Local Guide · Residential solar installers
Do I Need a Solar Permit in Texas? Houston, Dallas, San Antonio, Austin and Rural Areas
What Texas solar permits require city by city, why county rules differ, how SolarAPP+ and the 2025 third-party review law (SB 1202) work, and what to do if your installer never pulled a permit.
Inside Texas cities, rooftop solar almost always needs permits: Houston requires structural and electrical permits with a Texas engineer's sealed letter, and Austin requires an Auxiliary Power electrical permit plus an Austin Energy inspection. Unincorporated county areas usually have no building permit for existing homes, but TDLR licensing and utility interconnection still apply. Since September 1, 2025, SB 1202 lets licensed third parties review and inspect home backup power installations, with cities issuing approval within three business days.
Key facts
- Houston requires structural and electrical permits for any PV system; its permit lists a $91.06 fee plus a $33.56 administrative fee, with plan review at 25% of the permit fee.
- Houston accepts SolarAPP+ for eligible residential systems since July 15, 2024, except where design wind speed is 140 mph or greater.
- All solar, battery and interconnected generator projects in Austin Energy territory need an Auxiliary Power electrical permit through the AB+C portal.
- The 2026 NEC became the Texas state electrical code on September 1, 2026.
- SB 1202 (89th Legislature, effective Sept. 1, 2025) lets master electricians and other qualified third parties review and inspect home backup power installations; cities must issue approval within three business days of the notice.
- SB 1252 (2025) bars cities from regulating installation or inspection of home backup systems up to 50 kW or 100 kWh; city-owned utilities still may.
- Texas county building standards (Local Gov't Code 233.153) apply only to new homes and large additions in counties that adopt them, and do not require prior county approval.
- Texas solar contracts must commit the retailer or contractor to obtain permits and interconnection approval (Occ. Code 1806.155).
Do I need a permit for solar panels in Texas?
Inside a city, almost always yes. Texas cities enforce building and electrical codes, and a rooftop solar system involves both: it adds weight and wind load to your roof and connects a power source to your home's wiring. Houston, for example, requires at minimum a structural permit and an electrical permit for any photovoltaic system, issued under the same project number. Austin requires an Auxiliary Power electrical permit for every solar system, battery system or interconnected generator in Austin Energy territory.
Outside city limits, the answer is different. Texas counties have limited authority over building construction, and the main county building code law applies only to new homes and large additions (see the county section below). But even where no building permit is required:
- the work must still be done by a TDLR-licensed electrical contractor (with a narrow exception for some owner-occupants);
- the electric utility still requires an interconnection application and approval before you turn the system on, and some utilities ask for a city or county inspection permit as part of that paperwork; and
- floodplain, HOA deed restrictions and, on the coast, windstorm certification rules can still apply.
Under the 2025 Texas solar sales law, a contract that includes installation must commit the retailer or contractor to obtain the permits and utility interconnection approval (Occupations Code 1806.155). Permitting is your installer's job, but you should check that it actually happened.
Which codes apply: the state rules every Texas city starts from
| Code area | State rule | What it means for solar |
|---|---|---|
| Electrical | TDLR adopts each new National Electrical Code (NEC) as the state electrical code (Occupations Code 1305.101). The 2026 NEC took effect statewide on September 1, 2026 (16 TAC 73.100), with a limited exception for some outdoor GFCI requirements. | NEC Article 690 (PV systems), 705 (interconnection) and 706 (batteries) govern the wiring. Cities can require inspections and collect permit fees (1305.201). Note that city guides may still list an older edition; Houston's solar guide lists the 2023 NEC with Houston amendments. |
| Residential building | The International Residential Code (IRC) as it existed on May 1, 2012 is the baseline municipal residential code (Local Government Code 214.212). Cities may adopt later editions and local amendments by ordinance after a public hearing. | Roof loads, attachments and wind design. Houston's solar guide references the 2021 IRC. |
| Fire | Adopted locally (for example, Houston lists the 2021 International Fire Code) | Roof access pathways and spacing around arrays (IFC Section 1205 in Houston's guide). |
| Home backup systems | SB 1252 (2025): cities may not adopt NEC amendments or local rules regulating installation or inspection of residential energy backup systems up to 50 kW or 100 kWh; city-owned utilities still may | Applies to batteries and backup systems. See below. |
| Third-party review | Local Government Code ch. 247 (HB 14, 2023, and SB 1202, 2025) | Lets qualified third parties review plans and inspect home backup power installations. See below. |
City-by-city: Houston, Dallas, San Antonio and Austin
Each city runs its own process. The table summarizes what we could confirm from each city's or utility's official pages as of November 2026. Where we could not confirm a detail, we say so. Always check the current checklist with the city before relying on it.
