How Do You Build Out a Restaurant in Texas or Florida? Health Plan Review, Hoods, Grease Traps and Permits

A restaurant build-out needs more approvals than any other tenant improvement: health department plan review, building and fire permits, a hood and fire suppression system, a grease interceptor approved by the sewer utility, and, if you serve alcohol, a location that passes distance rules. Here is the sequence for Texas and Florida.

A restaurant build-out needs health plan review before you build, a building permit, fire review of the hood and suppression system, and grease interceptor approval from the sewer utility. In Florida, DBPR's Division of Hotels and Restaurants reviews plans for new, converted, remodeled or long-closed restaurants, typically within 30 days online. In Texas, a city or county health department (such as Houston Health) reviews plans, or DSHS where no local department has jurisdiction. Check alcohol distance rules before signing a lease.

Key facts

  • Florida DBPR's Division of Hotels and Restaurants requires plan review for new establishments, conversions, remodels and reopenings after a closure of at least 18 months; online applications are typically reviewed within 30 days.
  • Florida plan review needs a completed application, a scaled floor plan with equipment and sinks labeled, and a sample menu.
  • Florida's plan review guidance requires automatic fire suppression over cooking equipment that produces grease-laden vapors and a Class K extinguisher within 30 feet of cooking equipment.
  • In Houston, plan review is required for new construction or extensive remodeling, final approval is subject to field inspection, and pre-opening inspections must be scheduled at least 14 business days ahead (Houston Health).
  • Houston's food dealer permit costs $224.44 to $739.44 depending on risk level; a grease trap generator registration is $123.54 plus a $33.56 admin fee (Houston Permitting Center).
  • Houston Code Sec. 47-512(b) requires every grease interceptor in city limits to be fully pumped at least every 90 days unless a waiver is approved; manifests must be kept 5 years.
  • Miami-Dade requires a Fats, Oils and Grease (FOG) Discharge Control Operating Permit for any non-residential facility that prepares food and may discharge grease to the public sewer; permits are not transferable to new owners.
  • Texas cities and counties may ban alcohol sales within 300 feet of a church, school or public hospital, and within 1,000 feet of a school on request (Alcoholic Beverage Code 109.33).
  • Florida bars new on-premises alcohol locations within 500 feet of a school unless locally approved, but exempts restaurants with at least 51% of gross revenue from food and nonalcoholic drinks (s. 562.45).
  • Texas privately funded public accommodations with an estimated construction cost of $50,000 or more must submit plans to TDLR for accessibility review before a building permit application is filed (Gov't Code 469.101-.102).

The restaurant build-out sequence at a glance

  1. Before you sign the lease: confirm zoning allows a restaurant, check alcohol distance rules, and have your contractor or engineer check the existing grease interceptor, hood, gas service, electrical capacity and restroom count.
  2. Design: hire a design professional to draw the floor plan, kitchen equipment layout, plumbing (including grease waste), mechanical (hood exhaust and makeup air), electrical and fire protection.
  3. Health plan review: submit the plan and menu to DBPR (Florida) or the local health department (Texas).
  4. Accessibility review: in Texas, register the project with TDLR if construction will cost $50,000 or more.
  5. Building permit: submit to the city or county building department, often with separate trade permits.
  6. Utility approvals: grease interceptor sizing and sewer discharge permits from the wastewater utility or county environmental agency.
  7. Construction and inspections: rough-ins, hood and duct, fire suppression test, final building and fire inspections.
  8. Pre-opening health inspection and food permit, then certificate of occupancy and opening.

The steps overlap, but health and utility reviews often control the schedule, so start them as early as your plans allow. For the general tenant improvement process, see commercial tenant build-outs.

Do you need health department plan review?

