Local Guide · Residential solar installers
How Does Net Metering Work in Florida? PSC Rule 25-6.065, Credits, True-Up and Tiers
Florida's net metering rule lets customers of the four investor-owned utilities roll extra solar credits forward month to month, then get paid for leftovers once a year at a much lower energy rate. City utilities and co-ops write their own rules, and several pay far less.
For FPL, Duke Energy Florida, Tampa Electric and Florida Public Utilities, net metering follows PSC Rule 25-6.065. Your meter measures power you take from the grid and power you send back. Extra kWh in one month become a credit on next month's energy use. Credits carry forward up to 12 months, and at the end of each calendar year the utility pays you for unused credits at its COG-1 as-available energy rate. You still pay the monthly customer charge. Municipal utilities and co-ops set their own terms.
Key facts
- Florida PSC Rule 25-6.065, F.A.C., applies to all investor-owned utilities; it was adopted 2-11-02 and last amended 4-7-08.
- Excess kWh are credited to the next month's energy use and may carry forward for no more than 12 months; unused credits are paid at year end at an average annual rate based on the utility's COG-1 as-available energy tariff.
- Net metering customers still pay the customer charge and any demand charge, no matter how much they export (Rule 25-6.065(8)(h)).
- For inverter systems, the gross power rating is the DC nameplate times 0.85; the rule's expedited interconnection covers systems up to 2 MW and no more than 90% of your service rating.
- Tier 1 customers cannot be charged extra fees, including application fees, and cannot be required to buy liability insurance; Tier 2 insurance can be required up to $1 million and Tier 3 up to $2 million.
- Florida Statute 366.91(6) required municipal utilities and rural co-ops to create their own net metering programs, with terms set by each governing board, not by the PSC rule.
- HB 741 (2022) would have phased down IOU net metering credits starting in 2024; it passed the Legislature but the Governor vetoed it on April 27, 2022.
- The PSC's 2025 net metering report counts 319,041 solar PV interconnections statewide across 52 utilities, about 3.15 million kW AC.
- You keep the Renewable Energy Certificates from your own system (Rule 25-6.065(9)).
How does net metering work in Florida, in plain English?
Net metering is a billing method. Your solar panels power your home first. When they make more than your home is using, the extra flows out to the grid through your meter. When the panels make less, such as at night, you pull power from the grid like any other customer.
Under Florida PSC Rule 25-6.065, the utility installs, at no extra cost to you, a meter that measures both directions: electricity it delivers to you and electricity you deliver to it. Each month it reads the meter on your normal billing cycle and bills you for the net amount.
- If you used more than you sent out: you pay for the difference at your normal rate schedule.
- If you sent out more than you used: you owe nothing for energy that month, and the extra kWh become a credit against next month's energy use.
- Every month, either way: you still pay the fixed customer charge (and a demand charge if your rate has one).
Tampa Electric describes this on its bill as two numbers: kWh Delivered (from the utility to you) and kWh Received (from your panels to the utility). Your billed energy is Delivered minus Received. If the result is negative, the difference is banked for next month.
The key thing to understand is that inside a month, and across months within the year, an exported kWh is worth the same as a kWh you would otherwise buy. That is what people mean by "full retail" or "1-to-1" net metering. The big exception is what happens to leftover credits at year end, covered below.
What exactly does Rule 25-6.065 say?
The rule is titled Interconnection and Net Metering of Customer-Owned Renewable Generation. It is a Florida Administrative Code rule adopted by the Florida Public Service Commission (PSC), first adopted February 11, 2002 and last amended April 7, 2008. Here are the parts homeowners care about most, in order.
| Subsection | What it says | What it means for you |
|---|---|---|
| (1) Scope | Applies to all investor-owned utilities | FPL, Duke Energy Florida, Tampa Electric, Florida Public Utilities. Not city utilities or co-ops. |
| (2)(a) Definition | System on your premises, primarily intended to offset part or all of your own use. Third-party purchase, lease, operation or maintenance is allowed if you do not buy retail electricity from that third party. | A leased system can be net metered. A deal where you buy kWh from a company that owns panels on your roof is treated differently. |
| (2)(b) Gross power rating | For inverter systems, AC rating = DC nameplate x 0.85 | A 10 kW DC array counts as 8.5 kW for tier purposes. |
| (3) Standards | IEEE 1547, IEEE 1547.1, UL 1741 | Your inverter must be listed and must shut off when the grid goes down. |
| (4) Qualifications and fees | System no larger than 90% of your service rating; no extra fees for Tier 1 | No application fee for typical home systems. |
| (5) Agreement contents | Local code inspection before operation; 10 days' notice before turning on; insurance limits by tier | Your permit must pass final inspection first. |
| (6) Disconnect switch | Utility may require a lockable visible-break switch at your expense, but inverter-based Tier 1 systems are exempt unless the utility pays | Most home systems do not have to buy this switch. |
| (7) Timelines | Utility confirms a complete application within 10 business days and signs the agreement within 30 calendar days (90 days if a Tier 3 study is needed) | Use these dates if your utility stalls. |
| (8) Net metering | Monthly netting, 12-month credit carryover, year-end payout at COG-1 rate, customer charge still applies | The billing rules. |
| (9) RECs | Customer keeps Renewable Energy Certificates | Any environmental attributes belong to you. |
| (11) Disputes | Use PSC complaint rule 25-22.032 or formal proceedings | Your path if the utility will not follow the rule. |
You can read the full rule text at the Florida Administrative Code site (flrules.org) under Rule 25-6.065. It is short, about four pages, and worth reading before you sign a solar contract.
What are Tier 1, Tier 2 and Tier 3?
The rule sorts systems into three tiers by gross power rating, measured in AC. These are the same tier bands utilities publish in their interconnection materials; for example, the Orlando Utilities Commission's application page lists them this way.
| Tier | Gross power rating (AC) | Rough DC array size (AC divided by 0.85) | Liability insurance the utility may require | Fees |
|---|---|---|---|---|
| Tier 1 | Up to 10 kW | Up to about 11.7 kW DC | None may be required (utility may recommend it) | No fees beyond what any customer pays, including no application fee |
| Tier 2 | Over 10 kW to 100 kW | About 11.8 to 117 kW DC | Up to $1 million | PSC-approved application fee allowed |
| Tier 3 | Over 100 kW to 2 MW | About 118 kW to 2.35 MW DC | Up to $2 million | Application fee plus possible interconnection study charge |
Example: A Tampa homeowner installs 32 panels rated 400 watts each. That is 12,800 watts, or 12.8 kW DC. Multiply by 0.85 and the gross power rating is 10.88 kW AC. That lands in Tier 2, so the utility may ask for proof of liability insurance (up to $1 million) and may charge a PSC-approved application fee. Dropping to 29 panels (11.6 kW DC, 9.86 kW AC) would keep the system in Tier 1.
This is why your installer's proposal should state both the DC size and the AC gross power rating. If a quote lands just over 10 kW AC, ask whether the extra panels are worth the Tier 2 paperwork and insurance. Many homeowner policies already carry personal liability coverage; check the amount with your agent before assuming you need to buy more.
Municipal utilities and co-ops often use similar tier bands but set their own fees. OUC, for example, lists no fee for Tier 1, $340 for Tier 2 and $1,300 for Tier 3, and requires proof of insurance only for Tier 2 and Tier 3 applications.
What happens to my excess solar credits at the end of the year?
This is the most misunderstood part of Florida net metering. Rule 25-6.065(8)(e) and (f) set up a two-stage system:
- Month to month: extra kWh you export in a billing cycle are credited against your energy use in the next billing cycle. These credits keep rolling forward and can offset usage in later months, for a period of not more than 12 months.
- Year end: at the end of each calendar year, the utility pays you for any unused energy credits at "an average annual rate based on the investor-owned utility's COG-1, as-available energy tariff."
The COG-1 rate is the utility's as-available energy rate, a price based on the energy cost the utility avoids when it takes your power. It is an energy-only value. It does not include the delivery, fixed and other costs built into the retail price you pay per kWh, so expect it to be well below your retail rate. Each utility's COG-1 tariff is on file with the PSC and on the utility's tariff pages; ask your utility for the current figure.
What that means in practice: credits are worth full retail value when they cancel out your own later use, but much less once they are cashed out. Florida homes tend to bank credits in spring and use them in the hot, high-use months. A system sized to cover your yearly use will mostly cancel out its own credits. A system sized well beyond your use builds a pile of credits that gets paid out at the low year-end rate.
The PSC's own data shows this. In its 2025 net metering report, FPL customers delivered about 783 million kWh to the grid during the year, yet FPL's reported payments to customers totaled about $1.71 million. Most exported energy was used up as bill credits, and only leftovers were paid in cash.
FPL's own page puts it simply: excess energy "is deducted from your monthly bill or credited toward a future bill within the same calendar year."
What if I move or close my account?
Rule 25-6.065(8)(g) says when a customer leaves the system, unused credits are paid at the same COG-1-based average annual rate. If you sell your home in October with a big credit balance, you get paid for those kWh at the low rate, not retail. Plan the timing of a move with that in mind, and see our guide to selling a home with solar.
Do I still pay a monthly bill with net metering?
Yes. Rule 25-6.065(8)(h) says that regardless of how much energy you send to the grid, you continue to pay the applicable customer charge and any applicable demand charge. Tampa Electric calls this the basic service charge. Most residential rates do not have a demand charge, but all have a fixed monthly customer charge.
Your bill also carries taxes and fees that are figured by your local government and the utility. Some of these are tied to the dollar amount of your bill and fall as your energy charges fall. Others are fixed. So even in a month where your panels covered every kWh, expect a small bill.
If a salesperson told you that you would "never pay another electric bill," that was wrong. One Florida utility, OUC, answers that exact question on its FAQ page: customers are billed the electric customer charge at minimum each month, plus other services such as water or waste where OUC provides them, plus taxes.
How to read your first net metering bill
- Find the two meter readings: energy delivered to you and energy received from you.
- Check the net kWh. If it is negative, look for a credit carried forward line.
- Check the customer charge. It should be the same as before solar.
- Compare your system's monitoring app with the "received" number. They will differ, because your home used part of the solar production directly before it reached the meter. Also, the app's dates usually run by calendar month while your billing cycle does not.
For a full walk-through of every line, see your electric bill after solar, explained.
How do I get net metering? The bidirectional meter swap
Net metering is not automatic. FPL states that you must apply to become a net metering customer before installing, and it then replaces your meter with one that measures excess power supplied to the grid. The general sequence under the rule is:
- Contract and design. Your solar contractor designs the system and pulls the building and electrical permits.
- Application. You or your contractor submit the utility's interconnection application. The utility must give written notice within 10 business days that the application is complete or explain what is missing, and within 10 business days of a complete application must confirm receipt and give inspection dates.
- Agreement. The utility must sign the Standard Interconnection Agreement within 30 calendar days of a completed application (90 days if a Tier 3 study is needed). You sign and return it.
- Local inspection. Rule 25-6.065(5)(a) requires the system to be inspected and approved by local code officials before it runs in parallel with the grid.
- Notice and meter. You must notify the utility at least 10 days before placing the equipment in service. The utility installs or reprograms the bidirectional meter at no extra cost.
- Permission to operate. Only turn the system on when the utility confirms it is approved. Running it early can export power without proper metering or credits.
If you later add panels that raise the gross power rating, the rule requires a new application at least 30 days before the change. For more on each step, see interconnection and permission to operate and Florida solar permits.
Does net metering apply to JEA, OUC, Gainesville and co-ops?
Not the PSC rule's billing terms. Florida Statute 366.91(5) told investor-owned utilities to build net metering programs under PSC rules. A separate subsection, 366.91(6), required each municipal electric utility and rural electric cooperative to create its own standardized interconnection agreement and net metering program by July 1, 2009, with the details set by that utility's own governing board.
So the 12-month carryover and year-end COG-1 payout described above apply to FPL, Duke Energy Florida, Tampa Electric and FPUC customers. City utilities and co-ops can, and do, choose different credit values. Examples from utility pages loaded November 19, 2026:
| Utility | How exports are credited |
|---|---|
| JEA (Jacksonville) | Under JEA's Distributed Generation Policy, energy sent to the grid earns a credit at JEA's fuel rate, calculated as kWh sent to JEA times the fuel rate. You pay standard rates for energy you buy. Credits above the bill accrue through the calendar year, and any remaining balance is paid at year end. DG customers cannot enroll in JEA MyWay. |
| OUC (Orlando) | Systems connected or approved on or before June 30, 2025 keep the full retail rate through June 30, 2045. Customers interconnected on or after July 1, 2025 are credited at the Community Solar Energy Rate for five years (through June 30, 2030), then at the retail levelized fuel rate. A grace period paid full retail through October 31, 2026; changes took effect November 1, 2026, when OUC also retired its "solar bank" and began crediting dollar value immediately, with leftover credits rolling to the next bill. |
| Other municipal utilities and co-ops | Set by each board. Ask for the written net metering or distributed generation policy before signing a contract. |
The difference is large. Under a fuel-rate credit, each exported kWh is worth only the fuel part of the price. That makes self-use far more valuable than export and changes how big a system should be. See Florida utility solar programs and our Jacksonville and Orlando guides.
The PSC still collects data from every utility. Its 2025 report lists 52 utilities with customer solar: investor-owned utilities account for 254,916 of the state's 319,041 solar PV interconnections, municipal utilities 31,405 and rural cooperatives 32,720.
Can a battery be net metered in Florida?
A battery can be connected to the grid alongside solar, but it is not a renewable generator in its own right, so it does not earn net metering credits for power it pulls from the grid and pushes back. Tampa Electric says it plainly: batteries are interconnected but not net metered.
Under full retail net metering, a battery does not add bill savings the way it would under a low export rate, because the grid already gives you full value for exported kWh within the year. A battery's main value for an FPL, Duke or TECO customer is backup power during outages. Under a fuel-rate credit such as JEA's, or OUC's newer rates, storing your own daytime solar for evening use can add more value. OUC offers a battery rebate, but customers must give up eligibility for its TruNet full retail export rate to get it. Read the terms closely. See batteries for hurricanes and outages.
Will Florida end net metering? The HB 741 story
In 2022 the Legislature passed CS/CS/HB 741. The House passed it 83 to 31 on March 2, 2022 and the Senate on March 7, 2022. According to the House's final bill analysis, it would have:
- Started a new IOU net metering program on January 1, 2024.
- Reduced how much each exported credit offset usage, based on the date your application was approved: 75% for approvals in 2024 and 2025, 60% in 2026, and 50% in 2027 and 2028.
- Let customers approved before January 1, 2029 keep the design that applied when they were approved for 20 years.
- Required the PSC to adopt a new program design for approvals after January 1, 2029.
- Allowed IOUs to petition for fixed charges, grid access fees or minimum bills on solar customers.
The Governor vetoed HB 741 on April 27, 2022. It never took effect. Rule 25-6.065, with full retail monthly netting, remains the rule for investor-owned utilities.
Could it change again?
Yes. The Legislature can pass a new law, and the PSC can amend its rule through public rulemaking. Neither has changed the IOU rule since 2008 as of the rule's history on flrules.org. If the rules change, HB 741 shows one model lawmakers have considered: grandfathering existing customers for a set period. Nothing guarantees that a future change would do the same. Watch the PSC's docket notices and the Legislature's session each spring.
Meanwhile, some municipal utilities have already moved away from full retail, as OUC did for new applicants after June 30, 2025.
Can a leased or third-party-owned system be net metered?
Yes, with a limit. Rule 25-6.065(2)(a) says customer-owned renewable generation does not stop the customer from contracting for the purchase, lease, operation or maintenance of an on-site system with a third party, as long as the terms do not include the retail purchase of electricity from the third party. In plain terms: a lease, where you pay for the equipment, fits the rule. A contract where you buy kWh from the panel owner raises a different question under Florida law, because selling retail electricity is generally reserved to utilities. If a salesperson offers a per-kWh agreement in Florida, ask in writing how it complies with Rule 25-6.065(2)(a) and get the answer reviewed. See lease vs PPA vs ownership.
How to file a complaint if your utility won't follow the rule
Rule 25-6.065(11) points disputes to the PSC's customer complaint rule (25-22.032) or a formal proceeding. Common problems are slow application reviews, delays in the meter swap, and billing that does not show carried-forward credits.
- Write down the dates: application submitted, completeness notice, agreement signed, local inspection passed, notice of in-service date.
- Compare them with the rule's timelines (10 business days, 30 calendar days).
- Call the utility's net metering or interconnection team and ask for a written answer.
- If unresolved, file a complaint with the Florida Public Service Commission through floridapsc.com. For municipal utilities and co-ops, start with the utility's own governing board or customer service, since their net metering terms are set locally.
For problems with the solar company rather than the utility, see how to file a solar complaint in Texas or Florida.
How to choose a provider
- Confirm whether your utility is an investor-owned utility (FPL, Duke Energy Florida, Tampa Electric, FPUC) or a municipal utility or co-op.
- If municipal or co-op, get the written net metering or distributed generation policy and the current export credit rate.
- Ask your installer for both DC size and AC gross power rating (DC x 0.85) and which tier it falls in.
- Size the system near your annual use so credits are used, not cashed out at the year-end COG-1 rate.
- Make sure the interconnection application is filed before installation.
- Do not turn the system on until local inspection passes and the utility gives approval.
- Check your first bill for kWh delivered, kWh received and credit carryover.
- Plan move dates knowing that unused credits are paid at the low as-available rate when you close the account.
- Keep copies of the application, agreement and inspection record for a future buyer.
Related residential solar installers guides
- Is Solar Worth It in Florida in 2026? Savings, Net Metering and Hurricane Reality
- Florida Utility Solar Rules: How Do FPL, Duke, TECO, JEA, OUC and the Co-ops Treat Rooftop Solar?
- What Size Solar System Do I Need? How Many Panels for a Texas or Florida Home
- What Is Solar Permission to Operate, and How Long Does Interconnection Take?
- Why Do I Still Have an Electric Bill With Solar, and How Do I Read It in Texas and Florida?
- Solar Batteries for Hurricanes and Grid Outages: What They Power and for How Long
- Selling or Buying a Home With Solar Panels: Owned, Leased and PPA Systems
- How Do Texas Solar Buyback Plans Work Without Net Metering?
Residential solar installers by state and city
Questions people ask
Does Florida still have full net metering in 2026?
For customers of the investor-owned utilities, yes. Rule 25-6.065 still nets your exports against your use each month at full value and carries extra credits forward up to 12 months. The only part paid at a lower rate is leftover credit at year end or when you close your account. The 2022 bill that would have phased this down (HB 741) was vetoed. City utilities and co-ops set their own rules, and some, such as JEA and newer OUC customers, credit exports at lower rates.
Do Florida utilities pay cash for excess solar?
Investor-owned utilities pay cash, or a bill credit, only for credits left unused at the end of the calendar year, or when you leave the system. The payment is at an average annual rate based on the utility's COG-1 as-available energy tariff, which is an energy-only value and well below retail. During the year, excess kWh are used to offset your future usage instead.
Is there an application fee for net metering in Florida?
Not for Tier 1 systems (up to 10 kW AC) on investor-owned utilities. Rule 25-6.065(4)(e) bars any fee beyond what regular customers pay, including application fees. Tier 2 and Tier 3 systems may be charged a PSC-approved application fee, and Tier 3 may face an interconnection study charge. Municipal utilities set their own fees; OUC lists $340 for Tier 2 and $1,300 for Tier 3.
Do I need extra insurance for net metering in Florida?
For a Tier 1 system on an investor-owned utility, no. The utility may recommend liability insurance but cannot require it. Tier 2 systems can be required to carry up to $1 million in general liability coverage, and Tier 3 up to $2 million. Separately, tell your homeowners insurer about the system so the panels are covered as part of the home. See our solar homeowners insurance guide.
Is Florida net metering grandfathered?
The current IOU rule has no end date, so there is nothing to grandfather yet. If the rule changes, past proposals such as HB 741 would have let existing customers keep their terms for 20 years, but no such protection exists in law today. Some municipal utilities have grandfathered existing customers in their own changes: OUC keeps full retail through June 30, 2045 for systems connected or approved by June 30, 2025.
Can I sell my excess solar to a neighbor in Florida?
No. Net metering credits are applied to your own account. The rule's definition of customer-owned generation also excludes arrangements where a third party sells you retail electricity. If you want to support solar without panels, utility community solar subscriptions are a separate product. See our community solar guide for Texas and Florida.
What happens to net metering when I sell my Florida home?
Your unused credits are paid out at the COG-1-based rate when you close the account. The buyer usually has to apply or sign an interconnection agreement in their own name to keep net metering. JEA, for example, requires a new owner to complete a form and sign an interconnection agreement to move to a PV rate. Under OUC's rules, buyers who took possession after June 30, 2025 do not inherit the old full retail rate.
What is the COG-1 rate?
COG-1 is the name of the as-available energy tariff that investor-owned utilities file with the PSC. It sets the price paid for energy delivered by small producers on an as-available basis, based on the utility's avoided energy cost. Rule 25-6.065 uses an average annual COG-1 rate to pay for year-end unused credits. Ask your utility for the current value; it changes with fuel and energy costs.
Does net metering reduce my customer charge?
No. Rule 25-6.065(8)(h) says the customer charge and any demand charge apply regardless of exports. Credits offset energy charges only, not fixed charges. That is why even a home that produces more than it uses over a month still receives a small monthly bill for the customer charge plus taxes and fees.
Sources
- Florida Administrative Code Rule 25-6.065 (full text)
- Florida Administrative Code Rule 25-6.065 (rule history)
- Florida Statutes 366.91, Renewable energy
- Florida House final bill analysis, CS/CS/HB 741 (2022)
- Florida PSC 2025 Net Metering Report
- FPL: Net Metering
- Tampa Electric: Solar incentives and net metering
- Tampa Electric: net metering and rate eligibility
- JEA: Distributed Generation
- JEA: Distributed Generation bill breakdown
- OUC: How to apply for solar at your home
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.