| City | Who issues the permit | Portal | Codes cited | Typical documents |
|---|---|---|---|---|
| Houston | Houston Public Works, Houston Permitting Center (Building Code Enforcement and Electrical Inspections) | iPermits (application and fees) and ProjectDox (plans) | 2021 IRC or IBC, 2023 NEC, 2021 IFC, with Houston amendments | Owner declaration checked against HCAD records, site plan, roof plan, Texas PE sealed structural letter and calculations, electrical plans per NEC 690 and 705, spec sheets, wind speed printout |
| Dallas | Development Services, Building Inspection (Permitting and Inspections) | DallasNow (all permits are submitted through it) | Not confirmed; Dallas moved its codes page to a new City Codes and Ordinances page | Not confirmed; ask Building Inspection for the current residential solar checklist |
| San Antonio | City of San Antonio Development Services Department | Not confirmed (the city's solar page was not reachable when we checked) | Not confirmed | Not confirmed; CPS Energy's old rebate manual noted building permits are required in some municipalities in its service area |
| Austin | City of Austin Development Services, with Austin Energy inspecting the solar system | Austin Build + Connect (AB+C) | City codes plus Austin Energy design and interconnection rules | Residential Auxiliary Power electrical permit, Distributed Generation Planning Application (DGPA), wire diagram or design packet, interconnection agreement |
Houston solar permits in detail
Houston publishes one of the most detailed solar checklists in the state: the Solar Photovoltaic Panel Permit and Inspection Guide and Checklist (Form CE-1198). Key points:
Before you apply
- Check deed restrictions with your civic association or county property records for rules about panel placement.
- Properties in the floodplain, a historic district or designated areas near an airport face additional requirements.
- An interconnection application must be submitted directly to CenterPoint Energy for approval, with subsequent inspection approval, before installation starts.
Application and fees
- Structural and electrical permits are both required, under the same project number. A registered licensed electrician must buy the electrical permit.
- Applications go through iPermits; plans are uploaded to ProjectDox. Contractors must register their license with the City of Houston.
- A signed Declaration Supporting Building Permit Application must match Harris Central Appraisal District (HCAD) ownership records, or you must upload proof of ownership.
- The city's solar panel permit page lists a $91.06 fee plus a $33.56 administrative fee. The guide adds a plan review fee of 25% of the permit fee, and the permit page notes valuation-based plan review may apply depending on scope.
What the plans must show
- Cover sheet and code analysis listing the codes used (2021 IRC or 2021 IBC, not both, plus 2023 NEC, 2021 IFC and Houston amendments).
- A scaled site plan from a survey, showing easements and setbacks; no equipment may encroach into easements.
- A scaled roof plan with panel layout, roof penetrations and rail and mount locations relative to rafters, with an anchorage detail.
- Structural letters, calculations and details sealed by a Texas professional engineer (PE), including a sealed letter that the existing structure can carry the system or plans showing added framing.
- Wind design for the specific address using IRC Table R301.2(1) or IBC 1609.3 and a printout from the ASCE 7 hazard tool.
- Electrical plans signed and sealed by a licensed electrician or Texas engineer, showing NEC Article 690 compliance, with panels listed to UL 1703, plus labels per NEC 690, 691 and 705 and a one-line diagram.
- Dimensioned roof access pathways and spacing per 2021 IFC Section 1205.
- Calculations showing how the system was sized.
Plans marked "preliminary" or "not for construction" are returned without review. New or unusual products may need an alternative method submittal (Houston handout CE-1103).
Houston inspections
- The licensed electrical contractor schedules the inspection when work is complete.
- The contractor must be on site with one of the solar panels, the drawings and paperwork. The inspector checks labels, listings and whether the installation matches the approved plans.
- The structural engineer provides a special inspection letter certifying the completed installation matches the approved design (Houston also offers Form CE-1387 as a post-install letter template).
Contacts listed in the guide: Structural Inspections (832) 394-8840; Electrical Inspections (832) 394-8860; Plan Review questions (832) 394-8820, solarpanels@houstontx.gov.
Austin solar permits in detail
In Austin, the permit and the utility inspection are linked, because Austin Energy is city-owned. Austin Energy's Solar Permitting Manual (May 2026 version) says all solar distributed generation systems, energy storage systems and interconnected spinning generators in Austin Energy territory require an Auxiliary Power Electrical Permit, applied for through the Austin Build + Connect (AB+C) portal. Contractors must be registered with the city to apply.
Which permit path
- Typical rooftop panels on a home: a Residential Auxiliary Power electrical permit. The city lists it as a stand-alone permit for registered contractors that does not require formal plan review.
- Solar shingles or ground-mounted systems inside city limits: City of Austin Residential Plan Review with engineer-stamped plans, a building permit and city inspection. The Auxiliary Power permit falls under the building permit.
- Projects in the ETJ or outside city limits (but in Austin Energy territory): a Residential Auxiliary Power permit; no City of Austin building permit, though other electrical permits may be needed for service work.
- Solar and batteries can be on the same Auxiliary Power permit.
Documents
- A Distributed Generation Planning Application (DGPA), required for all Auxiliary Power permits.
- A wire diagram or design packet.
- An interconnection agreement, now required for all residential projects, reviewed by Austin Energy before the permit is activated.
Austin Energy adds its own reviews when a project's solar plus battery output is 25 kW-ac or more, connects to the Downtown Network, includes a battery, or is commercial. A contractor that fails Austin Energy's DG plan review more than twice pays a re-review fee for the third review.
Inspections
Austin Energy says every solar system in its service area must pass a final solar inspection before it can be turned on. Solar companies request inspections through AB+C, and both the company and customer get emails when the inspection is received, scheduled, passed or failed. Any related service repair or upgrade permit must be closed before the final solar inspection. Austin Energy Solar Inspections: 512-482-5346.
Dallas and San Antonio: what to ask
We could not confirm a current, published residential solar checklist for Dallas or San Antonio from official pages in November 2026. Here is what we could confirm and how to fill in the gaps.
Dallas
Dallas Development Services says all permits are submitted through its DallasNow portal. The city's building construction codes page has moved to a new City Codes and Ordinances page. Most of Dallas is served by Oncor, which requires an interconnection application through its DG portal (see our PTO guide). Ask Building Inspection:
- Which permit types a rooftop solar system needs (electrical only, or electrical plus building).
- Which IRC and NEC editions and local amendments apply.
- Whether a Texas PE structural letter is required.
- Which inspections are required and how to schedule them.
San Antonio
San Antonio's Development Services Department issues building and trade permits. CPS Energy, the city-owned utility, runs its own interconnection process. Its 2019 rebate program manual noted that building permits are required for PV installations in some municipal jurisdictions within the CPS service territory, and required systems over 25 kW-AC to have signed and sealed drawings by a Texas professional engineer for that program. That manual is dated, so confirm current rules with both the city and CPS Energy. San Antonio has 1,497 kWh per kW of yearly solar potential at a standard south-facing tilt, per PVWatts, so it is worth getting the process right.
For both cities, ask your installer for the permit number and look it up yourself.
Do unincorporated Texas county areas require solar permits?
Often there is no county building permit for adding solar to an existing home, but check before assuming. Here is why.
Texas counties do not have the broad building code powers cities have. The main county building code law, Local Government Code Chapter 233, Subchapter F, applies only in counties that have adopted it by order, and only to new residential construction: a new single-family house or duplex, or an addition that increases the existing home's square footage or value by more than 50%. The law also says it may not be read to require prior county approval before construction begins, and the county may not charge a fee to enforce these standards (233.153). In those counties, the builder arranges inspections by qualified third parties, such as licensed engineers or certified inspectors (233.154). A rooftop solar system on an existing home is not "new residential construction" under that definition.
What can still apply outside city limits
- A city's extraterritorial jurisdiction (ETJ). If a city has adopted a building code in its ETJ, that code controls there (233.153(c)). Austin Energy, for example, requires an Auxiliary Power permit for solar in the ETJ within its service area.
- County development permits for other work. Travis County, for example, has a permit process for solar on existing non-residential structures, solar requiring extra impervious cover, and solar farms, including floodplain and drainage review.
- Floodplain rules. Counties administer floodplain management. Building in a mapped floodplain can trigger requirements.