Florida: DBPR Division of Hotels and Restaurants

Public food service establishments in Florida are licensed by DBPR's Division of Hotels and Restaurants, and its plan review page says review is required for:

  • Newly built establishments
  • Conversions of an existing building from another use
  • Remodels
  • Reopenings after the establishment has been closed for 18 months or more

You submit a completed application, a scale floor plan with all equipment labeled (showing sink and equipment locations), and a sample menu. DBPR says online applications can expect review within 30 days. If a plan is denied and you request a variance, routine variance responses take about 90 days and emergency ones about 30. Plan review is the first step to getting the restaurant license.

Division of Hotels and Restaurants plan review contact: dhr.planreview@myfloridalicense.com, (850) 487-1395, 2601 Blair Stone Road, Tallahassee, FL 32399-1011.

DBPR is not the only reviewer. Its guidance notes the Department of Health approves septic systems and the Department of Environmental Protection approves wells for sites without public water or sewer, the State Fire Marshal or local fire authority handles fire safety, and the local building authority sets restroom fixture counts and ventilation.

Texas: your local health department, or DSHS

Texas has no single state plan reviewer for restaurants. Most large cities and many counties run their own food programs. The Texas Department of State Health Services (DSHS) publishes a Retail Food Establishments Jurisdiction Interactive Map so you can find which health department has authority over your address. Use it before you design, because rules and fees differ.

Houston is a good example of a city program. Houston Health says plans are needed for construction of a food establishment and for remodeling that changes the scope of food service. Taking over an existing permitted business without changes may not need plans; the inspector decides. You submit two sets of plans and specifications to the Houston Permitting Center's Commercial Plan Review Section at 1002 Washington Ave. (Health Department Plan Review is on the 3rd floor). Even with approved plans, final approval depends on a field inspection, and you must bring the stamped plans and schedule the pre-opening inspection at least 14 business days in advance, with a certified food manager on site.

Houston's food dealer permit costs $224.44 to $739.44 depending on low, medium or high risk level, and is valid for one year (Houston Permitting Center). Dallas, San Antonio and Austin run their own programs; check each city's health department before submitting.

What the health reviewer looks for

Florida's plan review guidance, which follows the FDA Food Code, lists requirements that also match what most Texas reviewers check:

ItemRequirement in Florida DBPR guidance
Handwash sinksSeparate sink in each food prep, warewashing and food dispensing area, with hot and cold running water under pressure, soap, hand drying and a sign
WarewashingThree-compartment sink or commercial dishmachine, with drain boards at both ends
Mop sinkUtility or custodial sink (or can wash) with hot and cold water, connected to sanitary sewer
Lighting50 foot-candles where employees work with food; 20 in self-service and handwash/warewash/restroom areas; 10 in walk-ins and dry storage
Equipment legsTabletop equipment at least 4 inches high; floor equipment at least 6 inches
StorageClean equipment, food and paper goods at least 6 inches above the floor
FinishesSmooth, nonabsorbent floors, walls and ceilings in wet areas, with coved baseboards
RefrigerationPotentially hazardous food held at 41 degrees F or colder
RestroomsAt least one public bathroom (with listed exceptions); fixture counts per local building authority; vented
Dumpsters and grease containersOn nonabsorbent surfaces such as concrete or machine-laid asphalt
Ice machinesIn enclosed, protected areas with a handwash sink nearby

Bring the equipment schedule (make, model and NSF or equivalent listing for each item) with your plans. Changing equipment after approval can require re-review; Houston tells applicants to get approval of modified plans before building something different.

What does a commercial kitchen hood system require?

Commercial cooking that produces grease-laden vapors needs an exhaust hood, grease duct and an automatic fire suppression system. The governing standard in most jurisdictions is NFPA 96, Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations, published by the National Fire Protection Association (the 2027 edition is NFPA's current edition; your fire marshal enforces the edition the state or city has adopted, which is often older). The mechanical code adopted by your jurisdiction also governs hood design and makeup air.

In plain terms, NFPA 96 and the mechanical codes deal with:

  • Type of hood: grease hoods over fryers, griddles, ranges and charbroilers; condensate or heat hoods may be allowed over dishwashers and some ovens.
  • Grease duct: liquid-tight welded duct with clearances to combustibles, cleanouts and a fire-rated enclosure where it passes through floors or ceilings.
  • Exhaust fan and discharge: roof or wall fans located away from air intakes and property lines.
  • Makeup air: fresh air to replace what the hood removes, so doors close and burners draw properly.
  • Fire suppression: an automatic system over the cooking line that shuts off fuel and power to the appliances when it discharges.
  • Cleaning and inspection: regular hood and duct cleaning and periodic suppression system service.

Florida's DBPR plan review guidance states that automatic fire suppression systems are required over cooking equipment when grease-laden vapors are produced, and that a portable Class K extinguisher must be within 30 feet of the cooking equipment. General extinguishers must be rated at least 2A10BC and within 75 feet of travel distance.

What is a UL 300 fire suppression system?

UL 300 is the Underwriters Laboratories test standard for fire-extinguishing systems that protect commercial cooking areas. Fire marshals commonly look for a system listed to it over the cooking line; confirm what your fire marshal requires. Ask the hood contractor to confirm the system's listing on your submittals. The full UL and NFPA texts are paid standards, so your designer and fire suppression contractor should work from the edition your jurisdiction has adopted.

If you take over a space with an existing hood, have it inspected before you sign: an undersized hood, missing makeup air or a non-compliant suppression system can cost as much to fix as a new installation.

What is a grease trap or grease interceptor, and who requires it?

A grease interceptor (often called a grease trap) is a tank on the kitchen drain line that lets fats, oils and grease (FOG) float and solids settle before wastewater reaches the public sewer. Small under-sink units are often called traps; large in-ground tanks are interceptors. Sizing and approval come from the plumbing code and, critically, the sewer utility or environmental agency, not the health department.

Houston

  • Owners or managers of a restaurant or food establishment with a grease trap must register as a special waste generator with Houston Health. Registration is $123.54 plus a $33.56 admin fee, renewed annually, and requires an Affidavit of Holding Capacity.
  • Under Sec. 47-512(b), every interceptor within city limits must be fully pumped at least every 90 days unless a Notice of Waiver is approved.
  • Keep waste manifests on site for five years; inspections can be unannounced. Citations for Chapter 47 violations range from $250 to $2,000 per violation.
  • Houston has proposed cutting the oil and grease discharge limit from 400 mg/L to 200 mg/L over a two-year phase-in; check whether it has been adopted before you size equipment.

Miami-Dade

  • Any non-residential facility that handles, prepares or processes food and discharges or may discharge FOG to the public sewer needs a Fats, Oils and Grease Discharge Control Operating Permit from the county (restaurants, cafeterias, supermarkets, schools, banquet halls and food courts are listed).
  • Permits are not transferable: a new owner must apply. Inside a municipality you first apply for the municipal occupational license or certificate of use, and the county's Environmental Resources Management plan review stamp is needed before the municipality finalizes the license.
  • The county says permits are mailed within about 30 days of approval and must be posted at the facility.

Other utilities (Dallas Water Utilities, San Antonio Water System, Austin Water, JEA in Jacksonville, and the Tampa and Orlando area utilities) generally set their own FOG rules; we did not verify each one. Ask the utility for its sizing method and pumping frequency in writing before your plumber designs the interceptor. In a second-generation space, have the existing interceptor pumped, inspected and its capacity confirmed; a tank sized for a cafe may be too small for a fryer-heavy menu.

What permits does a restaurant build-out need?

ApprovalTexasFlorida
Zoning / certificate of useCity zoning; some cities require a certificate of occupancy for a change of useCity or county zoning; many South Florida cities require a certificate of use
Health plan reviewLocal health department, or DSHS where it has jurisdictionDBPR Division of Hotels and Restaurants
Building permitCity building department; Local Government Code ch. 247 allows third-party review or inspection if the city misses its deadline by 15 daysLocal building department under s. 553.79; owners may use a private provider for plans review and inspections (s. 553.791)
Trade permitsPulled by state-licensed electrical, plumbing and ACR contractorsPulled by licensed Division II contractors or the GC within license scope
Fire reviewFire marshal: hood suppression, sprinklers, alarms, exitsState Fire Marshal or local fire authority
AccessibilityTDLR registration and review for projects of $50,000 or more (Gov't Code 469)Florida Accessibility Code, which incorporates the federal ADA Standards (s. 553.503)
Grease / sewerCity utility FOG program (e.g., Houston registration and quarterly pumping)County or city utility FOG permit (e.g., Miami-Dade FOG operating permit)
SignsSeparate sign permit in most citiesSeparate sign permit in most jurisdictions
AlcoholTABC permit; local distance rulesDivision of Alcoholic Beverages and Tobacco license; local zoning and school distance

Texas accessibility registration

Texas applies its accessibility standards to privately funded buildings that are public accommodations or commercial facilities under the ADA (Gov't Code 469.003). If estimated construction cost is $50,000 or more, the design professional must submit plans to TDLR within 20 days of issuing them, the owner may not apply for a building permit or start construction until they are submitted, and the owner must have the finished project inspected within one year of completion by TDLR or a Registered Accessibility Specialist (Gov't Code 469.101-.105).

Florida private providers

A Florida owner, or the contractor with written authorization, may hire a private provider for plans review or inspections. For commercial projects the local permit fee must drop by at least 25% of the plans-review or inspection portion, or at least 50% if the private provider does all of both (s. 553.791). On a schedule-driven restaurant opening this can matter. Permit basics are in Florida permits and Texas permits.

What liquor license zoning issues affect a build-out?

If alcohol is part of your plan, check location rules before you sign a lease or spend on design.

Texas

Under Alcoholic Beverage Code 109.33, a county (outside cities) or a city may prohibit alcohol sales by a business located within:

  • 300 feet of a church, public or private school, or public hospital
  • 1,000 feet of a public school, if the school board requests it
  • 1,000 feet of a private school, if the school's governing body requests it

Distance to churches and hospitals is measured along street-front property lines, front door to front door, and directly across intersections; distance to schools is measured property line to property line. Any applicant for an original permit whose public entrance is within 1,000 feet of a school must give written notice to school officials before applying (unless minors are barred from the premises). Local governments can grant variances. The Texas Alcoholic Beverage Commission (TABC) issues the permit, but the distance rule is local, so ask the city first.

Florida

Section 562.45 preserves county and city power to regulate the hours and location of alcohol licensees. It also bars a new location for on-premises consumption within 500 feet of a public or private elementary, middle or secondary school unless the county or city approves it. Restaurants licensed under ch. 509 that get at least 51% of gross revenue from food and nonalcoholic beverages are exempt from that school-distance restriction, as are premises licensed on or before July 1, 1999. Many Florida cities add their own distance rules in zoning. Confirm with the city's zoning office and the Division of Alcoholic Beverages and Tobacco.

Should you lease a second-generation restaurant space?

A second-generation space was previously a restaurant and may already have a hood, grease interceptor, walk-in cooler, gas line and restrooms. It can save months, but only if the existing systems fit your concept and current code.

CheckWhy it matters
How long has it been closed?In Florida, a reopening after 18 months or more requires plan review again
Hood size, type and suppression listingA hood sized for a sandwich shop may not cover a fryer line; outdated suppression systems may need replacement
Grease interceptor capacity and conditionUtilities size by flow and fixtures; Miami-Dade requires a new FOG permit for each new owner
Electrical service and gas meterUpgrades involve the utility and can take months
Restroom count and accessibilitySeat count drives fixture count; alterations trigger accessibility work
Existing permits and violationsOpen permits or unpermitted work can become your problem
Who owns the equipmentLeftover equipment may belong to the landlord, the prior tenant or a vendor

Get your contractor and designer into the space before you sign. Write a lease that says who pays for code upgrades the city requires when you apply for permits.

Who builds and who inspects a restaurant build-out?

Who can build it

In Florida, commercial build-outs need a licensed contractor whose scope covers the work. A building contractor may do commercial buildings up to three stories and non-structural remodeling of any size building; a general contractor's scope is unlimited (s. 489.105). Plumbing, electrical, mechanical, air conditioning and roofing must be subcontracted to licensed trade contractors unless the GC holds those licenses (s. 489.113). An owner may act as owner-builder on a commercial building for their own use only if the cost does not exceed $75,000 (s. 489.103(7)). Verify licenses on DBPR; see the Florida license lookup.

In Texas, no state license is required for the general contractor, but electrical, plumbing and air conditioning work require state licenses (Occupations Code 1305, 1301, 1302), and most cities require contractor registration to pull permits. Texas also taxes nonresidential remodeling: the total charge for remodeling or repairing nonresidential real property is taxable, while initial finish-out of new space is treated as new construction, so how your contract describes the work matters (Comptroller Publication 94-116). Ask your contractor how sales tax is handled on the bid.

Who inspects

  • Building department: framing, rough plumbing, electrical, mechanical, ceilings, final.
  • Fire marshal: hood suppression discharge test, sprinklers, alarm, exits and occupancy load.
  • Health department: pre-opening inspection against the approved plan.
  • Utility or environmental agency: grease interceptor installation.
  • Accessibility: in Texas, a Registered Accessibility Specialist inspection within one year of completion.

Florida's DBPR notes that fire safety items like emergency lighting and exit signs (required when occupancy exceeds 50 and exits are not readily visible) and outward-swinging exit doors (when occupancy exceeds 49) do not stop plan approval but can fail the fire inspection.

How long does a restaurant build-out take, and what does it cost?

Timelines depend on whether the space is first- or second-generation, how fast reviews come back, and equipment lead times. The review clocks we could confirm from primary sources:

  • Florida DBPR plan review: online applications typically reviewed within 30 days.
  • Florida plan variance after denial: about 90 days routine, 30 days emergency.
  • Houston: schedule the health pre-opening inspection at least 14 business days ahead.
  • Miami-Dade FOG permit: mailed within about 30 days of approval.
  • Texas permit delays: third-party review is available under Local Government Code ch. 247 once a city is 15 days past its deadline.
  • Texas accessibility: plans to TDLR within 20 days of issue and before the building permit application.

Add design time, building permit review, hood and walk-in fabrication, construction and inspections. Get a written schedule from your contractor that shows each approval as a separate milestone. See construction timelines and delays.

Cost: we did not find a named, dated, Texas- or Florida-specific source for restaurant build-out cost per square foot that meets our sourcing standard. Cost depends heavily on whether the hood, interceptor and restrooms already exist. Get at least three itemized bids and compare them line by line; see how to compare contractor bids and our sourced remodel cost guide.

Restaurant build-out checklist for owners and tenants

Before you hire, read how to hire a general contractor and the construction contract checklist. Then work through the steps below. Local contractor and permit context: Houston, Dallas, San Antonio, Austin, Miami, Tampa, Orlando and Jacksonville.

This page is general information, not legal advice. Confirm requirements with the health department, building department, fire marshal and sewer utility for your address.

How to choose a provider

  • Confirm zoning allows a restaurant and check alcohol distance rules before signing a lease
  • Find your health authority (Florida DBPR; Texas local health department via the DSHS jurisdiction map)
  • Have a contractor inspect any existing hood, suppression, interceptor, gas and electrical service
  • Ask the sewer utility for interceptor sizing rules and pumping frequency in writing
  • Hire a design professional for kitchen, MEP and fire protection drawings
  • Submit health plan review with floor plan, equipment schedule and menu
  • In Texas, submit plans to TDLR if construction will cost $50,000 or more
  • Apply for the building permit and trade permits; consider a private provider in Florida
  • Verify the contractor's license (Florida) or city registration and trade licenses (Texas)
  • Schedule hood suppression testing and fire inspection
  • Register the grease interceptor and set up a pumping contract and manifest file
  • Book the pre-opening health inspection early (14 business days in Houston)
  • Keep stamped approved plans on site for every inspection

Related general and residential contractors guides

General and residential contractors by state and city

Questions people ask

Do I need health department approval before building a restaurant in Florida?

Yes, in most cases. DBPR's Division of Hotels and Restaurants requires plan review for new establishments, conversions from another use, remodels, and reopenings after 18 or more months closed. Submit a completed application, a scaled floor plan showing labeled equipment and sinks, and a sample menu. DBPR says online applications are typically reviewed within 30 days.

Who does restaurant plan review in Texas?

There is no single state reviewer. Most large cities and many counties have their own health departments that review plans and permit food establishments; DSHS handles areas where it has jurisdiction. DSHS publishes an interactive jurisdiction map so you can find your health department. In Houston, plans go to the Houston Permitting Center's Commercial Plan Review Section, with Health Department review on the 3rd floor.

How often must a grease trap be pumped in Houston?

Houston Code Sec. 47-512(b) requires every grease interceptor within city limits to be fully evacuated at least every 90 days, unless the city approves a Notice of Waiver. Restaurants with a grease trap must also register annually as a special waste generator and keep waste manifests on site for five years. Citations for Chapter 47 violations range from $250 to $2,000 per violation.

Does a new restaurant owner in Miami-Dade need a new grease permit?

Yes. Miami-Dade's Fats, Oils and Grease Discharge Control Operating Permit is not transferable, so a new owner must apply even if the prior tenant had one. Any non-residential facility that prepares food and may discharge grease to the public sewer needs the permit. Inside a city, you first apply for the municipal license or certificate of use.

What is NFPA 96?

NFPA 96 is the National Fire Protection Association's Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations. It covers grease hoods, grease ducts, exhaust fans, clearances, fire suppression and cleaning for commercial kitchens. Fire marshals enforce the edition their state or city has adopted, which may be older than NFPA's current edition, so your designer should confirm the adopted edition.

How close to a school or church can a Texas restaurant sell alcohol?

Texas lets cities and counties prohibit alcohol sales within 300 feet of a church, public or private school, or public hospital, and within 1,000 feet of a school if the school requests it (Alcoholic Beverage Code 109.33). Measurement methods differ for churches and schools, and local governments can grant variances. Check with the city before signing a lease.

Do Florida restaurants face school distance rules for alcohol?

Florida bars new on-premises alcohol locations within 500 feet of an elementary, middle or secondary school unless the county or city approves it (s. 562.45). Restaurants that earn at least 51% of gross revenue from food and nonalcoholic beverages are exempt from that state restriction. Cities and counties may still have their own distance rules in zoning.

Can I build out my own restaurant as an owner-builder in Florida?

Only in limited cases. Florida's owner-builder exemption allows an owner to build or improve a commercial building for their own use only if the cost does not exceed $75,000, and the owner must directly supervise any work not done by licensed contractors. Most restaurant build-outs exceed that, and trade work still needs licensed contractors. A tenant who does not own the building is generally not the owner for this exemption.

Does Texas charge sales tax on a restaurant build-out?

It can. The Texas Comptroller treats remodeling and repair of nonresidential real property as taxable on the total charge, while initial finish-out work on new space is treated as new construction, where labor is not taxable. How the work is described matters. Ask your contractor how tax is handled in the bid and confirm with the Comptroller if the job mixes new finish-out and remodeling.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration