Change Orders: How to Handle Them Without Blowing Your Budget

What a change order must say, how hidden-damage and allowance changes are priced, how to keep a contingency, and how to dispute a charge, with Texas homestead and Florida lien and Notice of Commencement points.

A change order is a written amendment, signed by owner and contractor, that changes the scope, price or schedule of a construction contract. Require one for every change before the work starts, with a description, price breakdown, schedule effect and revised contract total. Set the markup and concealed-conditions rules in the original contract, keep your own contingency, and pay change-order work with the same lien protections as any other payment.

Key facts

  • AIA's standard Change Order form is G701-2017; its Construction Change Directive is G714-2017.
  • Texas's required residential disclosure (Property Code 53.255) warns that oral promises not in the written agreement may not be enforceable.
  • A Texas homestead lien requires a written contract signed before work starts, by both spouses if married, and filed with the county clerk (53.254).
  • Texas owners must reserve 10% of the contract price or of the value of work done for 30 days after completion (53.101).
  • A Florida Notice of Commencement expires 1 year after recording unless it states otherwise; payments after it expires are improper payments (s. 713.13).
  • Florida lienors who served a Notice to Owner can claim a lien even if the owner paid the contractor, so get a release with each payment (s. 713.06).
  • A Florida claim of lien must be recorded within 90 days after final furnishing (s. 713.08).
  • A Texas DTPA claim requires at least 60 days' written notice before suit (Bus. & Com. Code ch. 17).

What is a change order?

A change order is a written amendment to your construction contract that changes the scope of work, the price, the schedule, or all three. Both you and the contractor sign it, ideally before the changed work starts. The American Institute of Architects' standard form for this is the G701-2017 "Change Order," but any clear written document signed by both parties can work.

Change orders are normal. Almost every remodel has some, because owners change their minds, selections cost more or less than the allowance, and old houses hide surprises behind the drywall. What blows up budgets is not change orders themselves. It is changes made without a price, changes approved by text message, and changes nobody tracked until the final bill.

A good change-order process has three parts: a contract clause that sets the rules, a standard form for every change, and a running log so you always know where the budget stands. This page covers all three, plus what to do when you disagree.

Do change orders have to be in writing?

Your contract decides most of this, and almost every good contract says yes: no change in scope, price or time without a written change order signed by both parties. Insist on that clause. It protects you from surprise charges and protects the contractor from being told "I never asked for that."

Even where an oral change might be enforceable in theory, it is hard to prove what was agreed. Texas law makes the point in the disclosure statement that contractors must give residential owners before signing (Property Code 53.255): if a contractor made a promise about the work, make sure it is in the written agreement, because an oral promise that is not included may not be enforceable under Texas law.

Texas homestead projects

For a contractor to have a lien on a Texas homestead, the original contract must be in writing, signed before work or materials are furnished, signed by both spouses if the owner is married, and filed with the county clerk (Property Code 53.254). The Texas Constitution (art. XVI, s. 50(a)(5)) likewise requires renovation work on a family homestead to be contracted for in writing with the consent of both spouses. Neither text expressly addresses change orders. Because a large change is an amendment to that written contract, the cautious practice is to have both spouses sign any significant change order on a homestead job. If a change is large enough to look like a new project, ask an attorney whether it needs its own contract.

Florida projects

Florida requires a written lien law notice in direct residential contracts over $2,500 (s. 713.015) and a Recovery Fund notice in most residential contracts (s. 489.1425). Those notices live in the original contract. Change orders do not need to repeat them, but they should state that all other contract terms still apply. See required contract notices in Texas and Florida.

What should a change order include?

Use the same form for every change. A complete change order has these fields:

FieldExample
Change order number and dateCO #4, March 3
Project name, address and contract dateSmith kitchen, 123 Oak St., contract dated Jan. 10
Who requested it and whyOwner request; or concealed condition found during demolition
Description of the changeReplace 12 linear feet of rotted sill plate and 2 studs under kitchen window; add one 20-amp circuit for coffee bar
Work deleted, if anyDelete under-cabinet lighting in pantry
Pricing methodLump sum; or T&M not to exceed $X; or unit price
Cost breakdownLabor, materials, subcontractor, permit revision fee, markup at contract rate
Credit for deleted workMinus $350
Net change in contract pricePlus $2,140
Revised contract totalOriginal $48,000, prior COs plus $3,600, this CO plus $2,140, new total $53,740
Change in schedulePlus 3 working days; new completion date April 18
Permit or plan revision needed?Yes, electrical permit revision; contractor to obtain
Payment timingAdded to next progress payment
Statement that other terms remain in effectAll other contract terms unchanged
Signatures and datesOwner (both spouses on Texas homestead), contractor

Attach photos for concealed conditions and any supplier quote for new materials. The "revised contract total" line is the most important one for your budget. It makes every change order show the cumulative effect, not just this one item.

What kinds of change orders are there?

TypeExampleWho usually paysWhat to check
Owner-driven changeYou upgrade countertops or add a windowOwnerFair price, schedule effect, signed before work
Allowance adjustmentYour tile costs $2,400 more than the allowanceOwner, or credit to owner if underAllowance terms: material only? markup on overage?
Concealed or unforeseen conditionRotted subfloor, termite damage, no header over a doorway, buried debrisDepends on the contract's concealed-conditions clausePhotos before repair, whether it was reasonably foreseeable
Code or inspector-required workInspector requires smoke alarms or a guardrail not in the plansDepends on contract; often owner if plans did not show it, contractor if it was the contractor's job to knowWas it in the permit drawings? Who prepared them?
Contractor-driven changeContractor proposes a substitute product or a different methodShould be no cost to owner unless owner gains value; a credit if cheaperIs the substitute equal? Warranty effect
Design error or omissionPlans show a beam that does not fitOften the party responsible for the designArchitect, engineer or design-build contract
Deductive change orderYou delete the backsplash and will do it laterOwner receives a creditCredit should reflect the contractor's actual savings, often including markup

Contractor mistakes, such as cabinets ordered in the wrong size or work redone because it failed inspection, should not become change orders charged to you. They are the contractor's cost under almost any contract.

What if the contractor finds hidden damage?

Hidden, or concealed, conditions are the most common source of honest change orders in older Texas and Florida homes: rotted framing from slow leaks, termite damage, corroded cast-iron drain lines, undersized wiring, and window and door openings with no proper header.

What a concealed-conditions clause does

A concealed or differing site conditions clause tells you in advance who pays when the contractor opens a wall and finds something neither of you could see. A typical owner-friendly version says:

  • The contractor must stop work on the affected area and notify you in writing promptly, before disturbing the condition further except to make it safe.
  • You (or your inspector) get a chance to see the condition, and the contractor documents it with photos.
  • If the condition was concealed and could not reasonably have been anticipated, the price and time are adjusted by change order.
  • If the contractor fails to give notice, it may lose the right to extra payment.

Watch for one-sided versions: "Owner is responsible for all conditions not visible at the time of bid," with no notice requirement and no limit. That makes every surprise yours, at the contractor's price.

Practical steps when hidden damage appears

  1. Ask the contractor to stop and show you, in person or by video.
  2. Take your own photos before anything is removed.
  3. Ask for a written change order with a price before repairs go beyond making it safe.
  4. If the damage came from a storm, a sudden leak or another covered event, call your insurer before the repair covers it up. The Texas Department of Insurance warns that an insurer might deny a claim if you make permanent repairs before it sees the damage.
  5. If the price looks high, ask for a breakdown or a second price from a trade you choose, if the contract allows.
  6. Ask whether the repair needs a permit revision or inspection.

If a contractor knew about a condition and stayed quiet in order to bill for it later, that can raise a claim. In Texas, the DTPA lists knowingly making false statements about the need for parts, replacement or repair as a deceptive practice. See contractor dispute resolution.

How is a change order priced?

Your contract should say how changes are priced before the first one happens, because you cannot bid out a change in the middle of a job. Common methods:

  • Agreed lump sum. The contractor quotes a price for the change and you accept or reject it before work. Best for most owner changes.
  • Unit prices. Set in the contract for predictable extras, such as per sheet of roof decking or per linear foot of rotted sill replaced.
  • Time and materials with a not-to-exceed cap. For changes that cannot be priced until the work is opened up.
  • Cost plus the contract's stated markup. Common in cost-plus and GMP contracts.

What is a fair markup on change orders?

No Texas or Florida statute sets a markup for private change orders, and we did not find a named, current source for a "standard" residential change-order markup, so this page does not give a number. What protects you is agreeing on the rate in the contract, before any change exists. Points to settle:

  • One stated markup percentage on the contractor's direct cost for changes, and whether it differs for subcontracted work.
  • Whether the same markup applies to credits for deleted work, so deductions are fair.
  • Whether supervision time and general conditions can be charged on top of the markup for extended schedules.
  • Labor rates for T&M changes, by worker type.

Expect change-order pricing to be somewhat higher than the same work bid at the start. Small changes cost more per unit, and they disrupt sequencing. But a change order priced far above the logic of the original bid deserves a breakdown.

How much do change orders usually add, and how big should my contingency be?

We did not find a reliable, named, current source giving a typical percentage that change orders add to residential projects in Texas or Florida, or a standard contingency percentage. Figures you see online are usually unsourced. So rather than a rule-of-thumb number, set a contingency from your own project's risk:

FactorLower riskHigher risk
Age and condition of the homeNewer home, known conditionOlder home, past leaks, termite history, prior unpermitted work
How much is opened upCosmetic, surface workGut remodel, walls opened, structural changes
How complete the design isFull plans and all selections madeDesign still evolving, many allowances
Your own decision styleYou decide once and stick with itYou expect to upgrade as you see the space
Building typeSingle-family homeCondo unit with association rules, or a commercial space with landlord requirements
Storm or flood damageNoneWater damage that may have spread out of sight

Keep the contingency as your own money, outside the contract. Do not tell the contractor to "just use the contingency." Every draw on it should still come through a signed change order. If you have money left at the end, you keep it.

If a city inspector or an insurer reviews your project, do not mistake that for cost control. Texas law requires contractors to warn residential owners that inspections by government authorities and other outside parties are made for their own purposes and are not quality-control inspections (Property Code 53.255).

Can a contractor charge for a change I didn't sign?

If your contract requires signed change orders and you did not sign one, you have a strong position to refuse payment. But disputes over unsigned extras often turn on the facts, such as whether you asked for the work and watched it get done without objecting. Do not rely on the paper alone.

How to protect yourself:

  • Never ask for extra work casually. If you want something, say "Please send me a change order for that."
  • If the contractor starts extra work without a change order, tell them in writing (email is fine) to stop that item until there is a signed change order.
  • If you receive an invoice with an unsigned extra, reply in writing that you did not approve it and ask for the basis.
  • Pay the undisputed part of the invoice on time. Withholding everything over one disputed item can hand the contractor a claim that you breached first.

Can I refuse a change order?

For an owner-driven or optional change, yes: if you do not like the price, do not sign, and the original scope stands. For a change the work cannot proceed without, such as structural rot that must be fixed before the floor goes down, refusing does not make the problem go away. Your choices are to negotiate the price, ask for a breakdown, get an outside price if the contract allows, or have the contractor proceed under a construction change directive while the price is settled.

What is a construction change directive?

A construction change directive (CCD) is a written order from the owner telling the contractor to proceed with a change before the price or time adjustment is agreed. The AIA form is G714-2017. Large and commercial contracts often include CCDs so that work does not stop while people argue about money. The contract then sets how the final price is decided, often on actual cost plus the agreed markup with records.

Most homeowner contracts do not use the term, but the idea is useful: "Proceed with the sill repair on a time-and-materials basis not to exceed $3,000, with daily time sheets and receipts, and we will sign a change order for the final amount." Put that in writing so it is clear the work is approved but the price is not.

How do change orders affect the schedule?

Many change orders add time as well as money: new materials must be ordered, inspections rescheduled, and other trades resequenced. Every change order should state the change in schedule, even if it is "no change." If it does not, the contractor may later claim extra time for all the changes together, which can undercut any late-completion terms in your contract.

In Florida, schedule changes can also affect your Notice of Commencement. A Notice of Commencement expires 1 year after recording unless it states a different date, and payments you make after it expires are treated as improper payments, which can expose you to paying twice. Amendments may extend the period or correct or add information (s. 713.13). If change orders push your project close to the expiration date, record an amended notice before it lapses. See the Florida Notice of Commencement. A Florida single-family building permit also expires 1 year after issuance unless extended (s. 553.79), and work under a long-running permit can stall if inspections are not passing. See construction timelines and delays.

Should change orders be paid upfront?

Usually not in full. The common practice is to add approved change orders to the next progress payment once the changed work is done, or to pay a modest deposit when the change requires a special-order item. Paying large sums before work is done increases your risk, just as with the original deposit.

  • Florida: When you pay for change-order work, the same lien protections apply as for any other payment. Collect a written release from any subcontractor or supplier who served a Notice to Owner, as the statutory notice advises, and get the Contractor's Final Payment Affidavit before the final payment (s. 713.06).
  • Texas: Your 10 percent statutory retainage applies to the contract price as changed, so reserve 10 percent of change-order amounts too, during the work and for 30 days after completion (Property Code 53.101). On residential contracts, the contractor's disbursement statement with each payment request should list the subcontractors it intends to pay, including those doing change-order work (53.258).

See contractor deposits and payment schedules.

What is scope creep, and how do I stop it?

Scope creep is the slow growth of a project through many small additions: "while you're here, could you also..." Each one seems minor, but together they can add weeks and thousands of dollars, and they are often done without paperwork.

How to stop it:

  • Make all selections before you sign, so fewer decisions are left for later.
  • Keep a "parking lot" list of new ideas and decide on them together, once, rather than one at a time on site.
  • Require a priced change order for every addition, no matter how small.
  • Keep a change-order log with the running total, and look at it before approving the next one.
  • Ask for each change's schedule effect, not just its price.

How do I dispute a change order?

Most change-order disputes can be settled with documents and a calm meeting. Escalate only as needed.

  1. Re-read the contract. Look at the scope, allowances, exclusions, concealed-conditions clause, change-order clause and markup terms. Most disputes turn on one of these.
  2. Ask for backup. Request a written breakdown: labor hours, materials with receipts or quotes, subcontractor invoices and markup.
  3. Respond in writing. State what you dispute and why, what you accept, and what you propose. Keep it factual.
  4. Pay the undisputed amount on time and say in writing that you are doing so.
  5. Meet. Walk the site together with photos and the contract. Many disputes are a misunderstanding about what was in the original scope.
  6. Get a neutral opinion. An independent contractor, inspector or estimator can price the disputed work.
  7. Use the contract's dispute clause. Many contracts require negotiation, then mediation, then arbitration or court. Follow the steps and deadlines.
  8. Know the state pre-suit rules. In Texas, a DTPA claim requires at least 60 days' written notice before suit, and a construction defect claim on a residence generally requires an RCLA notice by certified mail at least 60 days before suit. In Florida, a construction defect claim requires a ch. 558 notice at least 60 days before suit (120 days for large associations).
  9. Watch for liens. A contractor that believes it is owed money may file a lien. In Texas, a residential original contractor must file its lien affidavit by the 15th day of the third month after the month its work was completed, terminated or abandoned. In Florida, a claim of lien must be recorded within 90 days after final furnishing, and an owner can shorten the time to sue to 60 days by recording a Notice of Contest of Lien. A lien that willfully exaggerates the amount is a fraudulent lien under Florida law (s. 713.31).

This is general information, not legal advice. For a dispute that is large, involves a lien, or threatens the project, talk to a construction attorney. See contractor dispute resolution, Texas liens and Florida liens.

What should the contract say about changes?

Before you sign, make sure the contract has a change clause that covers:

  • No change in scope, price or time without a written change order signed by both parties (and both spouses on a Texas homestead).
  • How changes are priced: lump-sum quote, unit prices, or T&M with a cap.
  • The markup rate for changes and credits.
  • A concealed-conditions clause with prompt written notice and owner inspection.
  • That each change order states its effect on the schedule.
  • That contractor errors and failed inspections are not change orders.
  • When change orders are paid.
  • Who obtains any permit or plan revisions.

See the construction contract checklist and how contract type affects changes.

How to choose a provider

  • Put a written change-order clause, pricing method and markup rate in the contract.
  • Add a concealed-conditions clause with prompt written notice and a chance to inspect.
  • Use one change-order form with price breakdown, schedule effect and revised total.
  • Never ask for extra work without asking for a change order.
  • Photograph hidden damage before it is repaired and call your insurer if it may be covered.
  • Have both spouses sign significant change orders on a Texas homestead job.
  • Keep a change-order log and check the running total before each new approval.
  • Keep your contingency outside the contract and spend it only by signed change order.
  • Texas: reserve 10% of change-order amounts along with the base contract.
  • Florida: collect lien releases for change-order payments and amend the Notice of Commencement if time runs long.
  • Dispute in writing, pay the undisputed amount, and follow the contract's dispute steps.

Related general and residential contractors guides

General and residential contractors by state and city

Questions people ask

Is an email or text good enough for a change order?

It is better than nothing, but a signed change order form is much stronger. If your contract requires a signed written change order, a text may not meet that requirement and can cause arguments about what was agreed. If you approve something by email in a hurry, follow up the same day with a proper change order stating the scope, price and schedule effect, and have both parties sign it.

Can a contractor stop work until I sign a change order?

It depends on the contract and the situation. If the change is necessary, such as structural damage that must be repaired before work can continue, the contractor may reasonably pause that part of the work. A good contract lets the owner direct the contractor to proceed while price is settled. Stopping the whole job over a disputed optional change can be a breach. Read your contract and get legal advice if work stops for long.

Who pays for work required by the building inspector?

It depends on who was responsible for knowing about the requirement. If the contractor or its designer prepared the permit plans and missed a code requirement, the cost often falls on them. If the requirement comes from a condition no one could see, or from your own design changes, it may be your cost by change order. Check your contract's code-compliance and concealed-conditions clauses.

Do I get a credit if I remove something from the scope?

You should. A deductive change order reduces the contract price for work you delete. The credit should reflect what the contractor actually saves, including materials not bought and labor not spent, and often the markup on them. Agree in the contract that the same markup rate applies to credits as to additions, so deletions are priced fairly.

What if I never received change orders and the final bill is higher?

Ask for a written itemization of every extra with dates and the basis for each. Compare it with your contract, emails and photos. Pay the undisputed contract balance, after lien releases, and dispute the rest in writing. Do not sign a final release or a final lien waiver for amounts you dispute. If the contractor threatens a lien, review the state lien deadlines and talk to an attorney.

Should my change orders include the new completion date?

Yes. Every change order should state the change in time, even if it is zero days, and the revised completion date. Without that, a contractor can later argue that the combined changes justified a long delay. In Florida, also check whether schedule changes push the job past your Notice of Commencement's expiration date, and record an amendment if needed.

What is a change order log?

It is a simple running list of every change order with its number, date, description, amount and schedule effect, plus the revised contract total. Keep one in a spreadsheet or notebook. Before you sign each new change order, look at the total so far. It is the easiest way to avoid surprise at the end of the job.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration