Local Guide · Hurricane shutters and impact windows
How Do Condo Buildings Replace All Their Windows? Engineering, SIRS, Votes, Access and Costs in Florida and Texas
A practical, statute-level guide for condo boards and owners planning a building-wide impact window and door replacement, from the structural integrity reserve study and owner votes to the 2026 threshold inspection rule, bidding, access and field testing.
A condo building-wide window replacement is an engineered project: the board confirms who is responsible under the declaration, uses the SIRS and engineer's findings, gets an owner vote if Florida s. 718.113(5) requires one, bids on one specification under s. 718.3026, and permits the work with wind calculations and, since 2026, threshold special inspections in buildings over three stories or 50 feet. Owners must give reasonable access, and in Florida generally do not pay to remove or reinstall protection for association repairs.
Key facts
- Florida s. 718.112(2)(g) lists windows and exterior doors among the minimum items in a condo structural integrity reserve study for buildings three habitable stories or higher.
- For budgets adopted on or after Dec. 31, 2024, owners of associations required to have a SIRS generally cannot vote to waive or reduce reserves for SIRS items (s. 718.112(2)(f)).
- Milestone inspections are due by Dec. 31 of the year a building turns 30, and every 10 years after, or at 25 where the local agency requires it (s. 553.899).
- A 2026 binding interpretation of FBC 110.8.1, ratified Jan. 26, 2026, requires threshold inspections by a certified special inspector for all window and door installations in threshold buildings, per Miami-Dade County.
- A threshold building is any building over three stories or 50 feet tall, or a large assembly occupancy (s. 553.71).
- Under s. 718.113(5)(a), a board may not require the same type of code-compliant hurricane protection again unless it reached end of useful life or is needed to prevent damage.
- Since July 1, 2025 (ch. 2025-175), an association that removes and reinstalls hurricane protection for its own repairs may not charge the owner (s. 718.113(5)(d)).
- Florida s. 718.3026 requires competitive bids for association contracts over 5% of the total annual budget including reserves; the lowest bid need not be accepted.
- FBC 1609.1.2: glazed openings within 30 feet of grade need large missile protection; above 30 feet, small missile.
- Texas Property Code s. 82.107(c): unless the declaration says otherwise, unit owners pay for windows and doors serving only their unit (post-1994 condos).
What is a building-wide window replacement project, and why do condo boards start one?
A building-wide window replacement project is when a condominium association replaces the exterior windows and glass doors across a whole building, or a whole elevation of it, under one engineered design, one permit strategy and one contract. It is very different from one owner swapping out a bedroom window. In a mid-rise or high-rise, the openings are part of the building envelope, the windows sit at heights where wind pressures are much higher, and the work touches common elements, unit interiors, the association's insurance and its reserve plan all at once.
Boards in Florida and coastal Texas usually start these projects for one or more of these reasons:
- End of useful life. Older aluminum windows and sliders leak, corrode near salt water, and stop locking or sliding properly. Once leaks show up inside units, the board is usually dealing with water damage claims, not just a window problem.
- The structural integrity reserve study (SIRS). Florida law now lists "windows and exterior doors" as one of the items a SIRS must study for condo buildings three habitable stories or higher. The study puts a remaining useful life and a replacement cost estimate on them, and the reserve schedule follows from that.
- Milestone inspection findings. The milestone inspection under section 553.899 is a structural inspection, not a window inspection, but deterioration found around openings or slab edges can lead to repairs that make it sensible to replace windows at the same time.
- Hurricane protection. Many older buildings still rely on a mix of owner-installed shutters, panels and unprotected glass. Florida section 718.113(5) lets the board, with an owner vote where required, install hurricane protection or require owners to install it, so one uniform system replaces a patchwork.
- After a storm. When a hurricane breaks glass or tears out units, the board often decides to replace the whole system rather than patch individual openings with mismatched products.
This guide walks through each stage: who is responsible, what Florida and Texas law says about votes, access and costs, how the engineering and permitting work in 2026 (including the new threshold-building inspection rule), how to bid the job, how field testing works, and what each unit owner should do to protect their home during the work. It is general information, not legal advice. For your building's documents, talk to the association's attorney; for engineering, the design professional of record. For background on the product types, see impact windows explained, and for the condo hurricane-protection statute in depth, see condo hurricane protection under 718.113.
Who is responsible for condo windows: the association or the unit owner?
The first question in any project is who owns, maintains and pays for the windows. The answer starts with the declaration of condominium, not with a general rule. Some declarations make the windows and sliders part of the unit. Some make them limited common elements, meaning common elements reserved for one unit's use. Some make the association responsible for all exterior windows and doors. Florida's chapter 718 defines common elements as the parts of the condominium property not included in the units, and limited common elements as common elements reserved for the use of certain units, "as specified in the declaration" (section 718.103). So the boundaries clause in your declaration is the key page to read.
Florida
Florida section 718.113(5) gives the board a set of powers over "hurricane protection" that apply to every residential and mixed-use condominium in the state, no matter when it was created. The board must adopt hurricane protection specifications for each building, which may include color and style, and the specifications must comply with the building code. Installing, maintaining, repairing, replacing and operating hurricane protection under that subsection is not a "material alteration or substantial addition" to the common elements, which matters because material alterations otherwise often need a large owner vote under the declaration.
The statute also treats exterior windows and doors as part of the picture. For example, an owner vote to require hurricane protection is not needed if the installation, maintenance, repair and replacement of the hurricane protection, "or any exterior windows, doors, or other apertures protected by the hurricane protection," is already the association's responsibility under the declaration.
Texas
Texas condominiums created by a declaration recorded on or after January 1, 1994 are governed by the Uniform Condominium Act, Texas Property Code chapter 82 (section 82.002). Section 82.107(c) says that, except as provided by the declaration, each unit owner is responsible for the cost of maintenance, repair and replacement of windows and doors serving only the owner's unit. That is the reverse of what many Florida owners expect. Older Texas condos (declarations recorded before 1994) are governed mainly by their own documents and the older condominium act unless they opted in, and section 82.107 is not on the short list of chapter 82 sections that automatically apply to them. If your building is in Galveston, Corpus Christi or South Padre Island, have the association's attorney confirm which law and which declaration clauses control before any cost allocation is announced.
| Question | Florida (ch. 718) | Texas (Prop. Code ch. 82, post-1994 condos) |
|---|---|---|
| Default rule on who pays for unit windows | Set by the declaration; 718.113(5) lets the board install or require hurricane protection | Unit owner pays for windows and doors serving only that unit, unless the declaration says otherwise (82.107(c)) |
| Is replacing hurricane protection a material alteration? | No, if done under 718.113(5) | Check declaration and 82.102 powers to regulate appearance and replacement |
| Association access to units | Irrevocable right of access during reasonable hours for maintenance, repair or replacement (718.111(5)) | Owners must afford access reasonably necessary for maintenance, repair and replacement (82.107(a)) |
| Who repairs damage caused by access | Declaration and contract; removal and reinstall cost rules in 718.113(5)(d) | The party responsible for the damage, or the association if it is responsible, must promptly repair it (82.107(a)) |
When does a Florida condo board need an owner vote to replace windows or install hurricane protection?
Under section 718.113(5)(a), the board may, subject to the competitive bidding rules in section 718.3026 and with the approval of a majority of the voting interests, install hurricane protection or require unit owners to install hurricane protection that complies with or exceeds the applicable building code.
The vote has formal steps:
- The vote to require installation must be set out in a certificate attesting to the vote and stating the date by which the hurricane protection must be installed.
- The board must record the certificate in the public records of the county where the condominium is located.
- After recording, the board must mail or hand deliver a copy of the recorded certificate to the owners at their addresses in the association's records, or send it electronically to owners who consented to electronic notice.
- Failing to record or send the certificate does not make the vote invalid or unenforceable, but a board that skips the steps invites disputes.
When no vote is needed
The statute says an owner vote is not required if the declaration, as recorded or amended, already makes the association responsible for installing, maintaining, repairing and replacing the hurricane protection or the exterior windows, doors and other apertures it protects, or if the declaration already requires unit owners to install hurricane protection. Many newer Florida declarations already put windows on the association, so the board can move ahead under its maintenance duty without a separate vote, though it still must follow its bidding and budgeting rules.
Operating shutters
Section 718.113(5)(b) lets the board operate hurricane protection, such as closing shutters on a unit, without the owner's permission only when that is necessary to preserve and protect the condominium property or association property. Boards often add this to their hurricane plan for absentee owners.
Approving an owner's own installation
Under 718.113(5)(c), if the documents require approval, the board may not refuse an owner's installation or replacement of hurricane protection that conforms to the board's adopted specifications, though it can require the owner to follow an existing unified building scheme for exterior appearance. That rule matters before a building-wide project: owners who already installed conforming impact windows did so with legal protection.
Can owners who already installed impact windows opt out of a building-wide replacement?
This is one of the most contested questions in Florida condo window projects. Section 718.113(5)(a) has a direct limit: if hurricane protection that complies with or exceeds the current applicable building code has been previously installed, the board may not install the same type of hurricane protection, or require owners to install the same type, unless the installed protection has reached the end of its useful life or unless it is necessary to prevent damage to the common elements or to a unit.
In plain terms: if an owner put in code-compliant impact windows a few years ago, the board generally cannot force that owner to replace them with another set of impact windows simply because the rest of the building is being done. The exceptions are real, though:
- End of useful life. If the engineer or the SIRS shows the owner's units have reached the end of their useful life, the limit no longer protects them.
- Preventing damage. If the existing units leak into the slab, the unit below or the common elements, the board can require replacement to prevent that damage.
- Not code compliant. The protection only applies to protection that "complies with or exceeds the current applicable building code." Units installed without a permit, outside their product approval, or rated below the required design pressure may not qualify.
Who pays when some units are excluded?
The statute limits installing the same type again; it does not by itself say how the cost of the rest of the project is shared. Owners who already paid for their own windows often ask for a credit. Whether one is possible depends on the declaration, how the expense is classified (common expense, limited common element expense or owner cost) and the association attorney's advice. Ask early, in writing, and ask the engineer to document the existing units' product approval numbers, permit records and condition so the decision rests on facts.
Practical tip for owners: if you installed impact windows, gather your permit number, final inspection record, the Florida product approval or Miami-Dade NOA numbers and any warranty now. You can look up approvals using the steps in our product approval lookup guide and our Miami-Dade NOA guide.
Are windows included in Florida's structural integrity reserve study (SIRS)?
Yes. Florida section 718.112(2)(g) requires a residential condominium association to have a structural integrity reserve study completed at least every 10 years for each building that is three habitable stories or higher, as determined by the Florida Building Code. At a minimum, the study must cover these items as they relate to the structural integrity and safety of the building:
- Roof.
- Structure, including load-bearing walls and other primary structural members and systems.
- Fireproofing and fire protection systems.
- Plumbing.
- Electrical systems.
- Waterproofing and exterior painting.
- Windows and exterior doors.
- Any other item with a deferred maintenance expense or replacement cost over $25,000 (or the inflation-adjusted amount set by the state's condominium division, whichever is greater) whose failure would negatively affect the items above.
What the SIRS must say about windows
The statute requires the study to identify each item visually inspected, state its estimated remaining useful life and estimated replacement cost or deferred maintenance expense, and provide a reserve funding plan with a recommended annual reserve amount that reaches that replacement cost by the end of the item's remaining useful life. It must include at least a baseline funding plan that keeps the reserve cash balance above zero.
For items with a remaining useful life of more than 25 years, the study may recommend that replacement reserves are not needed, though it may recommend a deferred maintenance amount. New impact windows may fall into that category in a future study; older windows near the end of life will not.
Who performs it, and the conflict-of-interest rule
A SIRS must be performed or verified by a Florida-licensed engineer or architect, or by a person certified as a reserve specialist or professional reserve analyst by the Community Associations Institute or the Association of Professional Reserve Analysts. Any design professional or licensed contractor who bids to perform a SIRS must disclose in writing any intent to bid on the repair or replacement work the study may recommend, and anyone bidding on the recommended work may not have an undisclosed interest in the firm that did the study. A contract can be terminated by the association if the required disclosure was not made. For a window project, this means the board should ask every bidder, in writing, whether they or a relative have any interest in the reserve study firm.
Reserves for windows cannot be waived the old way
Under section 718.112(2)(f), budgets of associations that must have a SIRS must keep reserves for the SIRS items the association is responsible for under the declaration, based on the most recent study. For a budget adopted on or after December 31, 2024, unit owners of such an association may not vote to provide no reserves or less reserves than required for the SIRS items, with a narrow exception for multicondominiums with a division-approved alternative funding method. If the declaration makes the association responsible for windows, window reserves are now mandatory in practice.
Deadlines and distribution
- Associations that existed on or before July 1, 2022 and are controlled by unit owners had to complete their first SIRS by December 31, 2025. One that must complete a milestone inspection on or before December 31, 2026 may do the SIRS together with it, but no SIRS may be completed after December 31, 2026 under that transition rule.
- Within 45 days of receiving the SIRS, the association must give each owner a copy, or notice that it is available, and file a statement with the state's condominium division saying it was completed and distributed.
- Directors who willfully and knowingly fail to complete a required SIRS breach their fiduciary duty to owners, and an officer or director must sign an affidavit acknowledging receipt of the completed study.
If you are a unit owner, ask for the SIRS line item on windows and exterior doors. The remaining useful life and replacement cost estimate there will usually tell you whether a project is coming, and roughly when.
How do milestone inspections relate to window replacement?
Florida's milestone inspection law, section 553.899, applies to buildings three habitable stories or more that are subject, in whole or in part, to residential condominium or cooperative ownership. The building must have a milestone inspection by December 31 of the year it reaches 30 years of age (based on the certificate of occupancy date) and every 10 years after that. The local enforcement agency may require the first inspection at 25 years where local conditions, such as proximity to salt water, call for it.
What the milestone inspection is, and is not
It is a structural inspection by a Florida-licensed architect or engineer of load-bearing elements and primary structural members and systems, to attest to life safety and the adequacy of the structural components. The statute says plainly that its purpose is not to determine whether the existing building complies with the Florida Building Code. So a milestone inspection will not tell you whether your windows meet today's impact or design pressure rules. That question belongs to the SIRS (for remaining life and cost) and to the engineer who designs the replacement.
The two phases
- Phase one: a visual examination of habitable and nonhabitable areas, including major structural components, with a qualitative assessment. It must be completed within 180 days after the owners receive the local agency's written notice. If no signs of substantial structural deterioration are found, phase two is not required.
- Phase two: required if substantial structural deterioration is found. It may involve destructive or nondestructive testing and must recommend a program for assessing and repairing the distressed areas. A phase two progress report with a timeline is due within 180 days after the phase one report.
Where windows come in
Window openings are where water gets into concrete and where slab edges, balcony slabs and openings meet. If a milestone or SIRS inspection finds deterioration around openings, the repair program may require removing windows and sliders anyway to repair the concrete. Boards often coordinate concrete restoration and window replacement so units are opened only once. Ask the engineer whether the repair sequence and the window installation can share access equipment, scaffolding or swing stages, and whether the window anchors depend on concrete that is being repaired.
Notices owners should receive
Within 14 days of receiving the local agency's notice that a milestone inspection is required, the association must notify owners and give the completion date. Within 45 days of receiving a phase one or phase two report, it must distribute the inspector-prepared summary to each owner, post it conspicuously on the property, and publish the full report and summary on the association's website if it is required to have one. The association pays the inspection costs for the parts of the building it maintains. Under 718.112(2)(g), a milestone inspection done within the past 5 years that meets the SIRS rules may be used in place of the SIRS visual inspection.
How is a high-rise window replacement engineered?
High-rise windows are engineered products installed to an engineered design. A board that tries to shortcut this step usually pays for it later in failed inspections, change orders or leaks. Here is what the design professional is working out.
Design pressure for each opening
Design pressure (DP) is the positive (pushing in) and negative (pulling out) wind pressure, in pounds per square foot, that a window must resist. It depends on the building's design wind speed, its Risk Category, its exposure (how open the surrounding terrain or water is), its height and the location of each opening on the wall. That is why Miami-Dade's 2026 threshold-building checklist requires "wind calculations for all openings related to the new installation" under Florida Building Code section 1620 and ASCE 7-22 Chapter 30, the components and cladding chapter of the national wind load standard. A window near a corner on the 30th floor and a window mid-wall on the 3rd floor may need very different ratings, so the window schedule should list each opening's required DP. For more on how DP works, see design pressure ratings explained.
Wind speed and exposure in the HVHZ
Miami-Dade and Broward are the High-Velocity Hurricane Zone (HVHZ). Florida Building Code section 1620.2 sets HVHZ design wind speeds (3-second gust) of 175 mph in Miami-Dade and 170 mph in Broward for Risk Category II buildings, which includes most residential condominiums, and section 1620.3 treats all HVHZ buildings as Exposure Category C unless Exposure D applies. Oceanfront towers are often in Exposure D, which raises pressures further. Outside the HVHZ, the design wind speed comes from the code's wind maps for the site.
Large missile versus small missile
Under FBC 1609.1.2, glazed openings within 30 feet of grade must meet the ASTM E1996 large missile test, and those more than 30 feet above grade must meet the small missile test. In the HVHZ, sections 1626.2 and 1626.3 set the same 30-foot line using TAS 201 and TAS 203: the large missile is a 9-pound 2x4 at 50 feet per second, and the small missile test fires 2-gram steel balls at 130 feet per second, 30 impacts per specimen. In a tower, that means the lower floors and podium usually need large-missile products and the upper floors may use small-missile products, though many boards specify large-missile products throughout for simplicity. For test details, see missile impact testing standards.
The 60-foot exception and gravel roofs
FBC 1609.1.2 lets glazing in Risk Category II, III or IV buildings go unprotected if it is more than 60 feet above the ground and more than 30 feet above any aggregate-surface roof within 1,500 feet. Gravel (aggregate) roofs matter because roof gravel becomes airborne debris in a hurricane. This exception sits in the general wind-borne debris section; HVHZ buildings follow the HVHZ provisions in section 1626, which require building envelope components to meet the impact criteria. Do not assume upper floors can be unprotected without the engineer confirming the code path for your building.
Mullions, bucks and anchors
Mullions (the members that join two windows side by side or stacked) need their own product approvals and sizes on the permit. Many older buildings have wood bucks (wood framing strips in the concrete opening). Miami-Dade now requires wood buck calculations for threshold-building window permits when the buck is 1-1/2 inches thick or more, under FBC section 1710. Anchors must match the product approval's installation drawings for the substrate (concrete, block, steel), embedment and edge distance. Spalled or patched concrete at the opening can change what anchor is allowed.
Glass, sizes and labels
Product approvals list a glass schedule. Miami-Dade requires the permit plans or the NOA to show which glass type and thickness and which options will be used. FBC 1709.5.1 requires each window and sliding door to carry a permanent label tracing it to the manufacturer and product, plus a permanent or temporary label with the positive and negative design pressure, maximum size tested, impact rating if applicable, the Florida or Miami-Dade approval number and the test standard. The temporary label must stay on until the building official's final approval, so tell owners not to peel stickers off new windows.
Escape openings and fall prevention
Replacement windows in required emergency escape openings get some relief under the Florida Existing Building Code section 505.3 if the replacement is the manufacturer's largest standard size that fits the existing opening. Section 702.4 can require window fall prevention devices meeting ASTM F2090 when certain operable windows are replaced in dwellings, depending on sill height. These details are easy to miss in a high-rise and are worth a line in the specification.
What is the 2026 threshold-building inspection rule for windows and doors?
This is the biggest recent change for Florida condo window projects. Miami-Dade County's permitting page reports that, based on a binding interpretation of Florida Building Code (8th Edition, 2023) section 110.8.1 issued by the Building Officials Association of Florida and ratified by the Florida Building Commission on January 26, 2026, all installation of windows and doors in threshold buildings requires a threshold inspection by a State of Florida certified Special Inspector, in addition to a special inspection plan from the engineer of record. Miami-Dade describes these requirements as active throughout Florida.
Is my building a threshold building?
Florida section 553.71 defines a threshold building as any building greater than three stories or 50 feet in height, or an assembly occupancy over 5,000 square feet with an occupant content of more than 500 persons. Nearly every mid-rise and high-rise condominium qualifies.
What Miami-Dade now asks for on threshold window and door permits
- Building data showing whether the building is a threshold building (FBC 107.2.1).
- The location of the units where windows or doors are being installed.
- Wind calculations for all openings in the new installation (FBC 107.3.5, section 1620 and ASCE 7-22 Chapter 30).
- Wood buck calculations when buck thickness is 1-1/2 inches or more (FBC 1710).
- A Threshold Building Affidavit (FBC 110.8.1).
- A Special Inspector form from a state-certified special inspector covering window and door installation, including bucks and fasteners.
- A threshold inspection plan from the design professional of record outlining scope and verification procedures.
The affidavit and special inspector form must be signed and sealed by a professional engineer or registered architect certified as a special inspector of threshold buildings. Other permit documents may be sealed by a licensed engineer or architect without that certification.
Who pays for the special inspector
Under section 553.79(5), the fee owner of a threshold building selects and pays the special inspector, but the inspector is responsible to the enforcement agency, not to the owner or contractor. The inspector must be a Florida-licensed engineer or architect, and the architect or engineer of record may serve if listed by the licensing board as qualified. Section 553.79 also bars virtual inspections for structural inspections on threshold buildings.
What this means for individual owners
The rule is not limited to building-wide projects. A single owner replacing a slider on the 14th floor of a threshold building now needs this documentation too, which adds engineering and inspection steps. That is one more reason many boards prefer one coordinated project. Check with your local building department, because counties and cities may phrase their checklists differently; the Miami-Dade list above is one jurisdiction's implementation. For permit basics elsewhere in Florida, see hurricane window permits in Florida.
Which products and approvals should the specification require?
Florida section 553.842 requires statewide product approval for windows, exterior doors, skylights, shutters and impact protective systems, and bars advertising or selling a product as hurricane or wind-borne debris protection unless it is approved under that law. In practice your specification should require, for every window, door, mullion and any shutter:
- A current Florida product approval (FL number) or a current Miami-Dade Notice of Acceptance (NOA). Miami-Dade accepts both for window, door and garage door permits.
- For HVHZ buildings, an approval valid for the HVHZ. Miami-Dade's product control database separates "High velocity hurricane zone" and "Non-High velocity hurricane zone" approvals.
- Design pressures at or above each opening's calculated requirement, at the size being installed. An approval rated for a smaller tested size does not automatically cover a larger opening.
- The impact rating that matches the opening's height (large missile within 30 feet of grade, small missile above, unless the engineer specifies large missile throughout).
- Water resistance suitable for exposure. Ask the engineer what water test pressure the specification should require for upper floors.
- Installation per the approval's anchoring drawings for the actual substrate.
Miami-Dade's product approval office reports reviewing about 1,250 applications a year and conducting more than 850 quality assurance audits of manufacturers, fabricators and labs each year, and first-time approvals are valid for five years. Approvals expire and get revised, so the engineer should confirm the approvals are current at bid time and again at permit time.
Avoid letting the specification name a single brand as the only acceptable product unless there is a real technical reason. A performance specification (ratings, approvals, finish, glass, hardware, sightlines) lets several qualified manufacturers bid. This guide does not recommend manufacturers or contractors.
What contractor license is needed for a high-rise window project in Florida?
Licensing limits are tied to building height and type, and they catch many bidders. Florida section 489.105 and the Construction Industry Licensing Board's rules draw the lines:
| License | What it allows for condo windows | Source |
|---|---|---|
| General contractor | Unlimited as to type of work; can contract and perform any work requiring licensure under part I of chapter 489, except as otherwise provided in s. 489.113 | s. 489.105(3)(a) |
| Building contractor | New construction of commercial and residential buildings up to three stories, or remodeling, repair or improvement of any size building if the work does not affect structural members | s. 489.105(3)(b) |
| Residential contractor | One-, two- or three-family homes up to two habitable stories above one uninhabitable story; not condo towers | s. 489.105(3)(c) |
| Specialty structure contractor | Windstorm protective devices (except impact-resistant glazing) with no height limit; certified window and door assemblies only in Group R buildings up to three stories or 30 feet | Rule 61G4-15.015 |
| Division I contractor subcontracting to a specialty structure contractor | Division I contractors (general, building, residential) may subcontract window and door assembly installation in Group R buildings of any height to specialty structure contractors | Rule 61G4-15.015 |
Practical meaning: a specialty structure contractor can install shutters on a high-rise, but cannot be the contractor for impact windows on a 12-story condo unless working as a subcontractor to a Division I contractor. Work that alters structural integrity, such as lintels or load-bearing walls, is outside the specialty structure scope entirely. If the project includes enlarging openings or concrete repair, the engineer and the attorney should confirm the license needed for that part.
Verify every bidder's license on the Florida Department of Business and Professional Regulation (DBPR) license search at myfloridalicense.com, and check any county requirements. For the full licensing picture, see Florida licensing for window and shutter installers.
How should a condo association bid and select a window contractor?
The legal bidding rule in Florida
Florida section 718.3026 requires association contracts for materials, equipment or services to be in writing when the statute applies, and requires competitive bids when a contract requires payment that in the aggregate exceeds 5 percent of the association's total annual budget, including reserves. The association is not required to accept the lowest bid. Contracts for engineering, architect and attorney services are exempt from that bidding requirement, as are employees and a few other categories, and nothing in the section limits the association's ability to get needed products and services in an emergency. Associations with 10 or fewer units may opt out with a two-thirds owner vote. Section 718.113(5)(a) makes hurricane protection installations expressly subject to 718.3026.
A building-wide window project almost always exceeds the 5 percent line, so competitive bids are required.
A sound selection process
- Hire the design professional first. Engineering is exempt from the bidding requirement, so the board can choose an engineer or architect based on qualifications. That professional prepares the specification, window schedule, wind calculations and threshold inspection plan.
- Issue one bid package. Every bidder should price the same drawings, schedule, quantities, products criteria, testing and phasing. Different scopes cannot be compared.
- Prequalify. Ask for the license number, insurance certificates, references for buildings of similar height, a safety program for work at height, and proof of experience with threshold inspections.
- Hold a pre-bid walk. Let bidders see representative units, sliders, wood bucks and concrete conditions so they do not pad prices for unknowns.
- Level the bids. Put the bids side by side line by line (see the table below) before anyone looks at the total.
- Collect conflict disclosures. Ask each bidder in writing about any interest in the SIRS firm or relationship to anyone with such an interest, as section 718.112(2)(g) requires.
- Have the attorney review the contract. Payment terms, retainage, schedule, insurance, indemnity, warranties, unit access obligations and dispute resolution belong in the contract, not in a sales proposal.
| Bid item to compare | What to look for |
|---|---|
| Product per opening type | FL or NOA number, HVHZ approval if needed, DP at the installed size, impact rating by floor |
| Glass | Glass make-up from the approval's glass schedule, tint, low-E coating if specified |
| Removal and disposal | Old windows, shutters and debris; protection of balconies and landscaping below |
| Opening repairs | Unit prices for buck replacement, concrete patching and sill repair, since quantities are often unknown until removal |
| Interior protection and restoration | Dust barriers, floor protection, drywall and paint touch-up at returns, reinstalling window treatments |
| Access equipment | Swing stages, mast climbers, cranes or interior installation, with permits for any right-of-way use |
| Testing | Number and type of field water and air tests and who pays for retests |
| Engineering and special inspection support | Shop drawings, anchor calculations and coordination with the threshold inspector |
| Schedule | Units per week per elevation, and the plan for hurricane season |
| Warranty | Manufacturer product warranty and contractor workmanship warranty, kept separate |
For general quote-comparison advice that also applies to individual owners, see choosing a contractor and comparing quotes and contracts and cancellation rights.
How long does a high-rise window replacement take, and how is it scheduled?
There is no reliable statewide figure for how long these projects take, and any number quoted without your building's details is a guess. Duration depends on the number of openings, product lead times, permit review, the threshold inspection plan, access equipment, concrete repairs found after removal, and whether the work stops for hurricane season or storms. Ask each bidder and the engineer for a written schedule with these phases:
- Investigation and design: surveys of existing conditions, sample removals, wind calculations, specification.
- Owner approvals and notices: the owner vote if required, the recorded certificate, budget or assessment steps.
- Bidding and contract.
- Submittals and permits: shop drawings, product approvals, threshold documents, permit issuance.
- Manufacturing: windows are usually custom sized, so ordering starts after field measurements.
- Mock-up: installing and testing a few openings first, so problems are found before production.
- Production installation: usually by vertical stack or elevation, a few units at a time.
- Testing, inspections and closeout: field tests, special inspector reports, final inspections, punch list, warranties.
Hurricane season
The Atlantic hurricane season runs June 1 to November 30, with the peak from mid-August to late October, according to the Florida Climate Center. A project in progress during a storm watch has openings out, materials on balconies and equipment on the roof. The contract should require a written storm plan: how quickly open units are closed or temporarily protected, how swing stages and materials are secured or removed, and who decides to stop work. Some boards schedule the most exposed elevations outside peak season. For more, see lead times and hurricane season.
Typical owner notice cycle
Owners usually get a project-level notice, then an elevation or stack schedule, then a unit-specific notice a short time before their unit is done. Ask the board to adopt the notice timeline in writing and include it in the contract so the contractor is bound by it.
Do unit owners have to give access, and how should they prepare?
Florida: section 718.111(5)(a) gives the association an irrevocable right of access to each unit during reasonable hours when necessary for the maintenance, repair or replacement of any common elements or any part of a unit the association maintains under the declaration, or as necessary to prevent damage to the common elements or a unit.
Texas: section 82.107(a) requires each unit owner to give the association and other owners, and their agents, access through the owner's unit reasonably necessary for maintenance, repair and replacement. If damage is caused to the common elements or a unit through which access is taken, the owner responsible for the damage, or the association if it is responsible, is liable for prompt repair.
So owners generally cannot refuse access for a properly authorized project, but "reasonable hours" and reasonable notice still apply, and the board should not use access as a reason to skip clear scheduling.
Owner preparation checklist
- Photograph and video every window wall, sill, floor and ceiling near each opening before work starts. Date the files.
- Remove or let the contractor remove window treatments, as the notice says. Window treatments are usually the owner's responsibility for insurance in Florida (see below).
- Move furniture, art and electronics at least the distance the notice requests from each opening.
- Tell the association about alarm sensors on windows, smart shades, built-ins or stone sills that need special handling.
- Arrange access for tenants. In Florida and Texas, tenants occupy the unit, but the owner usually remains responsible to the association under the documents.
- Ask who will be in the unit, for how long, whether it will be secured when the opening is out, and how to report damage.
- Keep the temporary product labels on new windows until the final inspection.
Who pays for interior damage, finishes and removing hurricane protection during the project?
Removing and reinstalling hurricane protection in Florida
Section 718.113(5)(d) says that, unless the declaration says otherwise, a unit owner is not responsible for the cost of removing or reinstalling hurricane protection, including exterior windows, doors or other apertures, if removal is needed for the maintenance, repair or replacement of other condominium or association property the association is responsible for. Chapter 2025-175 (HB 913), effective July 1, 2025, rewrote this part:
- If the declaration does not say who pays, the board decides whether the owner or the association does the removal or reinstallation.
- If the association does it, it may not charge the owner.
- If the owner does it, the association must reimburse the owner or credit future assessments in the amount of the owner's cost.
- The law deleted the association's former authority to collect such charges as assessments, so older articles describing that are outdated.
This rule commonly applies when concrete restoration requires removing an owner's shutters or windows. It is not a general rule that the association pays for every new window; that depends on who is responsible for the windows themselves.
Interior finishes
Replacing a window often disturbs the drywall return, sill, paint and sometimes flooring next to the opening. Neither Florida nor Texas statute sets a one-size answer. The contract should say what the contractor restores (for example, drywall returns patched and painted to match, sills replaced in kind) and what is excluded (for example, custom stone, wallpaper, built-in cabinetry). Ask for these points in the bid package so every bidder prices the same restoration.
Damage by the contractor
Damage the contractor causes should be its responsibility under the contract and its insurance. That is why the pre-work photos matter. In Texas, section 82.107(a) places prompt repair of damage from access on whoever is responsible for it. In Florida, follow the contract's claims process and report damage in writing promptly.
Insurance lines to know
In Florida, section 718.111(11) says the association's property policy must exclude personal property within the unit and certain unit items, including floor, wall and ceiling coverings, electrical fixtures, appliances, built-in cabinets and countertops, and window treatments (curtains, drapes, blinds and hardware) located within the unit and serving only that unit; those are the owner's responsibility to insure. In Texas, section 82.111 requires the association to carry property insurance on the insurable common elements and, for units with horizontal boundaries, the units, though not improvements and betterments installed by owners, to the extent reasonably available. Ask your own agent whether your unit owner's policy covers damage during a construction project.
What about balcony doors, sliders and railings?
In most condo towers, the sliding glass doors to balconies are the biggest and most exposed openings, and they often leak first. Under FBC 1709.5.1, exterior windows and sliding doors must be tested and labeled to AAMA/WDMA/CSA 101/I.S.2/A440 or TAS 202, and in the HVHZ they must comply with TAS 202 and ASTM E1300 or section 2404. In wind-borne debris regions they also need impact resistance or approved protection. For product details, see impact sliding glass doors.
What to check in the specification
- Design pressure and water resistance. Sliders on high floors face high positive and negative pressures and wind-driven rain. Sill height and the threshold design affect water performance.
- Sill and balcony slab conditions. Many balconies slope poorly or have deteriorated concrete at the door track. If the milestone or SIRS work includes balcony repairs, coordinate them with the door replacement.
- Accessibility and threshold height. A taller sill can improve water resistance but can create a trip hazard. The engineer and architect should balance both.
- Screens and hardware. Confirm whether screens, locks and handles are included and match the specification.
Railings
Balcony railings are not opening protection, but they are often replaced or removed during the same work. Railings are structural guards with their own load requirements and, on a threshold building, their own inspection needs. If the railing must come off to replace the doors, the bid should say who removes and reinstalls it, how the balcony is made safe while it is off, and who certifies it afterward.
Enclosed balconies
FBC 1609.1.2 says openings in sunrooms, balconies or enclosed porches built under existing roofs or decks need not be protected if a wall with all protected openings separates the space from the interior. Some boards use this when owners have glass balcony enclosures, but the engineer must confirm it applies, and the HVHZ has its own rules.
What field testing should be done on new condo windows?
Product approvals are based on lab tests of sample units. Field testing checks whether the windows as actually installed in your building keep out air and water. It is one of the best protections an association has against leaks that show up months after the contractor leaves.
AAMA 502 and AAMA 503
- AAMA 502 (Field Testing of Newly Installed Fenestration Products) is applicable to newly installed windows and doors. It sets requirements for test specimens, apparatus and sampling, and verifies air infiltration performance using ASTM E783 and water penetration performance using ASTM E1105, according to a summary of the AAMA 502-12 standard published by the testing firm Intertek. ASTM E1105 can be run as Procedure A (uniform static pressure while water is sprayed) or Procedure B (cyclic pressure).
- AAMA 503 covers air leakage and water penetration testing of newly installed storefronts, curtain walls and sloped glazing systems. A building-enclosure consulting firm describes it as specifically for newly installed systems and points to AAMA 501.2 for checking existing storefronts and curtain walls.
Most condo towers with punched windows and sliders use AAMA 502. Buildings with window walls or curtain walls may use AAMA 503. These standards are published by the Fenestration and Glazing Industry Alliance; buy or reference the current edition in the specification rather than relying on summaries.
How to put field testing in the contract
- Require a mock-up installation of each opening type, tested before production begins.
- Specify the standard, the number of specimens per elevation or per number of units, the test pressures and the pass criteria, as set by the design professional.
- Require an independent testing agency hired by the association, not by the contractor.
- State who pays for retests after a failure (usually the contractor) and that failed installation patterns must be corrected across all similar units.
- Time tests while interior finishes are still open enough to see and fix leaks.
Field testing is separate from the threshold special inspection, which focuses on installation per the approved documents, including bucks and fasteners. You want both.
How do condo associations pay for a window project, and what notices are required?
This section covers the governance rules that protect owners when an association funds a project from its own budget, reserves or assessments.
- Reserves. If the association is responsible for windows and must have a SIRS, its budget must reserve for windows and exterior doors based on the most recent study, and for budgets adopted on or after December 31, 2024, owners generally cannot vote to waive or reduce those reserves (section 718.112(2)(f)).
- Special assessments: meeting notice. Under section 718.112(2)(c), written notice of a board meeting at which a nonemergency special assessment will be considered must be mailed, delivered or electronically transmitted to owners and posted conspicuously on the property at least 14 days before the meeting.
- Special assessments: purpose. Section 718.116(10) requires the specific purpose of any special assessment to be stated in a written notice to each owner, and the money may be used only for that purpose. Excess funds after completion are common surplus that the board may return to owners or credit toward future assessments.
- Owner-paid windows. If the declaration makes owners responsible for their own windows, the board may require installation by a date under 718.113(5)(a), and owners pay their own contracts, but the work still has to meet the board's specifications.
For grant programs: Florida's My Safe Florida Home program is limited by statute to single-family homes on their own parcel (detached, or attached up to three stories) with a homestead exemption, so condo units in mid-rise and high-rise buildings generally do not qualify. See My Safe Florida Home for windows and doors for the details and the program's 2026 status.
What happens if a hurricane damages windows before or during the project?
Florida section 718.1265 gives condo boards emergency powers when a state of emergency is declared for the area, unless the declaration, articles or bylaws specifically prohibit them. Relevant to windows, the board may:
- Implement a disaster or emergency plan before, during or after the event, including shutting down elevators, electricity, water or other systems.
- Based on advice of officials or licensed professionals, decide whether parts of the property can be safely occupied.
- Act to mitigate further damage, including contracting for debris removal and removing wet drywall, insulation, carpet and similar items to prevent mold, even if the owner would normally be responsible for those items.
- Contract, on behalf of owners, for items or services that owners are individually responsible for but that are needed to prevent further damage, with the statute naming "the boarding of broken windows or doors" as an example. Owners must reimburse the association's actual costs, and the association may use its lien rights to collect.
- Levy special assessments without an owner vote, regardless of contrary provisions in the documents.
After a storm, a board under pressure may be tempted to sign a fast replacement deal. The emergency exception to competitive bidding in 718.3026 covers needed products and services in an emergency, but a full building-wide replacement is usually a planned project that should go back through the engineer and the normal process once the building is safe. For claim handling, see hurricane damage to windows: claims and repairs, and watch for the warning signs in hurricane window scams and storm chasers.
How do window projects work in Texas coastal condominiums?
Texas has no SIRS or milestone inspection statute like Florida's, but coastal condos in Galveston, Corpus Christi, Port Aransas and South Padre Island face their own rules through the Texas Department of Insurance (TDI) windstorm program and the Texas Windstorm Insurance Association (TWIA).
Windstorm certification
- TDI's windstorm program covers the designated catastrophe areas: Aransas, Brazoria, Calhoun, Cameron, Chambers, Galveston, Jefferson, Kenedy, Kleberg, Matagorda, Nueces, Refugio, San Patricio and Willacy counties, plus parts of Harris County east of State Highway 146 in listed cities.
- TWIA lists windows, entry doors and garage doors among improvements that need a Certificate of Compliance for TWIA coverage. Texas Insurance Code section 2210.2515(b) requires written notice to TDI, on its form, before starting work on a structure for which TWIA coverage is sought.
- Starting April 1, 2026, Certificate of Compliance applications (WPI-1) must be certified to the 2024 International Residential Code or 2024 International Building Code. TDI says most catastrophe areas are now inside the windborne debris region under the 2024 codes, and a condo tower will typically follow the IBC.
- Only TDI appointed qualified inspectors can inspect ongoing construction; any Texas-licensed professional engineer can inspect completed construction for a WPI-8-E. TDI says post-construction inspections can be more invasive and more expensive, so schedule inspections during the work.
- TDI inspectors do not charge an inspection fee and aim to inspect within 48 hours of the requested date, excluding weekends and holidays; the windstorm field offices are reached at 800-248-6032, option 4.
- TDI may not rescind a certificate once issued (2210.2515(k)), and TDI advises not making final payment until the work is finished and the certificate is issued.
Association law
For post-1994 Texas condos, section 82.107(c) makes owners responsible for the cost of windows and doors serving only their unit unless the declaration says otherwise, and 82.102 gives the association power, through its board, to regulate the use, maintenance, repair, replacement, modification and appearance of the condominium. Association meetings must be held at least once a year, and board meetings must be open to owners, with limited closed sessions (82.108). A board that wants a uniform building-wide project in Texas therefore often needs either a declaration amendment, owner agreement or a cost allocation the attorney is comfortable with.
Houston and inland towers
Houston high-rises outside the catastrophe areas are not in the TDI windstorm program, but they still face high winds. NOAA's National Centers for Environmental Information reported that a May 2024 derecho, with winds at times above 100 mph, blew out numerous windows in downtown Houston skyscrapers. City building codes and the engineer of record govern those projects. See Texas coastal building codes for windows and TWIA windstorm certification for windows.
Shutters or impact windows: what should a condo board choose?
Florida's condo statute leaves the choice of hurricane protection to the board's specifications, as long as they comply with the building code. Boards usually weigh these factors:
| Factor | Impact windows and doors | Shutters over existing windows |
|---|---|---|
| Storm-day work | None; always in place | Must be closed; the board may close them without owner permission only if needed to protect property (718.113(5)(b)) |
| Fixes leaks and old frames | Yes, replaces the whole unit | No; old windows remain |
| Height and access | Installed once from interior or swing stage | Permanent shutters on high floors must be reachable for operation and maintenance |
| Appearance | Uniform if specified | Unified building scheme can be required (718.113(5)(c)) |
| Permits in Miami-Dade | Window permit; threshold documents in threshold buildings | Shutter permit; zoning review required for permanent storm shutters on commercial buildings, including condominiums and apartment buildings |
| Labeling | Permanent and temporary labels on each unit (FBC 1709.5.1) | Permanent label on each shutter in set locations (FBC 1709.9) |
Many boards choose impact windows and doors because they replace aging units and need no action on storm day, while others add or keep shutters where windows are still within useful life. Price comparisons should come from bids on your building, not online averages. See impact windows vs. hurricane shutters and types of hurricane shutters.
A step-by-step roadmap for a condo window replacement project
- Read the documents. Have the association attorney confirm who is responsible for windows and doors under the declaration, and whether an owner vote is needed under 718.113(5)(a) or the Texas documents.
- Pull the data. Gather the SIRS line items for windows and exterior doors, milestone reports, leak logs, past permits and any owner-installed product approvals.
- Engage the design professional. Select the engineer or architect, who investigates conditions, makes sample removals and prepares wind calculations, specifications and the threshold inspection plan.
- Adopt or update hurricane protection specifications. Florida boards must have them for each building under 718.113(5).
- Hold owner meetings. Explain the reason, scope, schedule, access needs and cost allocation. Give the required 14-day notice for any meeting on a nonemergency special assessment.
- Vote and record if required. Record the certificate and send it to owners.
- Bid competitively. Follow 718.3026, prequalify bidders, collect conflict disclosures and level the bids.
- Sign a lawyer-reviewed contract with schedule, storm plan, testing, restoration scope, insurance and warranties.
- Permit. Submit product approvals, window schedule, wind calculations, wood buck calculations and threshold forms; in Texas, file the WPI-1 before work begins.
- Mock-up and test each opening type before production.
- Install by stack or elevation with unit notices, pre-work photos and daily cleanup.
- Inspect and test continuously: special inspector, building department, field tests, TDI or engineer inspections in Texas.
- Close out: final inspections, WPI-8 or WPI-8-E in Texas, warranties, as-built product approval list per unit, and owner handbooks for operation and care.
- Update the SIRS and reserves to reflect the new windows' useful life.
Common mistakes that cost condo associations time and money
- Letting a contractor write the specification. The scope then fits that bidder's product and pricing, and other bids cannot be compared.
- Ignoring the 2026 threshold inspection rule. Missing special inspector forms or wood buck calculations can stall permits.
- Using a license that does not fit the building. A specialty structure contractor cannot hold the prime contract for impact windows in a Group R building over three stories or 30 feet.
- No unit prices for hidden conditions. Rotted bucks and spalled concrete are common; without unit prices, every discovery becomes a negotiation.
- Skipping field testing. Leaks that appear after the warranty dispute starts are hard to prove without baseline test results.
- Forgetting owners who already upgraded. The 718.113(5)(a) limit on requiring the same type of protection again can upend a cost allocation late in the process.
- No hurricane season plan. Open units and loose equipment are serious hazards in a storm.
- Poor records. Keep, for each unit, the product approval numbers, permit numbers and inspection results. Owners will need them for insurance and resale, and the association will need them for the next SIRS.
How to choose a provider
- Read the declaration's unit boundary and maintenance clauses for windows and doors.
- Get the SIRS line item for windows and exterior doors: remaining useful life and replacement cost.
- Collect milestone inspection summaries and any concrete repair program.
- Hire the engineer or architect before bidding construction.
- Adopt or update the board's hurricane protection specifications for each building.
- Confirm whether an owner vote and recorded certificate are required.
- Identify units with existing code-compliant impact protection and document their approvals.
- Bid on one specification, prequalify licenses and insurance, and collect SIRS conflict disclosures.
- Include threshold inspection, wood buck calculations and field testing in the scope.
- Write a hurricane season storm plan into the contract.
- Send owners a written access and notice schedule; ask owners to photograph their units.
- Keep a per-unit record of product approvals, permits and inspections for closeout.
- In Texas coastal counties, file the WPI-1 before work and schedule TDI or appointed inspections during work.
Related hurricane shutters and impact windows guides
- Who Pays for Condo Hurricane Shutters and Impact Windows in Florida, and What Can the Board Require?
- Do You Need a Permit for Impact Windows, Doors and Shutters in Florida? Process, Documents, Fees and Inspections
- Design Pressure (DP) Ratings Explained: What Do DP50 and +60/-70 psf Mean for Your Windows?
- Missile Impact Tests Explained: What Are the Large and Small Missile Tests, ASTM E1996/E1886 and TAS 201/202/203?
- Impact Sliding Glass Doors: Why Do They Leak in Hurricanes, What Design Pressure Do You Need, and What Do They Cost?
- Who Can Install Impact Windows and Hurricane Shutters in Florida? Contractor Licensing Under Chapter 489
- How Do You Compare Impact Window and Shutter Quotes? 20 Questions to Ask Before You Sign
- Do You Need a Texas Windstorm Certificate (WPI-8) for New Windows, Doors or Shutters?
Hurricane shutters and impact windows by state and city
Questions people ask
Can my Florida condo board force me to replace my windows?
It depends on the declaration and the condition of your windows. Under section 718.113(5)(a), the board may, with a majority vote of the voting interests where required, install hurricane protection or require owners to install it. No vote is needed if the declaration already assigns windows or hurricane protection to the association or requires owners to install it. But if you already installed protection that meets current code, the board cannot require the same type again unless it has reached the end of its useful life or is needed to prevent damage.
Are windows part of the Florida SIRS?
Yes. Section 718.112(2)(g) lists windows and exterior doors among the minimum items a structural integrity reserve study must cover for condo buildings three habitable stories or higher. The study must state each item's estimated remaining useful life and replacement cost and provide a reserve funding plan. For budgets adopted on or after December 31, 2024, owners of associations that must have a SIRS generally cannot vote to waive or reduce reserves for those items.
Does a milestone inspection check whether my windows meet code?
No. Section 553.899 says the milestone inspection is a structural inspection of load-bearing elements and primary structural systems, and its purpose is not to determine compliance with the Florida Building Code. It can still affect window work if it finds deterioration around openings that requires removing windows or doors to repair concrete. Code compliance for new windows is checked through the permit, the building department and, in threshold buildings, the special inspector.
What changed for condo window permits in 2026?
Miami-Dade reports that a binding interpretation of Florida Building Code section 110.8.1, ratified by the Florida Building Commission on January 26, 2026, requires all window and door installations in threshold buildings to receive a threshold inspection by a state-certified special inspector plus a special inspection plan from the engineer of record. Threshold buildings include any building over three stories or 50 feet tall. Expect wind calculations, wood buck calculations and sealed forms with the permit.
Who pays if the association must remove my shutters or windows for its own repairs?
In Florida, unless the declaration says otherwise, section 718.113(5)(d) says the owner does not pay to remove or reinstall hurricane protection, including exterior windows and doors, when removal is needed for association-responsibility work. Since July 1, 2025, if the declaration is silent the board decides who does the work; if the association does it, it cannot charge you, and if you do it, the association must reimburse you or credit your future assessments.
Do I have to let the contractor into my unit?
Generally yes, with reasonable notice and at reasonable hours. Florida section 718.111(5) gives the association an irrevocable right of access to units when necessary for maintenance, repair or replacement of common elements or association-maintained parts of a unit. Texas section 82.107(a) requires owners to give access reasonably necessary for maintenance, repair and replacement. Ask the board for the schedule in writing and photograph your unit before work starts.
Do upper floors need large missile impact windows?
Not always. Under the Florida Building Code, glazed openings within 30 feet of grade must pass the large missile test and those higher than 30 feet must pass the small missile test; the HVHZ uses the same 30-foot line with TAS 201 and 203. Outside the HVHZ, glazing more than 60 feet up and more than 30 feet above any gravel roof within 1,500 feet may be unprotected in some cases. The engineer of record decides for your building.
What license does a contractor need to replace windows in a Florida condo tower?
A general contractor's license is unlimited in scope. A building contractor can do remodeling, repair or improvement on any size building if the work does not affect structural members. A specialty structure contractor can install certified window and door assemblies only in Group R buildings up to three stories or 30 feet, unless working as a subcontractor to a Division I contractor, which rule 61G4-15.015 allows for Group R buildings of any height. Verify licenses at myfloridalicense.com.
Does the association have to take the lowest bid?
No. Florida section 718.3026 requires competitive bids for contracts that exceed 5 percent of the association's total annual budget, including reserves, but says the association is not required to accept the lowest bid. Engineering and architect services are exempt from the bidding requirement, so boards often hire the design professional first and then bid the construction work on a single specification.
What is AAMA 502 field testing?
AAMA 502 is a field test method for newly installed windows and doors. It checks air infiltration using ASTM E783 and water penetration using ASTM E1105, on a sample of installed units, using a test chamber and a calibrated spray rack. Storefronts, curtain walls and sloped glazing use the related AAMA 503 standard. The engineer sets the number of specimens, pressures and pass criteria in the specification.
Do Texas condo owners pay for their own windows?
For Texas condominiums whose declarations were recorded on or after January 1, 1994, Property Code section 82.107(c) says each owner is responsible for the cost of maintaining, repairing and replacing windows and doors serving only that owner's unit, unless the declaration says otherwise. Older condos may follow different rules. In TDI's coastal catastrophe areas, replacement windows also need windstorm inspection and a Certificate of Compliance to stay eligible for TWIA coverage.
Can a condo unit get a My Safe Florida Home grant for impact windows?
Usually not in a mid-rise or high-rise. Section 215.5586 limits program inspections to site-built, owner-occupied, homesteaded single-family units on their own parcel, either detached or attached and no more than three stories. The program also changed in 2026 and its applicant portal was offline in November 2026 for a platform move, so check the program site before planning around it.
Sources
- Florida Statutes s. 718.113, Maintenance; limitation upon improvement; hurricane protection
- Florida Statutes (2026) s. 718.112, Bylaws (SIRS, budgets, reserves, milestone duties)
- Florida Statutes (2026) s. 718.111, The association (access, insurance)
- Florida Statutes (2026) s. 718.3026, Contracts for products and services; bids
- Florida Statutes (2026) s. 718.116, Assessments
- Florida Statutes (2026) s. 718.1265, Association emergency powers
- Florida Statutes (2026) s. 718.103, Definitions
- Florida Statutes (2026) s. 553.899, Mandatory structural inspections for condominium and cooperative buildings
- Florida Statutes (2026) s. 553.71, Definitions (threshold building)
- Florida Statutes (2026) s. 553.79, Permits; special inspectors
- Laws of Florida ch. 2025-175 (HB 913)
- Miami-Dade County: Windows, Shutters, Doors and Security Bars permit checklists
- Miami-Dade County: Product Approval
- Miami-Dade County: Product Control Search
- Florida Building Code, Building, 8th Ed. (2023), Chapter 16 Structural Design (UpCodes)
- Florida Building Code, Building, 8th Ed. (2023), Chapter 17 Special Inspections and Tests (UpCodes)
- Florida Building Code, Existing Building, 8th Ed. (2023), Chapter 7 Alterations Level 1 (UpCodes)
- Florida Building Code, Existing Building, 8th Ed. (2023), Chapter 5 Prescriptive Compliance (UpCodes)
- Florida Statutes s. 553.842, Product evaluation and approval
- Florida Statutes s. 489.105, Definitions (contractor categories)
- Florida Administrative Code rule 61G4-15.015, Specialty Structure Contractors
- Florida Statutes s. 215.5586, My Safe Florida Home Program
- Texas Property Code ch. 82, Uniform Condominium Act
- Texas Insurance Code ch. 2210, Texas Windstorm Insurance Association
- TDI: Windstorm adopted building codes
- TDI: Windstorm general questions (catastrophe areas)
- TDI: Windstorm inspection process
- TDI: Completed construction certificates
- TDI: Making repairs after a storm
- TWIA: Windstorm certification
- Intertek: AAMA 502-12 Field Testing of Newly Installed Fenestration Products
- Cx Associates: AAMA 503 field testing of storefronts, curtain walls and sloped glazing
- Florida Climate Center (FSU): Hurricanes
- NOAA NCEI: Billion-Dollar Disasters, Texas summary
This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.