Is Solar Worth It for a Small Business in Texas or Florida?

Commercial solar math is different from home solar. Demand charges, the 2027 federal credit cutoff, state property tax rules and lease terms decide whether panels pay off for your shop, restaurant, office or warehouse.

Solar can pay off for a small business that uses most of its power in daylight, is billed mainly for energy (kWh), and controls its roof for 25 years. Demand charges limit savings, because solar alone rarely cuts your monthly peak. Federal 48E credits require solar to be placed in service by December 31, 2027, unless construction began by July 4, 2026. Florida exempts 80% of the added value from property tax for nonresidential property; Texas exempts on-site solar under Tax Code 11.27.

Key facts

  • FPL's GSD-1 rate (demand 25 to under 500 kW) charges $12.70 per kW of demand, measured over the customer's highest 30-minute period each month, plus 2.825 cents per kWh base energy (tariff effective Jan. 1, 2026).
  • FPL's GS-1 rate for businesses under 25 kW has no demand charge and a base energy charge of 8.039 cents per kWh.
  • IRS Notice 2025-42: solar facilities placed in service after Dec. 31, 2027 lose the 48E and 45Y credits unless construction began by July 4, 2026.
  • The 48E credit base is 6%, rising to 30% with prevailing wage and apprenticeship, plus 10 points each for domestic content and energy communities (IRS).
  • The 2025 law makes 100% bonus depreciation permanent for qualified property acquired after Jan. 19, 2025 (IRS Notice 2026-11).
  • Florida exempts 80% of the value of renewable energy devices on nonresidential property (Fla. Stat. 193.624(2)(b) and 196.182), through Dec. 31, 2037.
  • Texas Tax Code 171.107 lets a business deduct 10% of the amortized cost of a solar energy device from its franchise tax margin.
  • Florida Rule 25-6.065 sets Tier 2 (over 10 to 100 kW) and Tier 3 (over 100 kW to 2 MW), with insurance requirements capped at $1 million and $2 million.
  • Berkeley Lab data (via Mercom, Oct. 2026) put the 2025 U.S. median price of small non-residential solar at $3.10 per watt, or $5.10 with storage.
  • ERCOT calculates Four Coincident Peak (4CP) intervals for June, July, August and September, used to allocate transmission costs.

Is solar worth it for a small business in Texas or Florida?

It can be, but the answer for a business depends on different things than for a home. Five questions decide it:

  1. How is your power billed? If your utility bills you for demand (kW) as well as energy (kWh), solar cuts only part of the bill. More on this below.
  2. When do you use power? A shop that runs coolers and air conditioning from 9 a.m. to 6 p.m. uses solar power as it is made. A bar that peaks at 10 p.m. sends most of its solar to the grid.
  3. What is exported power worth? Florida's investor-owned utilities credit exports under the state net metering rule. Most of Texas does not; your retail electric provider sets the buyback price.
  4. Can you use the tax benefits? The federal business credit (Section 48E) has a hard deadline for solar, and depreciation only helps if your business owes income tax.
  5. Do you control the roof for 25 years? If you lease your space, the roof belongs to someone else.

A quick test: take your last 12 months of bills. Add up the energy (kWh) charges, including fuel or power supply charges. That is roughly the part of the bill solar can reduce. If most of your bill is fixed customer charges and demand charges, the case is weaker. If most is energy charges and you run during daylight, the case is stronger.

Florida and Texas both have strong sun. Modeled with the federal PVWatts tool (now run by the National Laboratory of the Rockies, formerly NREL), each kilowatt of south-facing roof solar produces about 1,421 kWh a year in Houston, 1,506 in Dallas, 1,483 in Austin, 1,497 in San Antonio, 1,552 in Miami, 1,568 in Tampa, 1,544 in Orlando and 1,455 in Jacksonville. Those are model estimates for a standard fixed array, not guarantees, but they are a good starting point for sizing.

How commercial electric bills work: energy charges vs. demand charges

Most homes pay mostly for energy: the number of kilowatt-hours (kWh) they use. Many businesses also pay a demand charge, which is based on the highest rate of power use (kilowatts, kW) during the billing period. Think of kWh as how far you drove and kW as how fast you went. The demand charge bills you for your top speed, even if you only hit it for a few minutes.

