's occupancy office says electrical, mechanical and plumbing permits for CO corrections must be held by a licensed contractor. See Texas contractor license requirements and Texas city contractor registration.
Permits, change of occupancy and the certificate of occupancy
Most build-outs need a building permit, plus separate trade permits. The approval you need to open is the certificate of occupancy (CO), which confirms the space meets code for your specific use.
Houston
The City of Houston says all tenants or owners of a commercial building or an individual lease space must have a valid CO, and a CO must be obtained before the space is occupied. When an existing occupancy classification changes, plans and permits must be approved to obtain a new CO for the new use. Applications go to the Occupancy Inspections section (Form CE-1045A). An inspector visits, a report listing required corrections is emailed within one week, and the applicant has 180 days to get permits and finish corrections. Single-family homes and U occupancies do not need a CO. A business operating without a posted CO can receive a 15-day notice, followed by daily citations.
Dallas
The Dallas Development Code says a person may not use or change the use of a building, part of a building or land without a CO (single-family and duplex uses excepted). A new CO is needed for a first use, a change of use, a change of tenant, or an increase or decrease in floor area. If the use is the same, inspections can be scheduled once the application is approved and paid. If the use is different, the application goes to Building Code and Zoning review and may need a site plan, floor plan and parking analysis. Fees listed on the city's page include $375 for a general CO and $500 for a temporary CO.
Austin and San Antonio
In Austin, the registered general contractor obtains the CO or certificate of completion. San Antonio's Development Services Department handles COs. Confirm current steps and fees on each city's development services site.
Florida cities
Florida building departments issue a certificate of occupancy or completion after final inspections under the Florida Building Code. Many Florida jurisdictions also require a separate local business approval, often called a Certificate of Use (CU), tied to zoning. Miami-Dade County uses CUs (its ADU page, for example, requires a renewable CU). We could not load the county's commercial CU page for this guide, so confirm CU requirements with the zoning office of your city or county.
What a change of occupancy can trigger
When the use changes, the building official reviews the space against the code for the new use. Depending on the change, that can mean:
- More or larger restrooms, based on the new occupant load
- Added exits, exit signs and emergency lighting
- Fire sprinklers or fire alarm upgrades, or rated walls between tenants
- A grease interceptor, hood and fire suppression for food service
- Ventilation, plumbing and medical gas requirements for clinics
- Accessibility upgrades to the route into and through the space
- Parking requirements tied to the new use (Dallas may ask for a parking analysis)
The local fire marshal usually reviews plans and inspects fire and life-safety systems before the CO. Ask your design professional to do a code review before you sign the lease. It is the cheapest insurance you can buy.
Permit timing tools
- Texas: Local Government Code ch. 247 (created by H.B. 14, effective September 1, 2023) lets a qualified third party review plans or conduct inspections if the city or county misses its deadline by 15 days. The authority may not charge for the third-party review or require you to waive the deadlines.
- Florida: s. 553.791 lets an owner or contractor use a licensed private provider for plan review and inspections. For commercial projects, the local fee must drop by at least 25% of the plan-review or inspection portion, and at least 50% if the private provider does all plan review and inspections.
What ADA and accessibility rules apply to a build-out?
Three layers apply to most Texas and Florida commercial spaces:
- The federal ADA (Title III). Places of public accommodation and commercial facilities must meet the 2010 ADA Standards for Accessible Design for new construction and alterations.
- State accessibility law. Texas: the Architectural Barriers Act (Government Code ch. 469) and the Texas Accessibility Standards (TAS), run by the Texas Department of Licensing and Regulation (TDLR). Florida: s. 553.503 adopts the federal ADA standards into the Florida Accessibility Code for Building Construction, part of the Florida Building Code.
- Local building code review of accessibility during permitting.
Texas: TDLR registration and RAS review for projects of $50,000 or more
This is the step many small businesses miss. Under Government Code ch. 469:
- TAS applies to privately funded buildings that are "public accommodations" or "commercial facilities" under the ADA, among others (s. 469.003).
- Plans and specifications for construction or substantial renovation of such a building must be submitted to TDLR for review and approval if the estimated construction cost is at least $50,000 (s. 469.101).
- The architect, interior designer, landscape architect or engineer responsible for the design must submit them no later than the 20th day (not counting weekends and holidays) after issuing them (s. 469.102).
- The owner may not apply for a local building permit, or let construction start, before the plans are submitted to TDLR, and must show the permit office proof of submission (s. 469.102).
- The owner must have the finished project inspected for compliance no later than one year after construction is completed, by TDLR, a contracted entity, or a Registered Accessibility Specialist (RAS) (s. 469.105).
TDLR's FAQ adds two key points. Projects under $50,000 are not required to be registered and reviewed, but they still must comply with TAS. And when a tenant pays for renovations to areas only the tenant occupies, the owner generally does not have to provide accessibility for that work unless path-of-travel elements are also altered. Projects are registered through TDLR's online TABS system. Questions go to TDLR's Architectural Barriers program.
Florida
Florida's building departments review accessibility as part of the permit under the Florida Building Code, Accessibility, which incorporates the federal standards adopted by s. 553.503. There is no separate state registration step like Texas TABS.
The 20% path-of-travel rule
Under federal ADA rules (28 CFR 36.403), when you alter a primary function area (the space where your business happens), you must also make the path of travel to it accessible, including the entrance, the route and the restrooms serving it, unless the cost is disproportionate. Costs over 20% of the alteration to the primary function area are deemed disproportionate. Even then, the path of travel must be made accessible to the extent possible without disproportionate cost, with priority in this order: an accessible entrance, an accessible route to the altered area, then at least one accessible restroom for each sex or a single unisex restroom (28 CFR 36.403(g)). Budget for it from the start.
Who is responsible for ADA compliance, landlord or tenant?
Both. Federal rules say the landlord who owns the building and the tenant who operates the public accommodation are both subject to the ADA, and that the two can allocate responsibility between themselves by lease or other contract (28 CFR 36.201(b)). That allocation binds the two of you, but a person with a disability can still bring a claim against either. In practice:
- Negotiate who fixes existing violations in common areas, parking, entrances and shared restrooms. The landlord usually controls these.
- Make the landlord confirm in the lease that the base building and common areas comply, or that the landlord will fix them.
- Make sure your work letter says who pays for path-of-travel upgrades the permit office requires.
- In Texas, agree who registers the project with TDLR and who pays for the RAS review and inspection. The statute places the inspection duty on the owner.
An attorney should review these clauses. Accessibility claims are common, and the cost of a lawsuit is far higher than the cost of a correct ramp or restroom.
How long does a commercial build-out take?
We did not find a neutral, dated study of build-out timelines to quote. The schedule is driven by these stages, each of which can be the bottleneck:
- Lease negotiation and work letter
- Test fit and code review by a design professional
- Design and construction documents
- Landlord plan approval
- In Texas, TDLR project registration and plan submission for projects of $50,000 or more (before you can apply for the permit)
- Building, trade and fire permits
- Long-lead equipment orders (HVAC units, kitchen hoods, storefront glass, electrical gear)
- Construction and inspections
- Fire marshal and final inspections, then the CO
- In Texas, the RAS inspection within one year of completion
Negotiate a rent commencement date that is tied to permit issuance or CO, not a fixed calendar date, so permit delays do not cost you rent for space you cannot use. See construction timelines and delays.
How much does a commercial build-out cost per square foot?
Costs vary more than in residential work, because a dental office, a salon and a warehouse office are entirely different projects. Commercial real estate firms publish annual fit-out cost guides; Cushman and Wakefield, for example, listed a 2026 U.S. Retail Fit Out Cost Guide dated August 2026. We could not load the figures in that guide for this page, so we do not quote per-square-foot numbers. When you read any cost guide, check:
- The year and the city
- Whether figures include design fees, permits, furniture, cabling and equipment
- The assumed delivery condition (shell or second-generation)
- The assumed quality level
What drives your number
- Delivery condition: a cold shell costs far more to finish than a vanilla shell
- Plumbing: restrooms, sinks, floor drains and grease interceptors require cutting the slab
- HVAC: added units or capacity for kitchens, server rooms or clinics
- Code upgrades triggered by change of occupancy
- Accessibility path-of-travel work (up to 20% of the primary alteration under federal rules)
- Landlord requirements: approved contractors, supervision fees, after-hours work
- Storefront, signage and specialty equipment
Get at least three bids on the same drawings and compare line by line. See how to compare contractor bids and fixed price vs cost-plus.
Do I need an architect for a tenant improvement?
For most build-outs that add walls, restrooms, plumbing, HVAC or a change of use, yes, or at least a licensed design professional. Permit offices often require sealed drawings for commercial work, and in Texas the TDLR submission duty for projects of $50,000 or more falls on the architect, interior designer, landscape architect or engineer responsible for the design. A design professional also does the code and accessibility review that tells you what the space will really cost before you commit.
Small cosmetic jobs (paint, flooring, furniture) may not need one. Ask the building department. For a comparison of delivery methods, see design-build vs architect vs general contractor.
Who owns the improvements when the lease ends?
The lease decides. Typical lease language says improvements attached to the building (walls, ceilings, plumbing, HVAC, lighting) become the landlord's property when installed or at lease end, while your movable furniture, equipment and trade fixtures stay yours. Many leases also give the landlord the right to require you to remove specific improvements and restore the space at your cost.
- Ask the landlord to state at plan approval which items you will have to remove at move-out. Get it in writing.
- Define "trade fixtures" in the lease, especially for restaurant equipment, salon stations and medical equipment.
- Budget for restoration if the lease requires it. Removing a kitchen or lead-lined X-ray room is expensive.
Liens and payment: protecting the landlord, tenant and contractor
Contractors on a build-out can file liens if they are not paid. Who is exposed depends on state law and the lease:
- Florida: under s. 713.10, a lien generally reaches only the interest of the person who contracted for the work. If a tenant improves the property under an agreement with the landlord, the lien can extend to the landlord's interest, unless the lease expressly prohibits that and the lease, a memorandum of it, or a parcel notice with the required language is recorded before the notice of commencement. The tenant must tell its contractor about that lease provision. A lienor can demand a verified copy of the provision, and if the landlord does not provide it within 30 days, the landlord's interest can become subject to the lien.
- Texas: lien rights and deadlines are set by Property Code ch. 53. Landlords commonly require lien waivers in the statutory forms with each TI payment.
Whoever is paying should collect lien waivers from the general contractor and major subcontractors with each payment and a final release before the last payment. See Florida construction lien law, Florida notice of commencement and Texas lien waivers and releases.
How to choose a provider
- Get the landlord's delivery condition in writing, with a base building item list.
- Have a design professional do a test fit and code review before signing the lease.
- Negotiate the work letter: allowance, eligible costs, draws, overruns, code upgrades and restoration.
- Tie rent commencement to permit issuance or the certificate of occupancy.
- Get the landlord's contractor rules and insurance requirements.
- Hire a properly licensed contractor (Florida) or city-registered contractor with licensed trades (Texas).
- In Texas, register projects of $50,000 or more with TDLR and submit plans before applying for the permit.
- Budget for accessibility path-of-travel upgrades.
- Apply for building, trade and fire permits; consider a private provider in Florida or third-party review in Texas if the city is late.
- Collect lien waivers with every payment and a final release at the end.
- Pass final and fire inspections and obtain the CO (and any Certificate of Use) before opening.
- In Texas, schedule the RAS inspection within one year of completion.
- Keep as-builts, permits, warranties and the CO for the landlord and future renewals.
Related general and residential contractors guides
- How Do You Build Out a Restaurant in Texas or Florida? Health Plan Review, Hoods, Grease Traps and Permits
- What Does It Take to Build Out a Medical or Dental Office in Texas or Florida?
- Design-Build vs Hiring an Architect Then a Contractor: Which Delivery Method Fits Your Project?
- Which Florida Contractor License Does Your Project Need? General vs. Building vs. Residential vs. Specialty
- Texas City Contractor Registration: Houston, Dallas, Austin, San Antonio, Fort Worth, El Paso and More
- What Insurance Should a Contractor Have? General Liability, Workers' Comp and Builder's Risk Explained
- How Do I Compare Contractor Bids Apples to Apples?
- What Should Be in a Construction Contract? A Clause-by-Clause Checklist
General and residential contractors by state and city
Questions people ask
What is a TI allowance?
A tenant improvement allowance is money the landlord agrees to contribute toward building out your space, usually stated per square foot or as a lump sum. The lease and work letter define which costs qualify, how and when the landlord pays, what documents are needed, and whether unused allowance can be applied to rent. Landlords often recover the allowance through rent over the lease term.
Do I need a TDLR registration for a small office build-out in Texas?
If the space is a public accommodation or commercial facility and the estimated construction cost is $50,000 or more, the plans must be submitted to TDLR for review, and the owner may not apply for a building permit until they are submitted. The project must also be inspected by a Registered Accessibility Specialist within one year after completion. Projects under $50,000 do not need registration but must still comply with the Texas Accessibility Standards.
What is a certificate of occupancy for a business?
A certificate of occupancy is the local government's approval that a building or space meets code for a specific use and can be occupied. In Houston, every commercial tenant or owner must have a valid CO before occupying the space. In Dallas, a new CO is required for a new use, a change of use, a change of tenant, or a change in floor area. Do not open, or sign a lease with a fixed opening date, without a plan to get the CO.
Can I start construction before the permit is issued?
No. Building without required permits is a code violation in both states, and in Texas the owner of a project subject to TDLR review may not even apply for a local permit before the plans are submitted to TDLR. Starting early can lead to stop-work orders, fines and torn-out work, and it can violate your lease.
What is the difference between a CO and a Certificate of Use?
A certificate of occupancy confirms the building or space meets the building code for its use. A Certificate of Use, used by Miami-Dade County and some other Florida jurisdictions, is a separate zoning approval for the specific business or use, and may need renewal. A space can need both. Ask your local zoning office which applies.
Can my landlord charge me for managing my build-out?
Many leases allow a landlord supervision or construction management fee on tenant-managed work, often a percentage of construction cost, and some deduct it from the TI allowance. It is negotiable before you sign. Ask for it to be capped or waived, and make sure the work letter states it clearly.
Who pays if the city requires upgrades I did not plan for?
Whoever the lease and work letter say. Landlords often want tenants to pay for any code upgrades triggered by the tenant's use or plans, while tenants want the landlord to deliver a base building that already complies. Negotiate this before you sign, and get a design professional's code review early so surprises surface before the lease is final.
Sources
- Texas Government Code ch. 469, Elimination of Architectural Barriers
- TDLR, Architectural Barriers Frequently Asked Questions
- TDLR, 2012 Texas Accessibility Standards
- 28 CFR 36.201, General (landlord and tenant responsibilities)
- 28 CFR 36.403, Alterations: path of travel
- U.S. Access Board, ADA Accessibility Standards
- Florida Statutes s. 553.503, Adoption of guidelines (accessibility) (2026)
- Florida Statutes s. 553.791, Alternative plans review and inspection (2026)
- Florida Statutes s. 489.105, Definitions (contractor scopes) (2026)
- Florida Statutes s. 489.103, Exemptions (2026)
- Florida Statutes s. 713.10, Extent of liens (2026)
- Texas Local Government Code ch. 247 (third-party review and inspection)
- Texas Property Code ch. 53, Mechanic's, Contractor's, or Materialman's Lien
- Texas Occupations Code ch. 1305 (electricians)
- Texas Occupations Code ch. 1301 (plumbers)
- Texas Occupations Code ch. 1302 (air conditioning and refrigeration contractors)
- City of Houston, Occupancy Inspections (Certificate of Occupancy)
- City of Dallas, Certificate of Occupancy
- City of Austin, Contractor Registration
- Miami-Dade County, Accessory Dwelling Units or Guesthouses (Certificate of Use reference)
- Cushman and Wakefield, 2026 U.S. Retail Fit Out Cost Guide listing
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.