- Your electric utility. The utility still requires interconnection approval. A 2022 ERCOT-posted TDU matrix said AEP Texas asks for a city or county inspection permit with the interconnection paperwork. Electric co-ops set their own rules.
- Licensing. TDLR licensing applies statewide whether or not a permit exists.
- Deed restrictions and HOAs. See our HOA solar rights guide.
Is SolarAPP+ used in Texas?
Yes, at least in Houston. SolarAPP+ is automated plan review software developed with the National Laboratory of the Rockies (formerly NREL). It checks a standard rooftop design against code and issues an approval instantly, so eligible projects can skip traditional plan review.
The Houston Permitting Center began allowing licensed contractors registered with SolarAPP+ and the city to use it for residential PV permits on July 15, 2024. Key limits:
- It is for standard systems on existing one- and two-family homes. Large commercial projects still need regular plan review.
- Projects in areas where the basic design wind speed is 140 mph or greater (a windborne debris region) are not eligible and must use the traditional plan review process.
- Only licensed contractors registered with both SolarAPP+ and the City of Houston can use it. The contractor uploads the SolarAPP+ confirmation into iPermits.
We could not confirm SolarAPP+ adoption in Dallas, San Antonio or Austin from official pages as of November 2026. Austin's typical residential rooftop permit is already a stand-alone electrical permit without formal plan review. Ask your city whether it accepts SolarAPP+.
Texas law now also allows automated review in another way: under SB 1202 (2025), a qualified third party reviewing a home backup power installation may use software designed to automate the review without additional manual review.
Texas third-party review and inspection laws (HB 14 and SB 1202)
Two recent laws in Local Government Code Chapter 247 can speed up permits when a city is slow. Note: some sources call SB 1202 a 2023 law. The bill that passed is SB 1202 of the 89th Legislature, signed June 20, 2025 and effective September 1, 2025. A 2023 bill with the same number was about nursing home generators and died in committee.
HB 14 (2023): the general backstop
If a city or other regulatory authority does not approve, conditionally approve or disapprove a development document by the 15th day after its legal deadline, the review may be done by a qualified third party, such as a licensed engineer or a reviewer employed by another political subdivision approved by the authority. The same applies if the authority does not perform a required inspection by the 15th day after its deadline; an ICC-certified building inspector or licensed engineer may do it (247.002). The authority may not charge a fee for the third-party review or inspection (247.003).
SB 1202 (2025): home backup power installations
SB 1202 added Section 247.0025 for "home backup power installations," defined as an electric generating facility, an energy storage facility, a standby system and associated equipment that powers a one- or two-family home and connects at 600 volts or less. The bill's legislative subject listing includes solar energy. Under the law:
- A TDLR-licensed master electrician, an electrical inspector, or a person qualified under 247.002 may review the plans and perform the inspection without first submitting them to the city.
- Cities must post on their websites each law, rule, standard and fee schedule needed for the review, or provide it within two business days of a request. If a city has not posted or provided a fee schedule, it may not charge a fee for the approval.
- Reviewers may use automated review software.
- The reviewer must send the city the results within 15 days of completing the work, along with copies of documents and reports.
- The city must issue the approval, permit or certification by the third business day after receiving the approval notice.
- Construction may begin when the approval notice for the plans is submitted.
- The city is not liable for the third party's review, and the reviewer is liable for negligent acts.
- The law does not limit an electric utility's tariff or a co-op's or city-owned utility's interconnection and service policies.
How cities are implementing this varies, and whether a given rooftop solar project qualifies depends on how the definition is applied. Ask your installer whether it uses the SB 1202 path and get a copy of the third-party approval and the city's permit.
SB 1252 (2025): limits on city rules for home backup systems
TDLR explains that SB 1252, effective September 1, 2025, covers "residential energy backup systems": backup systems at a home capable of providing no more than 50 kW of electricity or with storage capacity of no more than 100 kWh. A city may not adopt or enforce an amendment to the NEC, or any ordinance, rule or other measure, that would regulate the installation or inspection of such a system. A municipally owned utility (such as Austin Energy or CPS Energy) may still regulate installation or inspection within its service area. TDLR notes that all non-exempt electrical work, including backup system work, must still be done by TDLR-licensed electricians.
For solar buyers, this matters mostly when a battery is part of the project. Your solar panels are still subject to the city's building and electrical permit rules, and your utility's interconnection rules still apply. See our home battery guide.
Do I need a structural engineer's letter?
In Houston, yes: the city requires a sealed letter from a Texas professional engineer stating the existing structure with the proposed system complies with structural code requirements, or sealed plans showing the added framing needed. The engineer must also provide a special inspection letter after installation. Houston's checklist says structural design must follow the Texas Engineering Practice Act and the building official's requirements, whichever is stricter.
In Austin, engineer-stamped plans are required for ground-mounted systems and solar shingles inside city limits. In other cities, rules differ, and many require engineering for some roofs or wind zones. Even where not required, an engineer's letter is worth asking for if your home is older, has an unusual roof, or sits in a coastal wind zone.
Coastal homes: TDI windstorm certification
If your home is insured for wind and hail by the Texas Windstorm Insurance Association (TWIA), roof work including solar needs windstorm inspection and certification through the Texas Department of Insurance. TDI says that when a project includes a full or partial re-roof plus solar, only one professional engineer or inspector may file the application for the entire scope. TDI's windstorm intake team handles WPI-8 certificate questions at windstorm@tdi.texas.gov or 800-248-6032, option 3.
What inspections happen for a Texas solar install?
| Inspection | Who does it | What it checks |
|---|---|---|
| Rough inspection (if wiring will be covered) | City or utility inspector | Wiring before walls or roof finishes cover it. Austin Energy offers rough and pre-wire inspections. |
| Final electrical inspection | City electrical inspector (Austin Energy in its territory) | Installation matches approved plans; labels and listings; NEC compliance |
| Structural sign-off | City structural inspection, or engineer's special inspection letter (Houston) | Attachments and load path match the engineered design |
| Third-party inspection (SB 1202 path) | Licensed master electrician, electrical inspector or other qualified person | Same code compliance, reported to the city |
| Windstorm inspection (TWIA areas) | Engineer or TDI-appointed inspector | Wind resistance of roof and solar work for WPI-8 certification |
| Utility review | TDU or city-owned utility | Interconnection paperwork, metering, disconnect and labeling |
Inspections are scheduled by the contractor in most cities. In Houston, the licensed electrical contractor must be present with a panel, the drawings and paperwork.
What fire code setbacks apply?
Fire codes require clear pathways on the roof so firefighters can move, ventilate and work safely. Houston's guide requires dimensioned roof plans showing access, pathways and spacing compliant with 2021 International Fire Code Section 1205 (Solar Photovoltaic Power Systems). The exact pathway widths depend on the code edition, roof layout and local amendments, so ask the installer to show the pathways on the roof plan and cite the code section.
Separately, the electrical code requires rapid shutdown of rooftop PV wiring. On one- and two-family homes, the rapid shutdown switch must be outside the building at a readily accessible location (NEC 690.12(C)). Expect your inspector to look for it and its label.
How long do Texas solar permits take?
It depends on the city, the permit path and how complete the application is. What the official sources say:
- Houston: standard residential projects using SolarAPP+ skip traditional plan review. Other projects go through electronic plan review; the city's permit page lists processing as "subject to online processing or in person sales window."
- Austin: typical rooftop systems use a stand-alone electrical permit without formal plan review, after the city's acceptance review and any Austin Energy reviews.
- SB 1202 path: once a qualified third party submits an approval notice, the city must issue the permit or approval within three business days.
- HB 14 backstop: if the city misses its deadline by 15 days, a third-party review or inspection is allowed.
- Incomplete applications: Local Government Code 245.002(e) lets an agency treat a permit application as expired 45 days after filing if required documents are missing, the agency sent written notice of what is missing within 10 business days, and the applicant did not provide it in time.
Utility interconnection runs on its own clock. Under PUC Rule 25.211, utilities covered by the rule target four weeks from a completed application for pre-certified equipment.
Can I look up my solar permit online?
Yes, in the large cities. Ask your installer for the permit or project number, then check it yourself.
- Houston: iPermits for permits and inspection scheduling; ProjectDox for plan review status.
- Austin: Austin Build + Connect (AB+C). Austin Energy also emails the customer when an inspection is requested, scheduled, passed or failed.
- Dallas: DallasNow. Dallas also publishes a public data dashboard of single-family residential permits.
- San Antonio: check with the Development Services Department.
Look for: permit type (structural and electrical, or Auxiliary Power), status (issued, active, finaled), inspection results, and the contractor named on the permit. The contractor on the permit should match the licensed electrical contractor named in your contract.
What if my installer never pulled a permit?
This happens, and it can cause real problems: the utility may refuse interconnection, your insurer may question a claim, and a buyer's inspector may flag it when you sell.
- Check the record. Search the city portal by address. Ask the city's permit office if you cannot find it.
- Ask the installer in writing for the permit number and inspection results. In Texas, contracts that include installation must commit the retailer or contractor to obtain permits and interconnection approval (Occ. Code 1806.155).
- Keep the system off if it has not passed inspection and received utility permission to operate.
- Get an after-the-fact permit. Cities generally allow a permit to be pulled for completed work, with an inspection, sometimes with extra fees. A licensed electrical contractor must pull the electrical permit. Some work may need to be opened up for inspection.
- File complaints. TDLR takes complaints against electrical contractors for solar work at any time, and against solar retailers for contracts signed on or after September 1, 2025. TDLR: 1-800-803-9202. For older sales issues, the Texas Attorney General's consumer protection office.
Under Occ. Code 1806.201, allowing installation by anyone who is not an electrical contractor is a prohibited act for solar retailers, and TDLR can order cancellation of a solar agreement and a refund after notice and hearing (1806.207). See our complaints guide.
Can I install solar myself in Texas?
Possibly, but with limits. The Texas Electrical Safety and Licensing Act exempts "work not specifically regulated by a municipal ordinance that is performed in or on a dwelling by a person who owns and resides in the dwelling" (Occ. Code 1305.003(a)(6)). Inside cities, ordinances usually do regulate electrical work. Houston, for example, requires a registered licensed electrician to purchase the electrical building permit for a PV system.
Outside city limits, an owner-occupant may have more room, but the utility still controls whether you can connect to the grid, and many utilities require certified equipment, a signed application, diagrams and inspection evidence. Mistakes on grid-tied systems can endanger utility workers. If you plan a DIY build, talk to your utility first and consider hiring a licensed electrical contractor for the final connection. See our off-grid solar guide for systems that do not connect to the grid.
How to choose a provider
- Confirm whether your address is inside city limits, in a city's ETJ, or unincorporated.
- Check HOA or deed restrictions before design.
- Ask the installer which permits it will pull (structural, electrical, Auxiliary Power) and whether it uses SolarAPP+ or the SB 1202 third-party path.
- Make sure the contract names the TDLR-licensed electrical contractor and commits to permits and interconnection (Occ. Code 1806.155).
- In Houston, expect a Texas PE sealed structural letter, wind design printout and a CenterPoint interconnection application before installation.
- In Austin, confirm the Residential Auxiliary Power permit, DGPA, wire diagram and interconnection agreement are filed in AB+C.
- If coastal and insured by TWIA, confirm one engineer or inspector will file the TDI windstorm application for the full scope.
- Get the permit number and look it up on the city portal.
- Do not turn the system on until the final inspection passes and the utility grants permission to operate.
- Keep copies of permits, inspection results, engineer letters and the PTO letter for insurance and resale.
Related residential solar installers guides
- What Is Solar Permission to Operate, and How Long Does Interconnection Take?
- Does Texas Require a Solar License? TDLR Electrician Rules and Who Can Install
- HOA Solar Rules in Texas and Florida: What Your HOA Can and Cannot Do
- How Do I Choose a Solar Installer in Texas or Florida?
- Can Solar Panels Survive a Hurricane? Wind Ratings, Codes and What Fails
- Solar Permits in Florida: Miami-Dade, Tampa, Orlando, Jacksonville and Statewide Rules
- How Big a Home Battery Do You Need? Sizing, Chemistry, Safety Codes and Costs in Texas and Florida
- Texas Utility Solar Rules: How Do Austin Energy, CPS Energy, Co-ops, Oncor, CenterPoint and Non-ERCOT Utilities Treat Rooftop Solar?
Residential solar installers by state and city
Questions people ask
Do I need a permit for solar panels in Houston?
Yes. Houston requires both a structural permit and an electrical permit for any PV system, under one project number, plus an interconnection application to CenterPoint Energy before installation starts. Plans need a Texas professional engineer's sealed structural letter, wind design for your address, and NEC-compliant electrical drawings. Eligible standard rooftop systems on one- and two-family homes can use SolarAPP+ instead of traditional plan review, except where the design wind speed is 140 mph or more.
What does Austin require for a solar permit?
Austin Energy territory requires an Auxiliary Power electrical permit for every solar, battery or interconnected generator project, applied for in the Austin Build + Connect portal by a city-registered contractor. Residential applications need a Distributed Generation Planning Application, a wire diagram and an interconnection agreement. Solar shingles and ground mounts inside city limits also need residential plan review with stamped plans and a building permit. Austin Energy must pass a final solar inspection before the system turns on.
Do Texas counties require solar permits?
Usually not for adding solar to an existing home in an unincorporated area, because county building code authority under Local Government Code Chapter 233 covers only new homes and large additions in counties that opt in. But a nearby city's ETJ rules, county floodplain rules, utility interconnection requirements, deed restrictions and TDLR licensing can still apply. Some utilities ask for a city or county inspection permit with the interconnection application, so check with yours.
Is SB 1202 a 2023 law?
No. The Texas law allowing third-party review and inspection of home backup power installations is SB 1202 of the 89th Legislature, signed June 20, 2025 and effective September 1, 2025. It added Section 247.0025 to the Local Government Code. A different 2023 bill numbered SB 1202 dealt with emergency generators at nursing facilities and did not pass. The general third-party backstop in Section 247.002 came from HB 14 in 2023.
How long does a Texas solar permit take?
Timelines vary by city and permit path. Houston's SolarAPP+ path skips traditional plan review for eligible systems. Austin's typical rooftop permit is a stand-alone electrical permit without formal plan review. Under SB 1202, once a qualified third party submits an approval, the city must issue the permit within three business days. Utility interconnection is separate; PUC Rule 25.211 targets four weeks from a completed application for pre-certified equipment.
What happens if I install solar without a permit?
You risk being unable to get utility permission to operate, problems with insurance claims, and issues when you sell the home. The city may require an after-the-fact permit and inspection, which can mean opening up work and paying extra fees. If your installer was supposed to pull the permit and did not, Texas contracts must commit the retailer or contractor to obtain permits, and you can complain to TDLR.
Who can pull a solar electrical permit in Texas?
Generally a TDLR-licensed electrical contractor registered with the city. Houston says a registered licensed electrician must purchase the electrical building permit, and Austin requires contractors to register with the city before applying in AB+C. Texas law has a narrow exemption for an owner who lives in the home doing work not specifically regulated by a municipal ordinance, but most cities regulate electrical work.
Does a battery need its own permit in Texas?
It is usually part of the solar permit. Austin lets solar and batteries share one Auxiliary Power permit, and adds an Austin Energy plan review when a battery is included. SB 1252 bars cities from adopting their own rules regulating installation or inspection of home backup systems up to 50 kW or 100 kWh, but city-owned utilities can still regulate them, and TDLR-licensed electricians must still do the work.
Sources
- Houston Permitting Center: Solar PV permit and inspection guide and checklist (CE-1198)
- Houston Permitting Center: Solar panel permit (HPWCODE1119)
- Houston Permitting Center: SolarAPP+ for streamlined solar panel permitting
- Houston Permitting Center: SolarAPP+ pilot program (2022)
- Austin Energy: Solar Permitting Manual (May 2026)
- Austin Energy: Solar inspections
- City of Austin Development Services: Types of permits
- City of Dallas: Permitting and Inspections
- City of Dallas: Building construction codes (moved page)
- CPS Energy Solar Rebate Program Manual (rev. 2019)
- Travis County: Solar on an existing structure
- Texas SB 1202, 89th Legislature, enrolled text
- Texas SB 1202 (89R) bill history
- Texas SB 1202 (88R) bill history
- Texas Local Government Code Chapter 247
- Texas Local Government Code Chapter 233
- Texas Local Government Code Chapter 214 (Sec. 214.212)
- Texas Local Government Code Chapter 245
- TDLR: SB 1252 changes to residential energy backup system regulations
- TDLR: Commission adopts 2026 NEC
- Texas Occupations Code Chapter 1305
- Texas Occupations Code Chapter 1806
- TDLR: Residential Solar Retailers, what is in effect
- TDLR: Residential solar retail sales now regulated by TDLR
- TDI Windstorm Inspections Program newsletter (Apr. 2023)
- ERCOT-posted REP solar questions, TDSP matrix (Aug. 2022)
- PUC Texas Substantive Rule 25.211
- Mike Holt: NEC 690.12 rapid shutdown
- PVWatts v8 API result, San Antonio
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.