A Florida example: FPL's small business rates

FPL's tariff, effective January 1, 2026, shows the difference clearly:

FPL rateWho is on itBase chargeDemand chargeBase energy charge
GS-1 (General Service, non-demand)Demand under 25 kW$14.20 per month (minimum bill $30)None8.039 cents per kWh
GSD-1 (General Service Demand)Measured demand of 25 kW to under 500 kW$33.71 per month$12.70 per kW2.825 cents per kWh

Both rates also carry fuel and other clause charges listed on FPL's billing adjustment sheets, which change over time. Under GSD-1, FPL measures demand as your greatest use over any 30-minute period in the month.

Look at what this means for solar. On GS-1, every kWh solar saves avoids the 8.039-cent base energy charge plus fuel and clauses. On GSD-1, the base energy charge is only 2.825 cents, because much of the cost moved into the $12.70 per kW demand charge. Solar saves energy charges reliably, but it only cuts the demand charge if it is producing at the exact 30 minutes of your monthly peak. One cloudy afternoon at peak time, or a peak at 6:30 p.m., and the demand charge stays.

Example: a small retail store on GSD-1 peaks at 60 kW. The demand charge is 60 x $12.70 = $762 for the month. If a 40 kW solar array is producing 25 kW during that peak half-hour on every day of the month, the peak could drop to 35 kW and the demand charge to $444.50. But if just one afternoon is stormy, the monthly peak is set that day, and the saving is lost. Proposals that assume large demand savings from solar alone deserve skepticism. Ask the seller to show 15-minute or 30-minute interval data from your own meter.

A Texas example: two bills in one

In competitive areas like Houston and Dallas, your bill has two parts. The retail electric provider (REP) sells you energy at the price in your contract. The transmission and distribution utility (TDU), such as CenterPoint or Oncor, charges regulated delivery fees that your REP passes through. For larger business accounts, TDU delivery charges are often billed per kW of demand rather than per kWh. Your exact charges depend on your TDU rate class, so pull your TDU's tariff or ask your REP for a bill breakdown.

Solar cuts the REP energy charge on each kWh you avoid buying. It may or may not cut the TDU demand-based charges, for the same reason as in Florida.

ERCOT's 4CP: the summer peaks that set transmission costs

ERCOT publishes Four Coincident Peak (4CP) calculations for each distribution service provider for the months of June, July, August and September. The 4CP is the 15-minute interval when ERCOT's whole grid hits its highest demand in each of those four months. Transmission costs are allocated using these peaks, and for larger interval-metered business customers, the transmission part of the TDU bill is based on the customer's own demand during those four intervals. The size threshold for 4CP billing is set in each TDU's tariff; we did not confirm the current thresholds for this guide, so check with your TDU or REP. Most small shops and offices are not 4CP-billed, but a large warehouse or cold-storage building might be.

Why it matters for solar: summer grid peaks in ERCOT often fall in the late afternoon or early evening, when solar output is falling. A battery that discharges during likely 4CP intervals can matter more than extra panels for a 4CP-billed account.

Is a battery worth it for demand charge reduction?

For some businesses, yes. A battery can discharge during your peak half-hour no matter what the clouds do, which solar alone cannot. That makes batteries the main tool for cutting demand charges.

Weigh it carefully:

  • Cost: According to Lawrence Berkeley National Laboratory's latest data as summarized by Mercom (October 2026), the median installed price for small non-residential solar-plus-storage projects was $5.10 per watt in 2025, compared with $3.10 per watt for solar alone. EnergySage's H1 2026 marketplace report put residential battery quotes around $1,130 per kWh of storage.
  • Typical size: the same Berkeley Lab data (via Mercom's secondary summary) put the median small non-residential battery at 20 kWh in 2025, with 14 kW of discharge.
  • Peak shape: a battery works best when your peaks are short and predictable, like a kitchen startup or a compressor bank. A peak that lasts three hours needs a much bigger battery.
  • Controls: demand reduction depends on software that predicts and responds to your load. Ask how the system decides when to discharge, and what happens if it misjudges.

Do the math on your own rate. Under FPL GSD-1 at $12.70 per kW, cutting 15 kW of peak every month saves about $190 per month, or about $2,290 a year, before fuel and clauses. Compare that with the extra cost of storage and the battery's warranty life. In Texas, the value depends on your TDU's demand rate and whether you are 4CP-billed.

Batteries can also keep critical loads running in an outage, which is covered below. Tampa Electric notes that batteries are interconnected but not net metered, so stored power is for your own use.

Can my business still get a federal solar tax credit?

Possibly, but the window is closing. The residential credit (Section 25D) ended after 2025 and never applied to businesses anyway. Businesses use the Clean Electricity Investment Credit (Section 48E) or the production credit (Section 45Y). The One Big Beautiful Bill Act (P.L. 119-21, signed July 4, 2025) cut these short for solar.

The 48E deadlines for solar

  • Under IRS Notice 2025-42, the 45Y and 48E credits end for wind and solar facilities placed in service after December 31, 2027, unless construction began by July 4, 2026.
  • That July 4, 2026 begin-construction date has now passed. So for a project that did not begin construction by then, the system must be placed in service by December 31, 2027 to qualify.
  • To show construction began, the IRS generally requires the Physical Work Test (physical work of a significant nature) plus a continuous program of construction. The older Five Percent Safe Harbor is no longer available for solar, except for a "low output solar facility" with a maximum net output of 1.5 MW AC or less. Most small business systems are well under that size.

How much the credit is worth

The IRS 48E page says the base credit is 6% of the qualified investment. It can be increased up to five times (to 30%) for facilities meeting prevailing wage and registered apprenticeship requirements, plus 10 percentage points for meeting domestic content rules and 10 points for being in an energy community. The credit is claimed on Form 3468. The IRS also notes that 48E is eligible for elective (direct) payment or transfer for certain entities, such as tax-exempt organizations and government bodies, after a pre-filing registration.

Ask your tax adviser how the wage and apprenticeship rules apply to a project of your size. The IRS page we reviewed still describes the pre-2025 phase-out schedule, which was replaced for solar by the 2027 cutoff, so read it with Notice 2025-42 beside it.

The foreign-entity (FEOC) rules

The 2025 law also bars certain energy credits for facilities that receive "material assistance" from a prohibited foreign entity. The IRS has issued interim safe harbors in Notice 2026-15. In practice, this means equipment origin now affects whether your system qualifies. Ask any seller to state in writing which modules, inverters and batteries are used and how they support the claim that the project meets the material-assistance rules. EnergySage reported that 2026 battery prices were pushed up partly by these compliance requirements.

Bottom line: a 2026 or 2027 business solar project should be planned around the December 31, 2027 placed-in-service date, with a margin for permit and utility delays. A project that misses it loses the credit entirely. Never sign a contract whose savings depend on a credit without a written plan for meeting the deadline, and have a CPA review the assumptions.

What about depreciation and bonus depreciation?

Business solar equipment is depreciable property. This is a tax question for your CPA; here are only the published facts. On January 14, 2026, the IRS announced Notice 2026-11, guidance on the permanent 100% additional first-year (bonus) depreciation that the 2025 law provides for qualified property acquired after January 19, 2025. Taxpayers can elect a smaller 40% deduction for property placed in service in the first tax year ending after January 19, 2025.

What we could not confirm: the 2025 law also changed the cost-recovery class for some energy property, and the rules for how a 48E credit reduces the depreciable basis are technical. We have not verified the current MACRS class life for solar placed in service in 2026 or 2027 against a primary IRS source. Ask your CPA which recovery period and bonus percentage apply, and how the credit affects your basis.

Two practical points:

  • Depreciation only helps if you have taxable income to offset. A business with losses may get little benefit in the first year.
  • A seller's savings projection that includes "tax savings" should show the exact assumptions: credit percentage, depreciation method, your tax rate. If those numbers were not built from your own tax situation, the projection is a guess.

State tax breaks: Florida

Florida offers three tax benefits that apply to business solar:

BenefitLawWhat it does
Real property assessmentFla. Stat. 193.624(2)(b)For nonresidential property, 80% of the just value added by a renewable energy source device may not be counted in assessments (devices installed on or after January 1, 2018).
Tangible personal property exemptionFla. Stat. 196.18280% of the assessed value of a renewable energy source device considered tangible personal property is exempt from property tax, for devices installed on or after January 1, 2018.
Sales and use taxFla. Stat. 212.08(7)(hh)Solar energy systems and their components are exempt; the Florida Solar Energy Center certifies the list of qualifying equipment to the Department of Revenue.

The statute defines a renewable energy source device to include photovoltaic modules, inverters, storage, power conditioning equipment, and the wiring and structural supports integral to the system, but not conventional backup generators or equipment on the utility side of the meter. The 2017 amendments behind the 80% nonresidential rules expire December 31, 2037. For homes, the residential rule in 193.624(2)(a) is broader: the device's value is not counted at all.

Ask your county property appraiser how to report the system, especially if you file a tangible personal property return for business equipment.

State tax breaks: Texas

Texas has no state income tax, so its solar benefits come through property tax and the franchise (margin) tax.

  • Property tax exemption, Tax Code 11.27: the added appraised value from a solar device installed primarily for on-site use is exempt. This applies to businesses as well as homes. Since 2021, subsection (a-1) lets the owner of the device claim it even if they do not own the land, which matters for tenants and for leased systems. The definition covers devices that convert, store or distribute solar energy.
  • How to claim it: file Comptroller Form 50-123 with your county appraisal district (not the Comptroller) between January 1 and April 30 of the year you want the exemption. If the chief appraiser asks for more information, you have 30 days to answer.
  • Appraisal of commercial solar, Tax Code 23.26: for solar energy property used for a commercial purpose and installed on or after January 1, 2014, the appraiser must use the cost method with a useful life of no more than 10 years, and the depreciated value cannot fall below 20% of the adjusted value. This matters for systems that are taxable, for example if they do not qualify under 11.27.
  • Franchise tax deduction, Tax Code 171.107: a taxable entity may deduct 10% of the amortized cost of a solar energy device from its apportioned margin, if the device is used in Texas for heating, cooling or power, and the cost is amortized over at least 60 months. The entity files an amortization schedule with the Comptroller.

The PUC's consumer solar guide notes that the State of Texas does not offer grants or rebates for installing solar. Local utilities sometimes do. Austin Energy and some others have run commercial incentives; check your utility's current offerings.

How does net metering work for commercial accounts in Florida?

Florida's net metering rule, Rule 25-6.065 of the Florida Administrative Code, applies to all investor-owned utilities (FPL, Duke Energy Florida, Tampa Electric and Florida Public Utilities), for residential and commercial customers alike. It sorts systems into three tiers by size:

TierSystem size (AC rating)Liability insurance the utility can requireNotes
Tier 110 kW or lessNone (utility may recommend it)No extra fees, including application fees
Tier 2Over 10 kW up to 100 kWUp to $1 millionMost small business systems fall here
Tier 3Over 100 kW up to 2 MWUp to $2 millionMay need an interconnection study

Key points for businesses:

  • Sizing: for inverter-based systems, the AC rating equals the DC nameplate times 0.85. The system cannot exceed 90% of your utility distribution service rating.
  • Credits: excess energy in a month is credited to the next month. Credits roll for up to 12 months, and at year end the utility pays for unused credits at its COG-1 as-available energy rate, which is far below retail.
  • Demand charges stay: net metering customers still pay the customer charge and any demand charge regardless of exports (Rule 25-6.065(8)(h)). This is why demand-billed businesses see smaller percentage savings.
  • Timelines: the utility must confirm receipt of a completed application within 10 business days and sign the interconnection agreement within 30 days (90 days if a Tier 3 study is needed).
  • Before turning on: local code officials must inspect and approve the system, and you must give the utility at least 10 days' notice.
  • RECs: you keep the renewable energy certificates your system produces.

Municipal utilities and co-ops set their own rules under Fla. Stat. 366.91(6). JEA in Jacksonville credits exported energy at its fuel rate rather than retail. OUC in Orlando moved new applicants off full retail credits after June 30, 2025, and, after a full-retail grace period that ended October 31, 2026, credits their exports at its Community Solar Energy Rate for five years (through June 30, 2030), then at its Retail Levelized Fuel rate. Get your utility's current rules before sizing. Our Florida net metering guide covers the rule in full.

One more Florida rule matters for business deals: Rule 25-6.065(2)(a) lets customer-owned systems be leased, operated or maintained with a third party only if the terms do not include the retail purchase of electricity from that third party. A third party may lease you equipment, but an arrangement where you buy the electricity itself from a company other than your utility does not fit the rule. Have an attorney review any "power purchase" offer in Florida.

How do Texas businesses sell excess solar power?

Texas has no statewide net metering rule. How you are paid for exports depends on where you are.

  • Competitive areas (Houston, Dallas-Fort Worth and others): under Utilities Code 39.916(j), a solar owner sells surplus power to the REP that serves their account, at a value the two agree on. Some REPs offer buyback plans; many business plans offer little or nothing. Shop the buyback terms before you size the system.
  • City-owned utilities and co-ops: they set their own rules. Austin Energy credits solar under its Value of Solar rate, which its April 2026 update set at 12.89 cents per kWh for systems under 1 MW and 10.22 cents for systems over 1 MW, for fiscal years 2027 to 2029 (Austin Energy's web figures; a staff deck rounded them to 12.88 and 10.21 cents).

Other Texas rules that protect business owners:

  • Distributed renewable generation is defined as up to 2,000 kW on the customer's side of the meter. Utilities must allow interconnection if the system has a five-year warranty against breakdown or undue degradation and does not exceed the service capacity (Utilities Code 39.916).
  • Utilities and REPs may not require you to buy extra liability insurance for a compliant system (39.916(e)).
  • If your system is sized so its estimated annual production is no more than your estimated annual use, you are not treated as an electric utility or REP and need not register with the PUC (39.916(k)).

Because buyback rates are usually low, Texas business systems are usually sized to match daytime use rather than total annual use. See our Texas solar buyback plans guide and Texas utility programs guide.

What size system does a small office, restaurant or warehouse need?

Start from your 12-month kWh total, not from your roof. Divide your annual kWh by the per-kW production for your city to get the system size that would cover 100% of use. Then size down if your exports would earn little.

CityModeled kWh per kW per yearSize to cover 100,000 kWh a year
Houston1,421About 70 kW
Dallas1,506About 66 kW
Austin1,483About 67 kW
San Antonio1,497About 67 kW
Miami1,552About 64 kW
Tampa1,568About 64 kW
Orlando1,544About 65 kW
Jacksonville1,455About 69 kW

(PVWatts v8 estimates for a fixed, south-facing array at a 20-degree tilt with 14% system losses. Flat commercial roofs, east-west racking and shading lower these numbers. Get a site-specific model.)

Three examples

Small office in Dallas, 3,000 kWh a month (36,000 kWh a year), open weekdays 8 to 6. Full coverage would be about 24 kW. But weekends and evenings mean some power would be exported at a REP buyback rate. A design around 15 to 20 kW may capture most of the savings with fewer exports. Run the numbers both ways with your REP's buyback terms.

Restaurant in Tampa, 8,000 kWh a month (96,000 kWh a year). Kitchens run from late morning into the night, and coolers run all day. Under Tampa Electric's net metering, exports roll to the next bill, so a system near 60 kW could offset much of the annual energy. But a restaurant is often on a demand rate, and its peak may come at 6 or 7 p.m. when solar is low. Expect energy savings, not demand savings, unless you add a battery.

Warehouse in Houston, 20,000 kWh a month with large daytime cooling. Full coverage would be about 170 kW. The roof may fit it, but check the roof's structural capacity and remaining life first. If the account is large enough to be 4CP-billed, storage timed to summer peaks may be worth studying.

Roof space

Berkeley Lab's Tracking the Sun data show the median non-residential system in 2023 was 26 kW, and that non-residential roof-coverage ratios vary widely by building. Fire code setbacks, rooftop HVAC units, skylights and drains all eat into usable space on a flat commercial roof.

What does commercial solar cost?

Use dated, named sources and get several bids. The best national data come from Lawrence Berkeley National Laboratory's Tracking the Sun. As summarized by Mercom in October 2026 (we could not load the Berkeley Lab report directly), 2025 median installed prices were:

System type (2025, U.S.)Median installed price
Small non-residential solar (under 100 kW)$3.10 per watt (vs. $3.20 in 2024)
Small non-residential solar plus storage$5.10 per watt
Large non-residential solar (100 kW and up)$2.40 per watt
Large non-residential solar plus storage$3.70 per watt

At the small non-residential median, a 50 kW system would cost about $155,000 before any tax benefits. These are national medians. Texas and Florida prices can differ, and Berkeley Lab notes its medians can run higher than other benchmarks. Commercial jobs in Florida's coastal wind zones may cost more because of engineering and racking requirements. We did not find a 2026 primary source with small commercial prices specific to Texas or Florida.

Ask every bidder for an itemized price: modules, inverters, racking, electrical, roof work, engineering, permits, utility fees, monitoring and any battery. In Florida, the sales tax exemption should show up as no tax on qualifying solar equipment.

Can I install solar on a leased commercial building?

Yes, with the landlord's written agreement, and that agreement needs to cover more than a simple "OK." A solar system lasts 25 years or more. Most commercial leases are shorter. Before you spend anything, settle these points in a lease amendment reviewed by an attorney:

  • Roof rights: permission to attach to the roof, run conduit, and place inverters and disconnects.
  • Roof warranty: whether penetrations will void the roofing warranty, and who pays for any leaks.
  • Re-roofing: who pays to remove and reinstall the panels if the roof must be replaced during the lease. See our removal and reinstall guide.
  • Ownership at lease end: does the system stay with the building, does the landlord buy it, or must you remove it and restore the roof?
  • Meter and account: the system must connect to the meter on your account to offset your bill. In a multi-tenant building, a shared house meter complicates things.
  • Property tax: in Texas, Tax Code 11.27(a-1) lets the device's owner claim the exemption even without owning the land. In Florida, ask the property appraiser who reports the device.
  • Insurance: who insures the panels, and whether the landlord's policy covers rooftop equipment owned by a tenant.
  • Assignment: what happens to the system if you sell the business or the landlord sells the building.

If you are the landlord of a strip center, the same list applies in reverse. Some landlords install solar on the house meter to cut common-area costs (parking lot lights, signs, shared HVAC), which avoids tenant billing issues entirely.

Contracts and consumer protections: what changes for a business

Many protections homeowners rely on do not cover businesses.

  • Texas solar retailer law does not apply. TDLR says the Residential Solar Retailer Act (Occupations Code ch. 1806) exempts systems on nonresidential property and on multifamily dwellings with more than four units or stories. So the five-business-day right to cancel and the required contract provisions in that law do not protect a business installing on its own commercial building.
  • Texas Business and Commerce Code ch. 115 does cover small commercial customers. Sellers and lessors of distributed renewable generation must give residential and small commercial customers written disclosures, including salesperson and installer contact information, a description and cost of all equipment, and an accounting of fees. Leases and power purchase agreements must also disclose the term, rate and any payment escalators, and whether the agreement and warranties transfer to a buyer.
  • Florida: anyone contracting to install solar must hold the right license (see below). Florida's three-business-day home solicitation cancellation rule (Fla. Stat. 501.025) is written for sales made away from the seller's business location; whether it covers a business-to-business deal depends on the facts, so do not count on it.

Because the safety net is thinner, slow down. Get at least three itemized bids. Ask for every assumption in writing. Do not sign on the first visit. Have an attorney read any lease or power agreement before you sign.

Do I need a different permit for commercial solar?

Yes. Commercial permits usually need engineered plans, a structural review of the roof, and an electrical plan. Expect more review than for a home.

Florida

  • The Florida Building Code, 8th Edition (2023), governs permit applications submitted before December 31, 2026; the 9th Edition (2026) applies to applications submitted on or after that date. For coastal counties, wind design drives the job. Miami-Dade, in the High Velocity Hurricane Zone, lists common plan rejections: roof pressure zones not calculated or shown correctly, modules and racking not rated for the wind zones they sit in, and connections that fail HVHZ Chapter 16 wind load requirements. Palm Beach County's expedited checklist uses a design wind speed of 170 mph and requires engineered attachment details for every part of the load path.
  • The installer must hold a Florida certified or registered solar contractor license, or another Chapter 489 license whose scope covers the work (Fla. Stat. 489.105). Check licenses at the DBPR website, myfloridalicense.com.
  • Fire safety: Florida's Fire Prevention Code adopts NFPA 1 and the Life Safety Code (NFPA 101) by statute (Fla. Stat. 633.202). Ask your local fire marshal about roof access pathways and setbacks for your building type before the design is final.

Texas

  • Electrical work must be done by or through a TDLR-licensed electrical contractor (Occupations Code ch. 1305). TDLR adopted the 2026 National Electrical Code as the state electrical code effective September 1, 2026. Cities may have their own adoption and amendments.
  • Building and fire codes are adopted city by city. Houston, Dallas, San Antonio and Austin each run their own commercial permit review; ask the city's fire marshal about rooftop pathway rules.
  • Your TDU or city utility needs its own interconnection application, separate from the building permit.

Firefighter safety: rapid shutdown

The National Electrical Code (section 690.12) requires rapid shutdown for PV conductors on or in buildings, so firefighters can de-energize the array. Conductors outside the array boundary must drop to 30 volts within 30 seconds. Rapid shutdown rules first appeared in the 2014 NEC and have tightened since. Your installer's plans should show how the system complies with the edition your city enforces.

Can solar help my business during outages?

Solar alone will not. Grid-tied inverters must shut off when the grid goes down so they do not send power into lines that crews are repairing. Florida's interconnection rule requires a utility-interactive inverter that automatically isolates from the grid when the grid loses power, and Oncor defines a certified solar system as one with inverters tested and certified to UL 1741.

To keep running in an outage you need a battery (or generator) and equipment that can island your building safely, usually feeding a backed-up panel with only critical loads: refrigeration, point-of-sale systems, a few lights, maybe one HVAC unit.

Outages are not rare. The PUC of Texas found that Hurricane Beryl in July 2024 disrupted service for 2.7 million customers, including 2.2 million CenterPoint customers, with about 1 million outages still in place four days after landfall. A May 2024 derecho knocked out power to 1.05 million customers, mostly in CenterPoint's area. During the February 2021 winter storm, ERCOT shed 20,000 MW of load at the worst point. For a restaurant with $10,000 of food in its coolers, a few days without power is a serious loss.

See our guides on battery backup for hurricanes and outages and using solar with a generator.

What is a USDA REAP grant, and is it available in 2026?

The Rural Energy for America Program (REAP) gives grants to agricultural producers and rural small businesses for renewable energy systems and energy efficiency. It changed sharply in 2026:

  • On April 15, 2026, USDA rescinded the funding notice that had covered fiscal years 2025 to 2027. Applicants without a fully signed award agreement had to reapply under new rules.
  • A new final rule took effect October 16, 2026. Under it, projects must be fully built and running before you apply. You then submit 12 months of actual production or savings data along with 12 months of data from before installation. USDA plans a single national competition instead of state-level ones and will announce funding in a separate notice.
  • Under the current regulation, the minimum grant request is $1,500 and the maximum for a renewable energy system is $500,000. Cost sharing must cover at least 75% of the project cost, so a grant covers at most a quarter.
  • Rural means outside any city or town of more than 50,000 people and outside the urbanized area next to such a city. Projects in Houston, Dallas, Miami or Tampa do not qualify; many small towns do.
  • Ineligible projects include residential systems, projects at more than one location, and ground-mounted solar on cropland. When storage is included, annual solar production is capped at 120% of the applicant's prior 12-month use.

Because grants now come after the system is built, you take the risk that funding will not be awarded. Contact your USDA Rural Development state office (Texas or Florida) before you build to ask about the next funding notice. Our farms and ranches guide covers REAP for agricultural producers.

How do I evaluate commercial solar proposals?

Compare bids on the same basis. Ask every seller for these items, in writing:

ItemWhat to look forRed flag
Production estimatekWh per year from a named model (such as PVWatts) with your roof's tilt, direction and shadingNo model or a production figure far above PVWatts for your city
Bill savingsBased on your actual tariff and 12 months of interval dataA flat "you'll save 50%" claim
Demand savingsShown separately with the assumed peak reductionLarge demand savings from solar with no battery
Rate escalationThe assumed yearly electricity price increase, statedHigh escalators that inflate long-term savings
Tax benefitsCredit percentage, placed-in-service plan, depreciation, all marked "confirm with CPA"Tax savings included with no deadline plan
Degradation and O&MYearly output loss and maintenance costs over the termNo maintenance or inverter replacement cost
WarrantiesModule, inverter, workmanship and roof-penetration warranties, with who backs eachOnly a manufacturer warranty, no workmanship warranty
Licenses and insuranceTDLR electrical contractor or Florida solar/electrical license numbersLicense number missing or not matching the company
InterconnectionWho files, expected timeline, and any utility upgrade costsNo mention of utility approval

Then check each production estimate yourself with PVWatts. If one bid claims 30% more output than the others for the same size system, ask why. Our quote review guide walks through a full proposal line by line.

Owning vs. leasing the equipment

Businesses can own a system outright or lease it from a third party. In a lease, the third party owns the equipment, claims any tax benefits, and charges you a fixed or escalating payment. EnergySage reported that the share of installers quoting third-party ownership rose from about 14% to about 41% in the first half of 2026, as the residential credit ended. Note that the business credits a third-party owner relies on also face the December 31, 2027 placed-in-service cutoff for solar that did not begin construction by July 4, 2026.

When comparing, look at the total payments over the term, the escalator, who maintains and insures the system, what happens if you move or sell, and the end-of-term options. Remember that in Florida, buying the electricity itself from a third party does not fit the state's net metering rule. Our lease vs. PPA vs. ownership guide explains the contract types.

How to choose a provider

  • Pull 12 months of bills and, if possible, 15- or 30-minute interval data from your utility.
  • Identify your rate schedule and split your bill into customer, demand and energy charges.
  • Find out how your utility or REP credits exported power.
  • Confirm you control the roof for 25 years, or get a written lease amendment.
  • Have the roof inspected; re-roof first if it has less than 10 to 15 years left.
  • Model production for your address with PVWatts.
  • Get at least three itemized bids from licensed contractors.
  • Ask your CPA to review credit, depreciation and the December 31, 2027 deadline.
  • Ask each seller to document equipment origin for the foreign-entity rules.
  • In Texas, file Form 50-123 with your appraisal district between January 1 and April 30.
  • In Florida, confirm the sales tax exemption and ask the property appraiser how to report the system.
  • File the interconnection application and get written permission to operate before turning the system on.
  • If you are rural, contact USDA Rural Development about the next REAP funding notice before you build.

Related residential solar installers guides

Residential solar installers by state and city

Questions people ask

Is solar worth it for a small business?

It is most likely to pay off when your business uses most of its power during daylight, is billed mostly for energy (kWh) rather than demand (kW), owns or controls its roof for 25 years, and can use tax benefits. Florida investor-owned utilities credit exports under net metering, which helps. In most of Texas, buyback rates set by your retail provider are often low, so size the system to your daytime use.

How do demand charges affect commercial solar savings?

A demand charge bills your highest use over a short window, such as FPL's 30-minute peak under its GSD-1 rate at $12.70 per kW. Solar reliably cuts energy charges, but it only cuts demand charges if it is producing at the exact time of your monthly peak. One cloudy afternoon can erase the demand saving for the month. A battery is usually needed for dependable demand reduction.

What is the 48E credit deadline for business solar?

Under IRS Notice 2025-42, solar facilities lose the 48E and 45Y credits if placed in service after December 31, 2027, unless construction began by July 4, 2026. That begin-construction date has passed, so new projects must be in service by the end of 2027. Small systems up to 1.5 MW AC could use the Five Percent Safe Harbor to prove an earlier start. Ask a CPA to confirm your project's status.

Does Florida's 80% commercial solar property tax break apply to my building?

If your property is nonresidential, Fla. Stat. 193.624(2)(b) keeps 80% of the value added by a solar installation out of the real property assessment, and Fla. Stat. 196.182 exempts 80% of the value of a device treated as tangible personal property. Both apply to devices installed on or after January 1, 2018, and both expire after 2037. Ask your county property appraiser how to report it.

Can I install solar on a building I lease?

Yes, if the landlord agrees in writing. Your lease amendment should cover roof rights, roof warranty, re-roofing costs, who owns the system when the lease ends, insurance and what happens if either side sells. In Texas, the device owner can claim the property tax exemption even without owning the land. Have an attorney review the agreement.

How do Texas businesses get paid for extra solar power?

In competitive areas, you sell surplus power to your retail electric provider at a value you agree on under Utilities Code 39.916(j). Many business plans pay little, so compare buyback terms before you buy. City utilities set their own credits; Austin Energy's Value of Solar rate is 12.89 cents per kWh for systems under 1 MW for fiscal years 2027 to 2029.

Is a battery worth it for my business?

It can be if you pay high demand charges with short, predictable peaks, if you are billed on ERCOT's summer 4CP intervals, or if outages cost you money. Berkeley Lab data summarized by Mercom show small non-residential solar-plus-storage at a 2025 median of $5.10 per watt versus $3.10 for solar alone. Compare the yearly demand savings with that extra cost.

Do Texas solar contract protections cover my business?

Mostly not. TDLR says the Residential Solar Retailer Act exempts systems on nonresidential property, so the five-business-day cancellation right does not apply to your commercial building. Business and Commerce Code chapter 115 still requires written disclosures for small commercial customers, including equipment costs and lease terms. Take extra time and get an attorney's review.

Can solar keep my business open during a blackout?

Not by itself. Grid-tied inverters shut off when the grid fails. You need a battery or generator plus equipment that safely separates your building from the grid, usually powering a critical-loads panel. Hurricane Beryl disrupted service for 2.7 million Texas customers in 2024, so for restaurants and shops with perishable stock, backup is worth pricing.

What is USDA REAP and can my business use it?

REAP grants help rural small businesses and agricultural producers install renewable energy. Under the rule effective October 16, 2026, you build first, then apply with 12 months of production data. Grants range from $1,500 to $500,000 for renewable systems, and you must cover at least 75% of costs. Businesses in large cities are not eligible.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration