Kitchen Remodel Guide: Process, Permits, Contractors and Costs in Texas and Florida

How a kitchen remodel actually runs, from layout to final inspection, with 2025 cost and resale figures for Houston, Dallas, Austin, San Antonio, Miami and Jacksonville, and the permit, licensing and contract rules that differ between Texas and Florida.

Plan a kitchen remodel in this order: decide minor refresh or major rebuild, design the layout around your appliances, confirm permits and any condo or HOA approvals, get comparable bids, sign a contract with the required state notices, then build. In 2025 a midrange minor remodel averaged about $25,000 to $29,000 and a midrange major remodel about $76,000 to $83,000 in Texas and Florida metros. Electrical, plumbing and gas work need licensed trades and permits in both states.

Key facts

  • The 2025 Cost vs. Value report put a midrange minor kitchen remodel at $28,300 in Houston, $26,097 in Dallas, $25,463 in Austin and San Antonio, $29,424 in Miami and $29,002 in Jacksonville.
  • The same report put a midrange major kitchen remodel at $75,737 to $83,468 across those Texas and Florida metros (U.S. average $82,793).
  • In 2025, minor kitchen remodels were estimated to recoup about 104% to 121% of cost at resale in Texas and Florida metros; midrange major remodels about 47% to 52%.
  • Florida's new $7,500 single-family permit exemption (effective July 1, 2026) excludes electrical, plumbing, structural, mechanical and gas work and flood hazard areas (s. 553.79, Fla. Stat.).
  • Florida general, building and residential contractors must subcontract electrical, plumbing, mechanical and air-conditioning work unless they hold those licenses (s. 489.113).
  • Texas has no state general contractor license, but electrical (TDLR, Occ. Code 1305), plumbing including gas piping (Occ. Code 1301) and HVAC (TDLR, Occ. Code 1302) are state-licensed.
  • Florida contracts over $2,500 on homes of up to four units must include the s. 713.015 construction lien notice in 12-point capitalized boldface type.
  • Texas homeowners must retain 10% of the contract price until 30 days after completion (Prop. Code ch. 53).
  • Paid work that disturbs paint in pre-1978 homes generally falls under the EPA Renovation, Repair and Painting rule (40 CFR 745, subpart E).

What counts as a minor vs. a major kitchen remodel?

People use "kitchen remodel" for everything from new cabinet doors to gutting the room down to the studs. Before you collect bids or read a cost chart, decide which kind of project you are actually planning. The clearest public definitions come from the 2025 Cost vs. Value report, the long-running annual study published by the Journal of Light Construction (Zonda research, with job costs from Verisk's XactRemodel estimating data). Its three kitchen projects make good benchmarks because each one is described in detail.

Project (2025 Cost vs. Value)What the report assumes
Minor kitchen remodel, midrangeA functional but dated 200-square-foot kitchen with 30 linear feet of cabinets and counters. Cabinet boxes stay; doors and drawer fronts are replaced with new shaker-style panels and hardware. New range and refrigerator, new laminate counters, a midpriced sink and faucet, resilient flooring, and fresh paint.
Major kitchen remodel, midrangeThe same 200-square-foot room rebuilt with a functional new layout: 30 linear feet of semi-custom wood cabinets including a 3-by-5-foot island, laminate counters, double-bowl stainless sink, range, vented range hood, built-in microwave, dishwasher, disposal, custom lighting, new resilient floor, and paint.
Major kitchen remodel, upscaleA 200-square-foot kitchen with top-line custom cabinets and interior accessories, stone counters with imported tile backsplash, built-in refrigerator, commercial-grade cooktop and hood, wall oven, built-in microwave, high-end undermount sink with filtration, new general, task and under-cabinet lighting, and tile or wood-look flooring.

In plain terms, a minor remodel keeps the layout and the cabinet boxes. Plumbing, gas and most wiring stay where they are. A major remodel changes the layout or replaces everything, which usually means new circuits, moved plumbing, a vented hood, new lighting and a full set of permits and inspections. That one difference drives cost, timeline, who you need to hire and which permits apply.

A third category sits beyond both: the kitchen that grows. Removing a wall to open the kitchen to a living room, bumping out an exterior wall, or adding windows or a patio door turns the job into structural work and, in some cases, an addition. If that is your plan, read the home addition guide as well.

How much does a kitchen remodel cost in Texas and Florida?

The table below uses the 2025 Cost vs. Value report's metro figures for Texas and Florida cities. These are average job costs for the defined projects above, not quotes. Your price depends on size, finishes, layout changes, the age of your house and how busy contractors are in your area. Use these numbers to sanity-check bids and to set a realistic first budget.

Metro (2025 Cost vs. Value)Minor, midrangeMajor, midrangeMajor, upscale
Houston$28,300$81,521$157,727
Dallas$26,097$75,995$148,271
Austin$25,463$75,737$148,313
San Antonio$25,463$75,737$148,313
Miami$29,424$83,468$165,416
Jacksonville$29,002$82,596$163,350
West South Central region (includes Texas)$26,762$77,742$151,557
South Atlantic region (includes Florida)$28,567$81,076$161,511
U.S. average$28,458$82,793$164,104

Two notes on reading this table. First, the report shows identical job costs for Austin and San Antonio in 2025, which suggests the two cities share the same underlying cost data; the resale values for the two cities differ. Second, the report does not publish separate figures for Tampa or Orlando. For those cities, the South Atlantic regional figure is the closest published benchmark, and Jacksonville and Miami bracket it. Every figure here is a 2025 number; check the current year's edition before you lock a budget.

What makes one kitchen cost more than another?

  • Layout changes. Moving the sink, range or refrigerator means moving drain lines, water lines, gas lines, vents and circuits. In slab-on-grade homes, common in both Texas and Florida, moving a sink drain can mean cutting and trenching the concrete floor.
  • Cabinets. Cabinets are often the largest single line item. Refacing (new doors on old boxes), stock, semi-custom and custom cabinets sit at very different price points.
  • Counters and backsplash. Laminate, solid surface, quartz and natural stone differ in material and fabrication cost, and stone needs templating after the cabinets are set.
  • Appliances. Built-in and commercial-style units cost more and often need bigger circuits, gas upgrades or more powerful hoods.
  • Structural work. Taking out a wall may require an engineer, a beam and a structural permit.
  • Hidden conditions. Rotted subfloor near an old dishwasher, outdated wiring, or cast iron drains are common surprises once walls open. Older homes may also trigger federal lead-safe work rules (see below).
  • Location and permits. Permit fees, plan review, engineering and inspection requirements vary by city and county.

A sensible planning habit is to keep a separate contingency for things nobody can see until demolition. Ask each bidder how they price unforeseen conditions and how a change order will be written. Our change order guide explains how that should work, and remodel costs in Texas and Florida covers other projects.

Is a kitchen remodel worth it? What the 2025 resale data says

"ROI" for a remodel usually means how much of the cost shows up in the home's resale value. The Cost vs. Value report measures this by surveying real estate agents (more than 6,000 in 2025, through the National Association of Realtors' Realtors Property Resource) about how much each project adds to a sale price in their market. It is an opinion-based estimate, not an appraisal of your house, but it is the most widely cited dated source.

Metro (2025)Minor, midrange: cost recoupedMajor, midrange: cost recoupedMajor, upscale: cost recouped
Houston106.1%46.8%33.2%
Dallas120.4%51.8%34.3%
Austin119.8%51.4%37.3%
San Antonio121.3%49.7%37.3%
Miami107.3%48.8%34.2%
Jacksonville103.8%49.2%35.7%
U.S. average112.9%50.9%35.7%

The pattern is consistent across every Texas and Florida city in the report: a modest refresh of a working kitchen was estimated to return more than its cost at resale, while full midrange rebuilds returned about half, and upscale rebuilds about a third. That does not mean a major remodel is a mistake. It means a major remodel is mostly a decision about how you want to live in the house, not an investment that pays for itself at sale. If you plan to sell within a year or two, the data favors a focused refresh. If you plan to stay for a decade, function and durability matter more than the resale percentage.

What order does a kitchen remodel go in?

Most kitchen remodels, minor or major, follow the same sequence. Knowing it helps you read a contractor's schedule and spot a bid that skips steps.

  1. Define goals and budget. List what does not work now (storage, counter space, traffic flow, lighting, ventilation, accessibility). Decide minor or major. Set a budget that includes a contingency.
  2. Measure and document. Photograph and measure the room, note where windows, doors, vents, the electrical panel, gas line and plumbing are, and find out when the house was built (it matters for lead paint rules).
  3. Design. Work with a kitchen designer, architect, design-build firm or cabinet supplier on a layout, elevations and a cabinet plan. Choose appliances early, because their sizes and power or gas needs drive the cabinet plan and the electrical design.
  4. Check rules. Confirm permit needs with your building department. If you live in a condo or a community with an HOA, get the association's written approval rules now. See HOA architectural approval.
  5. Bid and hire. Get comparable written bids based on the same drawings and specifications. Verify licenses and insurance. See how to hire a general contractor and how to compare bids.
  6. Contract and permits. Sign a written contract with the required state notices. The contractor applies for permits. In Florida, a Notice of Commencement is usually recorded for jobs over $2,500 (see below).
  7. Order long-lead items. Cabinets, appliances, specialty sinks, windows and custom hoods can take weeks or months. Many contractors will not start demolition until cabinets are confirmed.
  8. Protect the house and demolish. Seal off the work area, protect floors, shut off utilities, and remove the old kitchen. In pre-1978 homes, lead-safe practices apply when paint is disturbed.
  9. Structural and rough-in work. Framing changes, then rough plumbing, gas, electrical and duct work for the hood. This is the "rough" stage, and inspections happen before walls are closed.
  10. Close walls. Insulation if exterior walls were opened, then drywall, texture and primer.
  11. Flooring (often before or after cabinets). Some floors go under cabinets, some butt up to them. Ask your contractor which order they use and why.
  12. Cabinets, then counters. Cabinets are set and leveled. Stone or quartz counters are templated after cabinets are installed, then fabricated and installed.
  13. Backsplash, finish plumbing and electrical. Tile, sink and faucet, disposal, dishwasher, lights, outlets and switches, then appliances.
  14. Final inspections and punch list. The building department signs off; you walk the job and list defects. Hold back final payment until the punch list and paperwork are done. See punch list and closeout.

How long does a kitchen remodel take?

There is no reliable statewide average for kitchen remodel duration, so be wary of any single number. What you can do is add up the phases that apply to your job:

  • Design and selections. A refresh with no layout change can be designed quickly. A full redesign with custom cabinets takes longer, and every late change to the plan resets the clock.
  • Permits. Florida law sets deadlines for local building departments. Under section 553.792, Florida Statutes, as amended by Chapter 2026-63 (effective July 1, 2026), a local government must decide complete applications for existing single-family homes within 5 business days for listed permit types, including electrical, plumbing, gas, mechanical and structural permits, where the work is under $15,000. Larger residential permits have longer deadlines (30 business days for structures under 7,500 square feet). If the county or city misses the deadline without a valid reason, it must reduce the permit fee by 10% for each business day late. Texas has a different tool: under Local Government Code chapter 247 (H.B. 14, 2023), if a city or county does not act on a plan review or inspection within 15 days after its own deadline, the applicant may use a qualified third-party reviewer or inspector at no extra fee to the city.
  • Lead times. Ask the cabinet supplier and appliance dealer for written lead times before you sign. They often control the start date more than the contractor does.
  • Construction. A minor remodel with no layout change is the shortest path. A major remodel adds rough-in, inspections, drywall and counter fabrication, each of which waits on the step before it.
  • Inspections and punch list. Failed inspections and slow punch list work are the most common reasons a job "almost done" stays almost done.

Ask every bidder for a written schedule with these phases and a planned start date, and put the completion terms in the contract. The timelines and delays guide explains delay clauses and what to do when a job stalls.

Do I need a general contractor for a kitchen remodel?

For a cabinet-door and paint refresh, maybe not. For any remodel that touches walls, wiring, plumbing or gas, a single responsible contractor is usually the safer path, and in Florida it is often a legal requirement. Here is how the two states differ.

Florida

Florida requires a state license for contracting work on buildings. Under section 489.105, Florida Statutes, general (CGC), building (CBC) and residential (CRC) contractors are Division I licenses; a residential contractor may work on one-, two- and three-family homes of up to two habitable stories. Under section 489.113, a general, building or residential contractor must subcontract electrical, mechanical, plumbing, roofing, sheet metal, swimming pool and air-conditioning work unless the contractor also holds that trade license. Electricians are licensed separately (Chapter 489, Part II). Plumbing contractors are Division II licenses (certified "CF" or registered "RF"), and Florida's definition of plumbing contractor includes natural gas and liquefied petroleum gas piping.

Florida has a minor-work exemption: under section 489.103(9), casual, minor or inconsequential work with an aggregate price under $2,500 does not need a contractor license, but it does not apply if the job is part of a larger project, if a job is split to get under the limit, or if the person advertises as a contractor. A kitchen remodel will almost never fit. Check any Florida license with DBPR; see Florida contractor license lookup.

Texas

Texas does not license general contractors or remodelers at the state level. The City of Austin states it plainly: in Texas anyone can be a general contractor, including homeowners. What Texas does license are the trades a kitchen depends on:

  • Electrical work requires a state license from the Texas Department of Licensing and Regulation (TDLR) under Occupations Code section 1305.151.
  • Plumbing, which Texas law defines to include gas piping, requires a license, registration or endorsement from the Texas State Board of Plumbing Examiners, and anyone advertising plumbing must have a responsible master plumber (Occupations Code section 1301.351).
  • HVAC work, including changes to ducted systems, requires a TDLR air conditioning and refrigeration contractor license (section 1302.251).

Cities add their own layer. Austin requires general contractors, trade contractors and homeowners acting as contractors to register with the city before construction tied to a permit. See Texas city contractor registration and Texas contractor license requirements.

Who else might you hire?

OptionWhat they doWatch for
General contractor or remodelerRuns the whole job, hires and schedules licensed trades, pulls permits, is your single point of responsibility.In Florida, verify the Division I license. In Texas, verify city registration and the licenses of the electrician, plumber and HVAC contractor.
Kitchen designerPlans the layout, cabinets and details. Some hold National Kitchen and Bath Association (NKBA) certifications.A designer may or may not manage construction. Get the drawings in a form any contractor can bid on.
Design-build firm or showroomDesign and construction under one contract.Fewer competing bids. Ask whether the design fee is credited if you build with them, and who owns the drawings if you do not.
Cabinet or countertop companySupplies and installs its product.Installation-only firms usually do not handle permits, plumbing or electrical. Someone still has to coordinate the trades.
Architect or engineerNeeded for structural changes, larger openings, or when your city requires sealed drawings.Ask the building department up front what drawings are required for your scope.

The design-build vs. architect vs. GC guide compares these paths in more depth.

Do I need a permit for a kitchen remodel?

Usually yes, unless you are only replacing finishes. The trigger is not the word "kitchen"; it is the type of work. The table shows the common triggers.

WorkPermit usually needed?Why
Paint, cabinet doors, hardware, like-for-like countersUsually noFinish work with no system changes. Confirm locally.
Replacing a kitchen faucet or disposal like-for-likeOften no in Texas citiesTexas Occupations Code 1301.551(c) lets cities skip plumbing permits for leak repairs and replacing kitchen faucets, disposals and similar items.
New circuits, moved outlets, new lighting, panel workYesElectrical permit and inspection.
Moving the sink, adding a pot filler or prep sinkYesPlumbing permit; drain and vent changes are inspected.
New or moved gas line for a rangeYesGas work is plumbing work in both states and is inspected and pressure-tested.
Vented range hood through a wall or roof, duct changesUsually yesMechanical permit; may also touch the roof or exterior wall.
Removing or opening a wallYesBuilding permit; load-bearing walls need engineering.
New or relocated exterior window or doorYesBuilding permit; in Florida, the product must be approved for wind loads.

Florida's new $7,500 permit exemption does not cover most kitchens

Starting July 1, 2026, section 553.79, Florida Statutes (as amended by Chapter 2026-63, HB 803), requires local governments to exempt single-family homeowners or their contractors from building permits for work valued under $7,500. The exemption does not apply to any electrical, plumbing, structural, mechanical or gas work, and it does not apply to property partly or entirely in a flood hazard area. You must submit a written exemption request with the contract or other proof of the work's value, and you may not split a project to stay under the limit. A cabinet and counter swap might qualify; a kitchen with new circuits or moved plumbing will not.

Texas city examples

In Dallas, the city's one- and two-family remodel checklist asks for dimensioned floor plans showing existing walls, walls to be removed and new walls, smoke and carbon monoxide alarm locations where required, a schedule of replaced doors and windows, a site plan when exterior walls are affected, and a statement that the work complies with the EPA lead renovation rule. Dallas also lets homeowners pull certain permits on their own homestead without registering as a contractor, including interior remodeling, plumbing, mechanical and electrical repairs after passing a city exam, if they do the work themselves without paid help. In Austin, the general contractor registered on a permit is responsible for activating it, scheduling inspections and obtaining final sign-off. For other cities see do I need a permit in Texas and the Houston, San Antonio and Austin city pages (Houston, San Antonio, Austin, Dallas).

Florida readers should also read do I need a permit in Florida. Building permits for single-family homes in Florida expire one year after issuance or on the effective date of the next Florida Building Code edition, whichever is later, unless the local government extends them.

Can I move plumbing, gas lines or walls in my kitchen?

Yes, almost always, but each move has a cost and a permit. Know what you are asking for before the design is final.

Moving the sink

A sink needs a drain with the right slope and a vent. On a raised floor you can usually reroute below. On a concrete slab, moving the sink more than a short distance often means saw-cutting the slab, trenching, connecting to the existing drain and patching, plus a plumbing inspection before the trench is closed. Ask your plumber to locate the existing drain and explain the route before you commit to an island sink.

Gas ranges and cooktops

In Texas, gas piping is part of the legal definition of plumbing (Occupations Code 1301.002), so it is licensed plumbing work. In Florida, the plumbing contractor license covers natural gas and LP gas installation and venting (section 489.105). Expect a permit, a pressure test and an inspection. If you are switching from electric to gas or adding a larger range, ask whether the gas meter and line size can handle the new load.

Walls

A wall that carries roof or floor loads needs a beam sized by someone qualified, usually an engineer, and a building permit. In Florida, structural work is the responsibility of a licensed general, building or residential contractor (section 489.113). Walls can also hide plumbing vents, ductwork and wiring that must be rerouted. A quick visit from your contractor and, if needed, an engineer before design is final avoids surprises.

Windows and exterior doors in Florida

If your kitchen plan adds or moves a window or patio door, Florida requires products to carry state or local product approval showing they meet the Florida Building Code, including wind-pressure ratings. The statewide product approval system is created by section 553.842, and the Florida Building Commission's product approval database lets you filter for products approved for the High-Velocity Hurricane Zone and for impact resistance. Miami-Dade County's Product Control Section separately reviews windows, exterior doors, glazing, shutters and other envelope products for use in that county. Ask your contractor for the approval number of each exterior product before ordering.

What electrical work does a kitchen need?

Kitchens carry more electrical load than any other room. The electrical code your city has adopted sets the rules, including how many circuits serve the countertop outlets and which outlets need protection against shock and arc faults. Your electrician designs to that code; your job is to give the electrician a complete list of what will be plugged in or hard-wired.

Appliances that commonly need their own circuit include the range or cooktop and wall oven (often a large 240-volt circuit for electric models), the dishwasher, the disposal, a built-in microwave, the refrigerator, and any built-in specialty appliances such as warming drawers or wine coolers. Islands and peninsulas have specific outlet rules, which is another reason to finish the layout before wiring starts.

Older homes in both states may need a panel upgrade to support an all-electric kitchen or induction cooktop. That is a utility coordination and permit issue, so ask early.

In Texas, electrical work must be done by a person licensed by TDLR under Occupations Code chapter 1305. There is a narrow exemption in section 1305.003(a)(6) for work on a dwelling by a person who owns and lives in it, but only for work not specifically regulated by a city ordinance; most Texas cities do regulate it and require permits. In Florida, a general contractor must subcontract electrical work to a licensed electrical contractor unless it holds that license (section 489.113). Use the TDLR license search or Florida DBPR lookup to confirm the electrician's license before work starts.

How should I plan the layout? The work triangle and NKBA guidelines

The "work triangle" is the classic layout idea that the sink, cooktop and refrigerator should form a compact triangle, so a cook can move between them easily without people walking through the middle. It is still a useful test: imagine making a meal, then unloading groceries, then cleaning up, and trace your steps on the plan.

Modern kitchens often plan in zones instead: a prep zone near the sink and the main counter run, a cooking zone with landing space on both sides of the cooktop, a cleanup zone with the dishwasher next to the sink, and a storage zone near the refrigerator and pantry. Two-cook kitchens, islands with prep sinks and coffee or beverage stations all push past the simple triangle.

The most detailed professional reference is the National Kitchen and Bath Association's Kitchen and Bath Planning Guidelines with Support Space and Accessibility. The fifth edition was prepared to align with the 2024 International Residential Code. It covers walkway and clearance recommendations, landing areas next to appliances, seating clearances, ventilation calculation methods, island power outlets, lighting, and accessible design. The guidelines are recommendations for designers, not law; your local building code is what an inspector enforces. If you hire a designer, ask whether the plan follows the NKBA guidelines and where it departs from them.

Layout questions worth asking your designer

  • Is there landing space next to the refrigerator, cooktop, oven and microwave?
  • Can two people pass with the dishwasher open?
  • Does the island leave enough room for seating and a walkway behind it?
  • Does the hood vent to the outside, and is the duct route realistic?
  • Will the refrigerator door and drawers open fully against nearby walls?
  • Where do trash and recycling go, and is it next to the prep area?
  • Is there task lighting over every work surface, not just ceiling lights?
  • If someone in the household uses a wheelchair or walker, or may later, are counter heights, aisle widths and appliance locations planned for that? See aging-in-place remodeling.

Are custom cabinets worth it vs. semi-custom or stock?

Cabinets come in four broad levels. None is "right"; it depends on your layout, budget and how long you will stay.

TypeWhat it meansBest fit
RefacingKeep the existing boxes; replace doors, drawer fronts and hardware, and cover the face frames.Sound boxes and a layout you like. This is what the Cost vs. Value minor remodel assumes.
StockStandard sizes and finishes, built ahead and kept in inventory.Budget jobs and simple layouts; fillers make up gaps.
Semi-customStandard boxes with more sizes, finishes and options. The Cost vs. Value midrange major remodel assumes semi-custom.Most full remodels; good balance of fit and cost.
CustomBuilt to your exact dimensions and design by a shop.Unusual spaces, specific design needs, or high-end finishes. Longest lead time.

The 2025 resale data above is a useful reality check: the upscale kitchen with custom cabinets was estimated to recoup about a third of its cost in every Texas and Florida city in the report. Custom cabinets make sense when you need the fit or want the quality for your own use. In humid Florida and Gulf Coast climates, ask about box material, finish durability and how the sink base resists water damage, regardless of the level you choose.

Can I live at home during a kitchen remodel? Setting up a temporary kitchen

Most families do live at home during a kitchen remodel. It is disruptive, but manageable with planning.

  • Pick a spot. A dining room, laundry room or garage corner near a sink and outlets works. Keep the temporary kitchen out of the dust path.
  • Bring the essentials. Refrigerator (the old one, if it is being replaced), microwave, toaster oven or countertop oven, electric kettle, coffee maker and a slow cooker or electric pressure cooker. Check that you will not overload one circuit.
  • Plan dishes. Washing up in a bathroom or laundry sink gets old quickly. Many families switch to simple meals and some disposable plates for the messiest weeks.
  • Control dust. Ask the contractor how they will seal the work area, protect HVAC returns and clean up daily. Put it in the scope of work.
  • Kids, pets and access. Agree on work hours, which entrance crews use, where they park, restroom access, and how tools and materials are secured.
  • Utility shutoffs. Ask for notice before water, gas or power will be turned off.

Homes built before 1978: lead-safe rules

If your home was built before 1978, the EPA's Renovation, Repair and Painting (RRP) rule applies to paid work that disturbs painted surfaces, unless testing shows the components are lead-free. Under 40 CFR part 745, subpart E, the firm must be EPA-certified, workers must use lead-safe practices, and you must receive EPA's lead pamphlet before work starts. The rule's minor-repair exclusion covers only small areas (6 square feet or less of painted surface per room inside), and window replacement and demolition of painted surfaces are never treated as minor. A kitchen gut in an older home almost always involves the rule. Dallas's remodel checklist specifically requires compliance with it. Ask your contractor for the firm's EPA certification.

What should my kitchen remodel contract include in Texas and Florida?

A clear contract protects both sides. Use our construction contract checklist for the full list. For a kitchen, make sure it includes the drawings, a cabinet and appliance list with model numbers, who buys which materials, allowances (and what happens if you go over), the schedule, the permit plan, how change orders work, how hidden conditions are priced, cleanup and dust control, the warranty, and a payment schedule tied to completed work. The state-specific items below are easy to miss.

Florida

  • Construction lien notice. Any direct contract over $2,500 for a home of up to four units must include the statutory lien law disclosure in section 713.015, in at least 12-point, capitalized, boldface type, signed and dated by the owner. It warns that unpaid subcontractors and suppliers can lien your home even if you paid the contractor.
  • Recovery fund notice. Residential contracts over $2,500 must include the Florida Homeowners' Construction Recovery Fund notice (section 489.1425).
  • Notice of Commencement. Before work starts on most jobs, the owner records a Notice of Commencement and posts a copy at the job site (section 713.13). For direct contracts over $5,000, a copy must be filed with the building department before the first inspection (section 713.135). See Florida Notice of Commencement.
  • Deposit rules. If a contractor takes more than 10% of the price as a first payment on residential work, it must apply for permits within 30 days and start work within 90 days after permits issue, unless there is just cause or you agreed in writing to longer periods (section 489.126). See deposits and payment schedules.
  • Lien releases. Collect written releases from anyone who served a Notice to Owner before you pay, and get the contractor's final payment affidavit before final payment. See Florida construction lien law.

Texas

  • "Know Your Rights" disclosure. Before you sign a residential construction contract, the original contractor must give you the statutory disclosure in Property Code section 53.255.
  • Subcontractor and supplier list. Before work starts, the contractor must give you a list of subcontractors and suppliers with contact information and update it within 15 days of changes, unless you sign the statutory waiver.
  • Retainage. Texas owners must retain 10% of the contract price (or of the value of work done) during the job and for 30 days after completion. If you do not, unpaid subcontractors who follow the rules may have a lien up to the amount you should have held.
  • Bills-paid affidavit and waivers. At final payment the contractor signs a bills-paid affidavit, and lien waivers must follow one of the four statutory forms to be enforceable. See Texas mechanic's liens and Texas lien waivers.
  • RCLA notice. Contracts covered by the Residential Construction Liability Act must include a 10-point bold notice that the contract is subject to Property Code chapter 27.

Both states: the 3-day right to cancel

If you sign a kitchen contract in your home after a salesperson's visit, the federal Cooling-Off Rule and state home-solicitation laws (Texas Business and Commerce Code chapter 601; Florida section 501.025) generally let you cancel until midnight of the third business day after signing. The seller must give you the cancellation notice in writing.

Remodeling a kitchen in a Florida condo or an HOA community

Condo kitchens add a second approval layer: the association. In Florida, section 718.113 says there can be no material alteration or substantial addition to the common elements except as the declaration allows, and if the declaration is silent, 75% of the total voting interests must approve before work begins. Walls between units, the slab, main plumbing stacks and building structure are often common elements, so a kitchen that moves plumbing or opens walls may need more than a simple board sign-off. Read your declaration and the association's alteration rules first.

Water damage is the big risk in a condo kitchen. Under section 718.111(11)(j), a unit owner is responsible for repair costs not paid by insurance when damage to other parts of the condominium is caused by the owner's (or the owner's tenants', guests' or invitees') negligence or failure to follow the declaration or association rules. That is one more reason to use licensed plumbers, follow the association's rules on water shutoffs and work hours, and confirm your contractor's insurance. Our Florida condo renovation guide covers this in detail.

For single-family homes in a Florida HOA, Chapter 2026-63 (effective July 1, 2026) bars an HOA or its architectural committee from requiring a government building permit before it reviews your proposed improvement. In Texas, HOA and deed-restriction rules are set by the community's recorded documents; check them before you design exterior changes such as new windows or vents. See HOA architectural approval.

What are the most common kitchen remodel mistakes?

  1. Choosing finishes before the layout. Appliance sizes and the cabinet plan come first; tile and paint colors come last.
  2. Underestimating hidden conditions. Budget a contingency, and ask how the contractor prices surprises.
  3. Bids that are not comparable. One bid includes cabinets and permits; another assumes you buy cabinets. Give every bidder the same drawings and specifications.
  4. Skipping permits. Unpermitted electrical, gas and plumbing work can create safety risks, insurance problems and trouble when you sell. In Florida, starting work that needs a permit without one is a prohibited act under section 489.127(1)(h).
  5. Too few outlets and too little light. Plan task lighting and outlets on the drawings.
  6. A range hood that does not vent outside, or a duct route that does not work. Decide the duct path during design.
  7. Ignoring the slab. Moving a sink in a slab home is a real cost item, not a detail.
  8. Overpaying up front. Tie payments to completed work. In Texas, hold the 10% retainage. In Florida, collect lien releases.
  9. No written change orders. Every change to scope, price or schedule should be signed before the work is done.
  10. Skipping license checks. In Florida verify the contractor's DBPR license. In Texas verify the electrician's TDLR license and the plumber's state license, plus city registration.
  11. Forgetting the old-house rules. Pre-1978 homes trigger EPA lead-safe work rules when paint is disturbed.

How to choose a provider

  • Decide minor refresh or major remodel, and write down what must change.
  • Find your home's year built; if before 1978, plan for EPA lead-safe work.
  • Choose appliances before finalizing cabinets and electrical.
  • Get condo or HOA alteration rules in writing before design is final.
  • Ask the building department which permits your scope needs.
  • Get at least three bids on the same drawings and specifications.
  • Verify licenses: Florida DBPR for the contractor; TDLR and the Texas plumbing board for trades in Texas.
  • Confirm general liability and workers' compensation coverage in writing.
  • Check the contract for required state notices (FL 713.015 and 489.1425; TX 53.255 and subcontractor list).
  • Tie payments to completed, inspected stages; hold 10% retainage in Texas.
  • In Florida, record and post the Notice of Commencement and collect lien releases.
  • Set up a temporary kitchen and a dust-control plan before demolition.
  • Do a written punch list walk before final payment and keep all final inspection records.

Related general and residential contractors guides

General and residential contractors by state and city

Questions people ask

How much does a kitchen remodel cost in Houston or Dallas?

According to the 2025 Cost vs. Value report, a midrange minor kitchen remodel (new cabinet fronts, counters, sink, two appliances, floor and paint in a 200-square-foot kitchen) averaged $28,300 in Houston and $26,097 in Dallas. A midrange major remodel with new semi-custom cabinets and a new layout averaged $81,521 in Houston and $75,995 in Dallas. Upscale major remodels averaged $157,727 and $148,271. These are 2025 averages for defined projects, not quotes, so use them to judge whether bids are in a reasonable range.

How much does a kitchen remodel cost in Miami, Tampa or Orlando?

The 2025 Cost vs. Value report lists Miami at $29,424 for a midrange minor kitchen remodel, $83,468 for a midrange major remodel and $165,416 for an upscale major remodel. It does not publish separate Tampa or Orlando figures. The South Atlantic regional averages ($28,567 minor, $81,076 major midrange, $161,511 upscale) are the closest published benchmark, and Jacksonville ($29,002, $82,596 and $163,350) is a useful in-state comparison.

Do I need a permit to replace kitchen cabinets and countertops?

Often not, if you are replacing cabinets and counters in the same layout without changing plumbing, wiring, gas or walls. Once you add circuits, move the sink, change the gas line or remove a wall, permits are required. In Florida, the new $7,500 exemption (effective July 1, 2026) covers some small single-family jobs but excludes all electrical, plumbing, gas, mechanical and structural work and any property in a flood hazard area. Always confirm with your local building department.

Can I be my own general contractor for a kitchen remodel?

In Texas, yes; the state does not license general contractors, though cities may require you to register or sign a homeowner affidavit, and electrical, plumbing and HVAC work still need licensed trades unless a narrow homeowner exemption applies. In Florida, you can act as an owner-builder on your own home under section 489.103(7), but you must personally sign the permit and a disclosure statement and directly supervise the work, and you may not hire an unlicensed person to run the job. See the owner-builder guides for both states.

Does a kitchen remodel add value to my home?

It adds some value, but rarely all of the cost. In the 2025 Cost vs. Value report, midrange minor kitchen remodels in Texas and Florida metros were estimated to return about 104% to 121% of cost at resale, while midrange major remodels returned about 47% to 52% and upscale remodels about 33% to 37%. Those are agent estimates averaged by city, not an appraisal. If resale is your main goal, a focused refresh tends to perform better than a full rebuild.

What is the difference between a kitchen designer and a design-build contractor?

A kitchen designer plans the layout, cabinets, lighting and details, and may or may not manage construction. A design-build firm offers design and construction under one contract, so one company is responsible for both. Hiring a designer separately lets you bid the drawings to several contractors; design-build can be simpler but usually means fewer competing bids. Ask who owns the drawings and whether design fees are credited toward construction.

Who should install a gas line for a new range?

A licensed plumber. Texas law defines plumbing to include piping that supplies gas, so gas work requires a license from the Texas State Board of Plumbing Examiners. Florida's plumbing contractor license covers natural gas and liquefied petroleum gas piping and venting. Expect a permit, a pressure test and an inspection. Do not let a cabinet installer or handyman connect gas lines.

Do I need to follow lead paint rules in an older kitchen?

If the house was built before 1978 and you hire someone to do work that disturbs paint, the EPA Renovation, Repair and Painting rule generally applies unless testing shows the painted parts are lead-free. The firm must be EPA-certified, use lead-safe practices and give you EPA's lead pamphlet before starting. The rule generally does not apply to homeowners working on their own home unless they rent it out, run a childcare center there or flip houses.

How big a deposit should I pay for a kitchen remodel?

There is no single legal maximum in either state, but there are protections. In Florida, a contractor who takes more than 10% up front on residential work must apply for permits within 30 days and start within 90 days after permits issue, unless you agreed otherwise in writing. In Texas, you must hold back 10% retainage until 30 days after completion. In both states, tie payments to completed, inspected work rather than to calendar dates.

Can I remodel my Florida condo kitchen without board approval?

Usually not if the work touches common elements, plumbing stacks, walls between units or building structure. Florida section 718.113 bars material alterations of common elements except as the declaration allows, and requires 75% of voting interests if the declaration is silent. Many associations also have alteration applications, insurance requirements and work-hour rules. Unit owners can be responsible under section 718.111(11)(j) for water damage caused by their negligence or rule violations.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration