How Does Florida's Chapter 558 Construction Defect Notice Work, Step by Step?

Florida requires owners and associations to serve a written notice of claim and allow inspection and an offer before suing a contractor, designer or supplier over construction defects. This guide gives every Chapter 558 deadline for homeowners and for associations, the 4-year limitations period, the 7-year statute of repose after the 2023 change, and how to write the notice.

Under Florida Statutes chapter 558, you must serve a written notice of claim that refers to chapter 558 at least 60 days before suing over a construction defect (120 days for an association representing more than 20 parcels). The contractor may inspect within 30 days (50 for large associations) and must give a written response within 45 days (75). You then have 45 days to accept or reject any offer in writing. Serving the notice pauses the 4-year limitations period but not the 7-year statute of repose.

Key facts

  • A claimant must serve written notice of claim referring to ch. 558 at least 60 days before filing an action, or at least 120 days for an association representing more than 20 parcels (s. 558.004(1)(a)).
  • The person served may inspect within 30 days after service, or 50 days for a large association; destructive testing requires mutual agreement and written notice (s. 558.004(2)).
  • The person served may forward the claim to subcontractors, suppliers or design professionals within 10 days (30 for large associations), who must respond within 15 days (30) (s. 558.004(3)-(4)).
  • The person served must give the claimant a written response within 45 days after service, or 75 days for a large association: an offer to repair, an offer to pay, a combination, a dispute, or a statement that its insurer will decide within 30 days (s. 558.004(5)).
  • A claimant who receives a timely settlement offer must accept or reject it in writing within 45 days; suing without doing so lets the court stay the case (s. 558.004(7)).
  • Serving a ch. 558 notice tolls the statute of limitations but does not toll any statute of repose (s. 558.004(1)(d), (10)).
  • Florida's limitations period for construction claims is 4 years, and the statute of repose is 7 years from the earliest of a temporary CO, CO, certificate of completion or abandonment (s. 95.11(3)(b)).
  • SB 360 (ch. 2023-22, approved April 13, 2023) cut the repose period from 10 to 7 years and switched the start date from the latest to the earliest triggering event.
  • Chapter 558 applies to post-completion defect claims on improvement agreements made after October 1, 2009, unless the parties agreed in writing to opt out (s. 558.005(1)).

What is Florida Chapter 558?

Chapter 558 of the Florida Statutes, titled Construction Defects, is a mandatory notice and opportunity to repair process. Before a property owner, later buyer or association sues (or starts arbitration) over damage caused by a construction defect, it must tell the responsible party in writing, let that party inspect, and consider any offer to repair or pay. The goal is to settle defect disputes without litigation.

If you skip the process and file anyway, the court must stay (pause) your case on a timely motion until you comply (s. 558.003). Nothing is lost permanently, but you lose time and leverage.

Key definitions

  • Construction defect: a deficiency in the design, specifications, surveying, planning, supervision, observation of construction, or construction, repair, alteration or remodeling of real property resulting from defective materials or components; a code violation that supports a claim under s. 553.84; a design that fails professional standards of care at the time of approval; or a failure to build or remodel according to accepted trade standards for good and workmanlike construction (s. 558.002(5)).
  • Action: a civil suit or arbitration for damage to or loss of real or personal property caused by a defect. Personal injury claims and administrative actions are not covered (s. 558.002(1)).
  • Claimant: a property owner, including a subsequent purchaser or an association. Contractors, subs, suppliers and design professionals are not claimants (s. 558.002(3)).
  • Who can be served: contractors, subcontractors, suppliers and design professionals, meaning licensed architects, landscape architects, engineers, surveyors, geologists and registered interior designers (s. 558.002(6)-(11)).
  • Service: certified mail with USPS proof of delivery or attempted delivery to the last known address, hand delivery, or courier with written proof of delivery (s. 558.002(9)).

Does Chapter 558 apply to my claim, including a remodel?

Chapter 558 applies when all of these are true:

  • The claim is for damage to real or personal property caused by a construction defect (not personal injury).
  • The defect arose after completion of the building or improvement. "Completion" means a certificate of occupancy (temporary or otherwise) for the entire building or improvement, or an equivalent authorization; where none is issued, substantial completion according to the plans and specifications (s. 558.002(4)). The notice is not required for a project that has not reached completion (s. 558.003).
  • The agreement to make the improvement was made after October 1, 2009, and the parties did not agree in writing to opt out (s. 558.005(1)).

Remodels count. The definition of construction defect expressly includes repair, alteration and remodeling, and the definition of contractor covers anyone legally engaged in designing, developing, constructing, manufacturing, repairing or remodeling real property. A completed kitchen remodel, roof replacement, window installation or room addition can be a ch. 558 claim.

Mid-project problems are different. If the job is still underway, ch. 558 does not stand in the way of completing the project or dealing with the contractor under the contract. See how to fire a contractor and contractor abandoned the job.

Step by step: the Chapter 558 process and deadlines

Step 1: Serve the notice of claim

Serve a written notice of claim at least 60 days before filing any action, or at least 120 days before filing if the claim involves an association representing more than 20 parcels. The notice must refer to chapter 558. If the defect claim arises from work done under a contract, serve the person you contracted with (usually your general contractor or builder) (s. 558.004(1)(a)). You may also serve subcontractors, suppliers or design professionals as applicable.

The statute asks claimants to try to serve within 15 days after discovering a defect, but missing that target does not bar a lawsuit (s. 558.004(1)(c)).

Step 2: Inspection

Within 30 days after service (50 days for a large association), the person served is entitled to a reasonable inspection of the property or each unit involved. You must give reasonable access during normal working hours, and the inspector must coordinate to minimize the number of inspections. An association's right of access for maintenance or repair includes authority to grant access for the inspection (s. 558.004(2)).

Step 3: Forwarding to others

Within 10 days after service (30 days for large associations), the person served may forward a copy of your notice to each sub, supplier or design professional it believes is responsible, naming the specific defect for each. That forwarding is not an admission. Each of them may inspect, and must serve a written response on the person who forwarded the claim within 15 days (30 days) of receiving it (s. 558.004(3)-(4)).

Step 4: The written response to you

Within 45 days after service (75 days for large associations), the person served must serve you a written response containing one of these (s. 558.004(5)):

  1. An offer to remedy the defect at no cost to you, with a detailed description of the repairs and a timetable.
  2. An offer to settle by money payment, with a timetable for payment.
  3. An offer combining repairs and payment, with details and timetables.
  4. A statement that it disputes the claim and will not repair or pay.
  5. A statement that a monetary payment, including any insurance proceeds, will be determined by its insurer within 30 days after notice to the insurer. If the insurer does not respond within those 30 days, you are treated as having met all pre-suit conditions.

If the response disputes the claim, or no response arrives in time, you may file suit without further notice (s. 558.004(6)).

Step 5: Accept or reject (45 days)

If you receive a timely settlement offer, you must accept or reject it by serving written notice within 45 days after receiving it. If you file suit without accepting or rejecting, the court must stay the case on timely motion until you do (s. 558.004(7)).

Step 6: Repairs or payment

If you accept a repair offer, give reasonable access during normal working hours to perform the repair on the agreed timetable. If the offeror does not pay or repair within the agreed time and manner, apart from reasonable delays outside its control such as weather, materials, your own actions or permits, you may sue without further notice. If it performs as agreed, you are barred from suing on the claim described in the notice (s. 558.004(8)).

Chapter 558 deadlines: homeowners vs large associations

StepStandard claimantAssociation representing more than 20 parcelsStatute
Serve notice before filing suitAt least 60 daysAt least 120 days558.004(1)(a)
Target to serve after discovering defect15 days (not a bar)15 days (not a bar)558.004(1)(c)
Inspection by person servedWithin 30 days of serviceWithin 50 days558.004(2)
Forward to subs, suppliers, designersWithin 10 days of serviceWithin 30 days558.004(3)
Their response to the forwarding partyWithin 15 days of receiving itWithin 30 days558.004(4)
Written response to claimantWithin 45 days of serviceWithin 75 days558.004(5)
Insurer decision (if that option is chosen)30 days after insurer notified30 days558.004(5)(e)
Claimant accepts or rejects offerWithin 45 days of receiptWithin 45 days558.004(7)
Limitations tolled untilLater of 90 days after service or 30 days after end of accepted repair/payment periodLater of 120 days after service or 30 days after end of accepted period558.004(10)
Document exchange on requestWithin 30 days of a written request citing s. 558.004(15)Within 30 days558.004(15)

Associations here include condominium, cooperative, homeowners' and mobile home park associations as defined in chapters 718, 719, 720 and 723 (s. 558.002(2)). For condominium boards, also see condo unit renovations and milestone inspections; defects found in a milestone inspection or structural integrity reserve study may become ch. 558 claims.

How to write a Chapter 558 notice of claim

The statute sets the content (s. 558.004(1)(b)):

  • Describe in reasonable detail the nature of each alleged defect and, if known, the damage or loss it caused.
  • Identify the location of each defect well enough for the responding party to find it without undue burden, based on at least a visual inspection by you or your agents.
  • You have no obligation to do destructive or other testing for the notice.
  • Refer to chapter 558.

Practical template (adapt it; not legal advice)

"NOTICE OF CLAIM UNDER CHAPTER 558, FLORIDA STATUTES. To: [contractor name and address]. Property: [address]. Contract dated [date] for [work]. Certificate of occupancy or completion dated [date]. The undersigned owner gives notice of the following construction defects: (1) [Defect]: [description]; Location: [room, wall, elevation, unit]; Damage: [water staining, mold, cracked tile]; Discovered: [date]. (2) ... Photographs and [inspector or engineer] report dated [date] are enclosed. Please contact [name, phone, email] to schedule any inspection during normal working hours. This notice is served under section 558.004, Florida Statutes."

Tips that matter in practice:

  • One notice can list many defects, and you can amend it as new defects become known. At trial, only defects that were noticed (and those reasonably related to or caused by them) can go forward, so amend promptly (s. 558.004(11)).
  • Serve properly: certified mail with USPS proof of delivery, hand delivery, or courier with written proof (s. 558.002(9)). Keep the proof.
  • Ask for documents. Either side can request design plans, specifications, as-built plans, photos and videos, expert reports, subcontracts, purchase orders and maintenance records; the request must cite s. 558.004(15) and offer to pay reasonable copying costs, and must be answered within 30 days.
  • Make emergency repairs if health or safety requires it. Chapter 558 does not stop you (s. 558.004(9)). Photograph the condition before and after and keep the removed materials if you can.

Destructive testing and inspections

Sometimes the cause of a leak or crack cannot be seen without opening walls, coring a slab or removing roofing. Destructive testing under ch. 558 happens only by mutual agreement on these terms (s. 558.004(2)):

  • The person served must notify you in writing, describing the testing, who will do it, the expected damage and restoration, the time needed, and the financial responsibility it offers for repairs.
  • If you promptly object to the person chosen, it must give you a list of three qualified people, and you pick one.
  • Testing happens at a mutually agreeable time, you or your representative may watch, and it may not make the property uninhabitable.
  • No construction lien can be claimed for the testing or restoration unless you contract for it.

Be careful about saying no. If you refuse reasonable destructive testing, you have no claim for damages that could have been avoided or reduced had the testing been allowed when requested and a feasible remedy promptly done.

Can I sue the subcontractor directly?

Often, yes, but the 558 process comes first. When the defect arises from work under a contract, you must serve the notice on the person you contracted with (s. 558.004(1)(a)). That party may then pull in the subs, suppliers and designers it believes are responsible (s. 558.004(3)). You may also serve those parties yourself, since the statute allows notice on the contractor, subcontractor, supplier or design professional "as applicable."

Whether you have a legal claim directly against a sub you never contracted with depends on the theory. One route is s. 553.84, which gives anyone damaged by a material violation of the Florida Building Code a civil cause of action against the person who committed the violation. A "material violation" is one that may reasonably result, or has resulted, in physical harm or significant damage to the building or its systems. That claim is limited where the party got the permits, the plans were approved, all inspections passed and there was no damage beyond the permitted property, unless the party knew or should have known of the violation. Ask a construction attorney which parties to name.

Statute of limitations and the 7-year statute of repose

Chapter 558 deadlines are layered on top of Florida's limitations periods in s. 95.11. For an action founded on the design, planning or construction of an improvement to real property:

  • Limitations: 4 years, running from the earliest of the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy or a certificate of completion, or the date construction was abandoned if not completed.
  • Latent defects (hidden defects not reasonably discoverable): the 4 years runs from when the defect was discovered or should have been discovered with due diligence.
  • Repose: 7 years from the same earliest triggering date. This applies even to latent defects, so a defect discovered in year 8 is barred.
  • Warranty repairs do not extend the clock. For work done under a building permit with a CO or certificate of completion, correcting or repairing completed work, under warranty or otherwise, does not extend the period.
  • Model homes: the period begins when a deed first transferring title to another party is recorded.
  • Multiple buildings: each building is its own improvement for the limitations period.
  • Counterclaims and third-party claims may be filed up to 1 year after the related pleading is served, even if otherwise barred.

Other periods can matter: actions on a written contract generally have 5 years (s. 95.11(2)(b)), and negligence claims generally 2 years (s. 95.11(5)(a)). For construction defect claims, the specific improvement-to-real-property provision is the one courts and lawyers focus on. Get legal advice on which applies to you.

Did Florida change the statute of repose in 2023?

Yes. CS for Senate Bill 360, enacted as chapter 2023-22, Laws of Florida and approved by the Governor on April 13, 2023, effective on becoming law:

  • Cut the statute of repose from 10 years to 7 years.
  • Changed the trigger from the latest of several dates (including actual possession and completion or termination of the contract) to the earliest of a temporary CO, CO, certificate of completion or abandonment.
  • Treated each building in a multi-building project as its own improvement.
  • Added a definition of "material violation" to s. 553.84.
  • Applied to actions filed on or after the effective date, but gave claims that would not have been barred under the old law until July 1, 2024 to be filed. That transition window has now closed.

Older guides that still say 10 years, or that start the clock at "the latest" date, are out of date.

Tolling: what the notice pauses and what it does not

Serving a ch. 558 notice tolls (pauses) the statute of limitations against everyone covered by the chapter and any bond surety until the later of 90 days after service (120 days for large associations) or 30 days after the end of the repair or payment period in an offer you accepted. The parties can extend that by written agreement (s. 558.004(10)). The notice does not toll any statute of repose (s. 558.004(1)(d)). If your 7-year date is close, talk to a lawyer about filing and serving notice right away.

Can I opt out of Chapter 558 in my contract?

Yes. Chapter 558 applies "unless a claimant and a potential defendant have agreed in writing to opt out" (s. 558.005(1)). The parties may also agree in writing at any time to pre-action mediation or to change the notice procedure (s. 558.005(4)).

Unless the parties agree the chapter does not apply, written contracts for improvement of real property signed after October 1, 2009 between an owner and a contractor or design professional must contain this notice: "ANY CLAIMS FOR CONSTRUCTION DEFECTS ARE SUBJECT TO THE NOTICE AND CURE PROVISIONS OF CHAPTER 558, FLORIDA STATUTES." Leaving it out carries no penalty; it is meant to promote awareness (s. 558.005(6)). Older contracts (July 2004 through September 2009) had longer required notices in capital letters.

Arbitration clauses do not override the chapter: to the extent an arbitration clause conflicts with s. 558.004, the statute controls (s. 558.004(14)). Before signing, read the contract for an opt-out, a shortened claim period or an arbitration clause, and ask what each means for you. See the construction contract checklist.

What are latent defects?

A latent defect is one that is hidden and would not be found by a reasonable inspection, such as missing flashing behind stucco, undersized rebar in a slab, or improper fastening under roof covering. A patent defect is visible, like crooked tile or a door that will not close.

The difference matters for timing. For latent defects the 4-year limitations period runs from discovery (or when you should have discovered it), but the 7-year repose period still applies from the CO, certificate of completion or abandonment date. For patent defects, the 4 years runs from the earliest of those dates. Document when and how you discovered each defect, and serve your ch. 558 notice promptly.

What happens to insurance, offers and evidence?

  • Offers are not admissions. An offer, or a failure to offer, is not an admission of liability and is not admissible in the lawsuit (s. 558.004(9)).
  • Insurance. The contractor still must follow its liability policy's notice terms. Providing your notice to its insurer is not a claim for insurance purposes unless the policy says so (s. 558.004(13)).
  • Expert reports exchanged under the chapter may not be used later unless the expert testifies or another testifying expert relies on the report (s. 558.004(15)).
  • The chapter creates no new rights and bars none, apart from what it says (s. 558.004(12)). Your underlying claim still has to rest on contract, warranty, s. 553.84 or another legal theory.

For warranty-based claims, see builder and remodel warranties. Condominium buyers also have statutory warranties under s. 718.203 that run against the developer and contractors.

Florida vs Texas pre-suit defect rules

IssueFlorida ch. 558Texas RCLA (Prop. Code ch. 27)
Notice before suit60 days (120 for large associations)60 days
DeliveryCertified mail with USPS proof, hand delivery or courierCertified mail, return receipt requested
InspectionWithin 30 days (50)Within 35 days; up to 3 inspections
Response or offerRequired within 45 days (75)Optional offer within 60 days
Owner's replyAccept or reject within 45 daysExplain unreasonableness within 25 days
Penalty for rejecting a reasonable offerNone built into ch. 558Recovery capped at the offer's value
Opt out by contractAllowed in writingAttempted waiver void since Sept. 1, 2023
Repose7 years10 years (6 with qualifying warranty)

See the Texas RCLA guide for the Texas process.

When to call a lawyer

This guide is general information, not legal advice. Talk to a Florida construction attorney when the repairs are significant, a condominium or homeowners' association is the claimant, several contractors or designers may be responsible, an insurer is involved, or a repose date is within a year or two. The Florida Bar's lawyer referral service can help. For smaller claims, county court small claims handles up to $8,000; see suing a contractor in small claims. City guides: Miami, Tampa, Orlando, Jacksonville, and the Florida overview.

How to choose a provider

  • Confirm the project is complete (CO or certificate of completion) and the claim is for property damage.
  • Check your contract for a ch. 558 opt-out, a mediation clause or an arbitration clause.
  • Find the CO, certificate of completion or abandonment date and calendar 4-year and 7-year dates.
  • Get at least a visual inspection, ideally by an inspector or engineer, of each defect.
  • Write a notice that refers to ch. 558 and lists each defect, its location and damage.
  • Serve the contractor you hired by certified mail with USPS proof, hand delivery or courier.
  • Wait at least 60 days (120 for associations over 20 parcels) before filing.
  • Give reasonable access for inspection within 30 days (50).
  • Respond in writing to any destructive testing request.
  • Expect a written response within 45 days (75).
  • Accept or reject any offer in writing within 45 days of receiving it.
  • Amend the notice promptly if new defects appear.

Related general and residential contractors guides

General and residential contractors by state and city

Questions people ask

How much notice must I give a contractor before suing in Florida?

At least 60 days before filing an action for a construction defect, or at least 120 days if the claimant is an association representing more than 20 parcels. The notice must be in writing, refer to chapter 558, describe each defect and its location in reasonable detail, and be served by certified mail with USPS proof of delivery, by hand delivery or by courier with proof of delivery.

How long does the contractor have to respond to a 558 notice?

The person you served must give you a written response within 45 days after service, or 75 days for a large association. The response must offer to repair, offer to pay, offer both, dispute the claim, or say its insurer will decide on payment within 30 days. If it disputes the claim or does not respond in time, you may file suit without further notice.

What is the Florida statute of repose for construction defects?

Seven years. Under s. 95.11(3)(b), a construction defect action must be filed within 7 years after the earliest of a temporary certificate of occupancy, a certificate of occupancy, a certificate of completion, or abandonment of construction, even for latent defects. A ch. 558 notice does not pause this deadline. The period was 10 years before SB 360 took effect in April 2023.

Did Florida change the statute of repose in 2023?

Yes. SB 360, chapter 2023-22, approved April 13, 2023, cut the repose period from 10 to 7 years and changed the start from the latest of several dates to the earliest of the CO, temporary CO, certificate of completion or abandonment. Claims that were still timely under the old law had until July 1, 2024 to be filed.

Can I opt out of chapter 558 in my contract?

Yes. Section 558.005 says the chapter applies unless the claimant and potential defendant agreed in writing to opt out. Parties may also agree in writing to pre-suit mediation or a different procedure. If the contract has an arbitration clause that conflicts with s. 558.004, the statute controls. Read any opt-out language carefully before signing.

Does chapter 558 apply to remodels?

Yes. The definition of construction defect includes repair, alteration and remodeling, and contractor includes anyone in the business of repairing or remodeling real property. The claim must involve a defect that arose after completion of the improvement. For a project that is still underway, the chapter 558 notice is not required, and contract remedies apply instead.

What are the 558 deadlines for condo associations?

For an association representing more than 20 parcels: serve notice at least 120 days before suing; the person served may inspect within 50 days and forward the claim within 30 days; recipients of a forwarded claim respond within 30 days; and the written response to the association is due within 75 days. The association still has 45 days to accept or reject an offer.

Does a 558 notice stop the statute of limitations?

It tolls the limitations period against everyone covered by the chapter and any bond surety, until the later of 90 days after service (120 for large associations) or 30 days after the end of an accepted repair or payment period. It does not toll the 7-year statute of repose, so serve early when that date is near.

Do I have to allow destructive testing?

Only by mutual agreement, after the contractor gives written notice describing the testing, who will do it, expected damage, restoration time and who pays. If you object to the tester, you can pick from three qualified people. But if you refuse reasonable destructive testing, you cannot recover damages that testing and a prompt fix would have avoided.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration