Local Guide · Hurricane shutters and impact windows

How Long Do Impact Windows Take, and When Is the Best Time to Buy?

Lead time is a chain of steps: association approval, permit, factory build, install and inspection. Here are the legal permit clocks in Florida and Texas, how hurricane season and price-gouging laws affect timing, and how to protect your home while you wait.

Plan for several months from first quote to final inspection, and aim to sign in late fall or winter so work is done before hurricane season starts June 1. Factory lead times vary by product and demand, so get them in writing. Permits run on legal clocks: Florida's 553.792 gives local governments 30 business days for most residential permits, and Texas cities have 45 days under Local Government Code 214.904. Use approved panels or code-compliant plywood while you wait.

Key facts

  • The Atlantic hurricane season runs June 1 to November 30, peaking mid-August to late October (Florida Climate Center, FSU).
  • Fla. Stat. 553.792 gives Florida local governments 30 business days to act on residential permits for structures under 7,500 sq ft, and 5 business days for listed permit types on existing single-family homes when work is under $15,000.
  • Florida permit fees drop 10 percent per business day when a local government misses the 553.792 deadline, with exceptions for written extensions, applicant delay and force majeure.
  • Texas Local Gov't Code 214.904 requires cities to act on building permits within 45 days or give written reasons, then decide within 30 more days or refund permit fees.
  • TDI windstorm inspectors charge no fee and aim to inspect within 48 hours of the requested date, excluding weekends and holidays.
  • Florida's price-gouging law (501.160) covers supplies, services, materials and lumber after an emergency declaration and lasts up to 60 days unless extended.
  • Texas DTPA 17.46(b)(27) bans exorbitant prices for building materials and construction tools during a designated disaster period, with Attorney General penalties up to $10,000 per violation.
  • Unlicensed contracting during a Governor-declared emergency is a third-degree felony in Florida (489.127).
  • A TWIA policy cannot be bought when a hurricane is in the Gulf, according to TDI.

How long does it take to get impact windows or hurricane shutters?

There is no single number, because the total time is a chain of separate steps, and each one has a different owner. The factory controls how long it takes to build the windows. Your city or county controls the permit. In some places a state agency controls an inspection. Your condo or HOA may control an approval before any of that starts. And the weather controls everything from June through November.

Manufacturers publish or quote factory lead times by product line, and those quotes change with demand. We do not publish week counts here because they shift month to month and we could not find a neutral, dated public source for them. Ask each bidder for the current factory lead time in writing, for your specific product line, sizes and color.

What we can tell you exactly is where the legal clocks are. Florida and Texas both set deadlines for how fast local governments must act on building permits, and Texas sets an inspection target for coastal windstorm work. Those are the pieces you can plan around with confidence.

StepWhat happensLegal clock, if anyWho controls it
1. Association approvalCondo or HOA reviews the product against its hurricane protection specificationsSet by your governing documents; Florida law bars denial of conforming protectionBoard or architectural committee
2. Measure and selectContractor measures, picks products whose approval covers each opening's size and design pressureNoneContractor and you
3. ContractYou sign; a cancellation window may apply3 business days for home solicitation sales in Florida and TexasYou
4. PermitContractor applies with product approvals and elevationsFlorida: Fla. Stat. 553.792; Texas cities: Local Gov't Code 214.904Building department
5. Order and manufactureCustom units are built to sizeNone; factory quoteManufacturer
6. InstallOld units removed, new ones anchored per approvalNoneContractor
7. InspectionsBuilding final; on the Texas coast, TDI windstorm inspection during constructionTDI aims to inspect within 48 hours of the requested dateBuilding department; TDI or appointed engineer
8. Insurance updateNew wind mitigation inspection (Florida) or WPI-8 certificate to TWIA (Texas)None set for homeownersInspector, insurer

The rest of this page walks through each clock, how hurricane season changes the picture, what happens to prices and lead times after a storm, and what you can use to protect your home while you wait. For the full installation sequence, see the impact window installation process.

How long do permits add? Florida's permit clock

Florida Statutes 553.792 sets deadlines for local governments to approve, approve with conditions, or deny a building permit after receiving a complete and sufficient application, unless you waive them in writing. A local government may not make you waive the deadlines as a condition of reviewing your application.

Permit type (s. 553.792(1)(a))Deadline
Listed permits (structural, accessory, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing or roofing) for an existing single-family home when the work is under $15,0005 business days
Residential permits for a structure under 7,500 square feet30 business days
Residential permits for a structure of 7,500 square feet or more60 business days
Signs or nonresidential buildings under 25,000 square feet60 business days
Multifamily residential up to 50 units60 business days

The statute does not name windows, doors or shutters as their own category. Ask your building department which category a window or shutter permit falls under; a small change-out on an existing home may qualify for a short review, while a whole-house project may be handled on the 30-business-day track.

Other parts of the Florida clock

  • Completeness notice. The local government must tell you in writing within 5 business days if your application is missing information. If it does not, the application is deemed complete.
  • Revisions. If the agency sends a timely written list of deficiencies, the applicant has 10 business days to submit revisions, and the agency then has 10 business days to approve or deny, unless you agree in writing to more time.
  • Fee reductions. If the local government misses the deadline, it must cut the permit fee by 10 percent for each business day it is late, with exceptions for written extensions, delays you caused, and force majeure or extraordinary circumstances. Missing the 10-day revision deadline means a 20 percent reduction per business day.

Some cities move faster than the statute requires. The City of Tampa lists shutters and awnings as a residential permit category, and some projects are eligible for its "Fast Pass-Same Day" application. Miami-Dade lets licensed contractors get residential accordion shutter and storm panel permits through its E-permitting system.

Larger buildings take longer. Since a binding interpretation ratified by the Florida Building Commission on January 26, 2026, window and door installations in threshold buildings (generally more than three stories or more than 50 feet tall) need a threshold inspection by a state-certified special inspector and a special inspection plan from the engineer of record. Build that engineering time into any condo or high-rise schedule. See high-rise condo window replacement projects and hurricane window permits in Florida.

How long do permits add on the Texas coast?

Texas has no statewide residential building code, so permits are issued by cities. Texas Local Government Code 214.904 sets a deadline for municipal building permits to erect or improve a building in the city or its extraterritorial jurisdiction:

  • By the 45th day after you apply, the city must grant or deny the permit, send written reasons why it has not been able to decide, or sign a written agreement with you setting a deadline.
  • If the city sends that notice, it must grant or deny within 30 days after you receive it.
  • If the city misses the deadline, it may not collect permit fees for the application and must refund any it already collected.

The second Texas clock is the windstorm inspection. In the 14 first-tier coastal counties and the part of Harris County east of State Highway 146, work you want insured by the Texas Windstorm Insurance Association (TWIA) needs a Certificate of Compliance. The owner or builder should file Form WPI-1 with the Texas Department of Insurance (TDI) before construction starts. TDI inspectors charge no inspection fee and try to inspect within 48 hours of the requested date, not counting weekends and holidays. TDI inspectors inspect during construction, not before or after, so the inspection has to be scheduled while the work is open.

If you miss that window, a Texas-licensed professional engineer can inspect after completion for a WPI-8-E certificate, but TDI says post-construction inspections can be more invasive and more expensive. Also note Texas Insurance Code 2210.2515(e): TDI may not issue a certificate for ongoing work if it has not received completed forms and full payment of inspection fees within six months after the final inspection. See TWIA windstorm certification for windows.

When is hurricane season, and when is the best time to buy?

The Atlantic hurricane season runs June 1 to November 30, with the peak from mid-August to late October, according to the Florida Climate Center at Florida State University. The center also notes that every part of Florida's coastline has been affected by at least one hurricane since 1850.

Working backward from that calendar gives the most common planning advice: get quotes and sign in the late fall or winter so the work is permitted, built and installed before June. That puts manufacturing and installation in the months when storms are least likely to interrupt crews or permit offices.

MonthsWhat to doWhy
December to FebruaryGet the free MSFH inspection if eligible (Florida), check condo or HOA specifications, collect at least three itemized quotesQuiet season; time for association approvals and comparisons
January to MarchSign the contract, submit the permit, file Form WPI-1 (Texas coast)Leaves room for permit review, revisions and the factory build
March to MayManufacturing and installation, inspectionsFinish before June 1
June to NovemberKeep temporary protection ready; schedule follow-up wind mitigation inspectionStorms can halt work; deploy protection when a watch is posted

Are there off-season deals? We found no neutral, dated public data showing that impact window or shutter prices reliably drop in winter. Some sellers run promotions; others do not. The real off-season advantage is time: more scheduling choice, less storm interruption and less risk that your project gets stuck behind post-storm repair work. Compare quotes on the same products and openings rather than chasing a seasonal discount. See choosing a contractor and comparing quotes.

If you plan to use a My Safe Florida Home grant, the program's timing matters more than the season. Grant recipients must finish construction and request a final inspection within 18 months of grant approval, and applications open in windows after each legislative appropriation. As of November 19, 2026, the program's applicant portal has been offline since November 10 for a move to a new platform. See My Safe Florida Home for windows and doors.

Can I get shutters or impact windows installed during hurricane season?

Yes. Nothing in Florida or Texas law stops installation during hurricane season, and many projects are installed in the summer. The risks are practical:

  • Storm interruptions. When a watch or warning goes up, crews stop new installs and switch to closing shutters and securing job sites. A hurricane watch means hurricane conditions (sustained winds of 74 mph or higher) are possible in your area; a warning means they are expected, according to the Federal Alliance for Safe Homes (FLASH).
  • Half-finished openings. Ask how the contractor will secure openings where the old window is out and the new one is not yet in if a storm approaches.
  • Post-storm backlogs. If a storm hits your area, permits, inspections and crews shift to repairs.

Shutters are usually the faster path in season because many shutter systems are simpler to build and install than a full window replacement. If time is short, some owners protect the house now with approved shutters or panels and replace windows later. See impact windows vs. hurricane shutters and types of hurricane shutters.

Insurance timing is a separate trap on the Texas coast: TDI says a TWIA policy cannot be bought when a hurricane is in the Gulf. If you are relying on new opening protection to qualify for TWIA coverage, get the certificate and the policy in place well before a storm forms.

Do prices rise after a hurricane? What price-gouging laws cover

Demand for windows, shutters, plywood and labor jumps after a storm, and some sellers raise prices. Both states have price-gouging laws that apply only after an official emergency or disaster declaration. They do not freeze prices; they ban unconscionable or exorbitant prices tied to the emergency.

Florida: Fla. Stat. 501.160

  • After the Governor declares a state of emergency, it is unlawful to sell or rent an essential commodity at an unconscionable price in the emergency area. The statute's definition of commodities includes supplies, services, materials and lumber needed because of the emergency.
  • A price is presumed unconscionable if it is a gross disparity from the average price in the 30 days before the declaration, or grossly exceeds the average in the trade area, unless the seller can explain it by added costs or national or international market trends.
  • The ban lasts up to 60 days under the initial declaration and can be extended by executive order.
  • It is enforced by the Department of Legal Affairs (the Attorney General) and state attorneys. It does not create a private cause of action, so you report it rather than sue under this section.
  • During a declared emergency, selling goods or services to the public without the required local business tax receipt is a second-degree misdemeanor.

Texas: DTPA 17.46(b)(27)

  • It is a deceptive trade practice to take advantage of a disaster declared by the Governor or the President by selling or demanding an exorbitant or excessive price for fuel, food, medicine, lodging, building materials, construction tools or another necessity.
  • It applies during a "designated disaster period" that runs from the disaster or declaration until the 30th day after the declaration ends.
  • In Attorney General actions, courts can award civil penalties of up to $10,000 per violation, plus up to $250,000 more if the practice targeted a consumer 65 or older.

A higher price after a storm is not automatically illegal. A contractor whose glass, aluminum or labor costs went up can pass those costs on. If you think a quote is gouging, save the written quote, ads and receipts and report it to the Florida Attorney General's office or the Texas Attorney General's Consumer Protection Division. See hurricane window scams and storm chasers and filing complaints against contractors.

Why do lead times get longer after a storm?

Every link in the chain gets busier at once. Damaged homes need emergency boarding, glass and doors. Owners who escaped damage decide not to wait for the next storm. Permit offices take on repair permits and may change procedures under emergency powers. Inspectors and contractors are stretched. And out-of-area crews arrive, some licensed and some not.

Local emergency rules can help or hurt timing. The City of Tampa's Post-Hurricane Permitting Guide (updated April 2026) says permit waivers apply only after a declared disaster and only after the Mayor exercises emergency powers under City Code Section 2-403. Even then, Tampa waives permits for size-for-size front or rear exterior door replacement, but always requires a permit for garage door replacement, with the fee waived during emergency powers.

Post-storm laws also protect you while you wait:

  • Florida: unlicensed contracting during a state of emergency declared by the Governor is a third-degree felony under Fla. Stat. 489.127. Check any contractor's license before signing.
  • Texas: Business and Commerce Code Chapter 58 requires written contracts for disaster remediation and bars the contractor from requiring payment before work begins. It does not apply to contractors that have kept a physical business address for at least a year in your county or an adjacent county. TDI warns that after a disaster it is illegal for out-of-town contractors to ask for a down payment before they start.

Note that Florida's storm-solicitation statute, 489.147, with its 10-day cancellation right after an emergency, is written for roof contracts. It does not expressly cover window or shutter contracts. See contracts and cancellation rights.

What temporary protection can I use while I wait?

If your windows or shutters will not be in before a storm, you need a plan for the gap. Options, from most to least durable:

1. Approved removable panels or fabric screens

These are often faster to get than a whole-house window order, and they become your permanent backup later. They need product approval, permanent anchors and in most places a permit. See hurricane panels and fabric hurricane screens.

2. Code-compliant plywood or OSB panels (Florida, outside the HVHZ)

The Florida Building Code allows wood structural panels at least 7/16 inch thick with a maximum 44-inch span between fastener lines as opening protection on Group R-3 or R-4 buildings (typical houses and townhomes) with a mean roof height of 33 feet or less, where the design wind speed is 180 mph or less. The panels must be precut to overlap the wall at least 2 inches beyond the fastener lines, predrilled, and attached with corrosion-resistant hardware permanently installed on the building. For wood-frame walls the anchors are sized on 1/4-inch lag screws with at least 300 pounds of design withdrawal capacity; masonry and concrete walls need anchors with at least 300 pounds withdrawal and 525 pounds shear capacity. This exception does not apply in the High-Velocity Hurricane Zone (Miami-Dade and Broward). See DIY plywood hurricane protection.

3. Plywood on the Texas coast

TDI lists properly installed plywood panels as an emergency measure. It says wood panel shutters may be possible depending on whether the panels can be properly secured and permanent fasteners installed into the wall framing.

4. Garage door protection

Do not forget the largest opening. IBHS (through its FORTIFIED program) says a garage door pushed in by wind lets pressure build inside the house, pushing up on the roof and out on the walls. Approved bracing systems can be a stopgap until a wind-rated door is installed. See garage door bracing and retrofits.

What does not work: taping windows, and decorative shutters. See window film and other myths.

For insurance, temporary measures count only if they meet a standard. On Florida's OIR-B1-1802 form, plywood or OSB meeting FBC 2007 Table 1609.1.2 rates as Level C, below tested shutters (Levels A and B). Undocumented systems are rated N.

Do custom sizes, colors and features extend lead time?

Often, yes, though the exact effect depends on the manufacturer. Things that commonly make an order slower or more complicated:

  • Non-standard sizes and shapes. Arched tops, very large sliders and oversized picture windows may need special glass or may fall outside a product approval's tested sizes, forcing a different product.
  • Higher design pressure. Openings near corners and on upper floors can need higher ratings. If a product line does not reach the required pressure at that size, you need a different series. See design pressure ratings explained.
  • HVHZ requirements. In Miami-Dade and Broward, every product must carry HVHZ-level approval and the permit must show positive and negative design pressures and the glass type from the approval's glass schedule. See HVHZ requirements.
  • Colors, frame finishes and specialty glass. Non-white frames, tinted, low-E or acoustic laminated glass and divided-lite grids are more likely to be built to order.
  • Historic or condo specifications. If a board requires a particular look, you may need a slower product line or a design review. See historic homes and condo hurricane protection rules.

Ask each bidder: Which items on my order are stock and which are custom? What is the current factory lead time for each? Do all units fit within the product approval's size and pressure limits?

Can I lock in a price before the lead time ends?

You can ask for it in the contract. Whether a price is fixed is a contract term, not a legal guarantee. Read for these clauses before you sign:

  • Price escalation clause. Some contracts let the seller raise the price if material costs rise before delivery. Ask whether the price is firm, and for how long.
  • Re-measure clause. A final measurement can change the price if openings differ from the estimate.
  • Delivery estimate vs. guarantee. Most contracts give an estimate, not a guaranteed date. Ask what happens if delivery slips past June 1.
  • Deposit and payment schedule. TDI advises coastal Texas owners not to make final payment until the work is done and TDI has issued the WPI-8. Texas Chapter 58 bars upfront payment demands from out-of-area disaster contractors.
  • Cancellation rights. If the sale was made at your home after a salesperson's visit, Florida (Fla. Stat. 501.025) and Texas (Bus. and Com. Code 601.051) both let you cancel until midnight of the third business day after signing. In Florida the contract must include a "BUYER'S RIGHT TO CANCEL" notice. Texas requires the cancellation notice in at least 10-point bold type next to your signature.
  • Permit responsibility. The contract should say the contractor pulls the permit and that you will receive the final inspection.

Before signing, check that the contractor is properly licensed. In Florida, installing windows and shutters is regulated under Chapter 489; see Florida licensing for window and shutter installers. Texas has no state license for this trade; see Texas contractor rules.

How condo and HOA approvals fit into the timeline

Association approval is often the first step, and it can be the longest if the board meets monthly.

  • Florida condos (Fla. Stat. 718.113(5)): every condo board must adopt hurricane protection specifications for each building. The board may not refuse a unit owner's installation that conforms to those specifications. If the association itself decides to install protection or require owners to install it, it needs a majority vote of voting interests, recorded in a certificate in the county public records stating the installation deadline. That deadline becomes your schedule.
  • Florida HOAs (Fla. Stat. 720.3035(6)): the board or architectural committee must adopt hurricane protection specifications and may not deny an application that conforms to them. Since July 1, 2026, under chapter 2026-63, an HOA may not require a government building permit before it reviews your application, so you can run the association review and the permit side by side.

Get the specifications first, pick a product that conforms, and submit early. See condo hurricane protection under 718.113 and HOA hurricane protection under 720.3035.

After install: updating your insurance

The project is not finished for insurance purposes until your insurer has proof. In Florida, Citizens Property Insurance says wind mitigation forms are usually valid for up to five years from the inspection date unless improvements call for a new form. If you add opening protection, the agent must submit documentation and photos (such as product NOA letters), and a new wind mitigation inspection may be required before the new discount applies. Schedule the inspection soon after final inspection so the discount starts at your next policy change or renewal.

On the Texas coast, send the WPI-8 to your TWIA agent. TDI says TWIA offers a discount for existing structures that retrofit openings with windborne-debris-resistant products, and owners can protect a few openings at a time, with an inspection each time and a final box checked when all openings are protected. See insurance discounts for impact windows and shutters.

How to choose a provider

  • Get condo or HOA hurricane protection specifications before collecting quotes.
  • Collect at least three itemized written bids in late fall or winter.
  • Ask each bidder for the current factory lead time for your exact products, in writing.
  • Confirm every opening fits the product approval's size and design pressure limits.
  • Read the contract for price escalation, delivery and re-measure clauses.
  • Make sure the contractor pulls the permit; note the statutory review deadline.
  • On the Texas coast, file WPI-1 before work starts and schedule the TDI inspection during construction.
  • Arrange temporary protection for any opening not finished by June 1.
  • Hold final payment until the final inspection passes (and the WPI-8 is issued in Texas).
  • Schedule a new wind mitigation inspection and send documents to your insurer.

Related hurricane shutters and impact windows guides

Hurricane shutters and impact windows by state and city

Questions people ask

What is the fastest way to protect my home if a storm is coming soon?

Use what is already approved and ready. If you have permanent anchors, install your stored panels or fabric screens. In most of Florida outside Miami-Dade and Broward, code-compliant 7/16-inch wood structural panels with permanent anchors are allowed on typical homes. On the Texas coast, TDI lists properly installed plywood as an emergency measure. Brace the garage door with an approved system. New custom windows will not arrive in time.

Does Florida law limit how long my city can take on a window permit?

Yes. Fla. Stat. 553.792 sets deadlines once a complete application is received, such as 30 business days for residential structures under 7,500 square feet and 5 business days for certain listed permits on existing single-family homes when the work is under $15,000. If the city misses the deadline, it must reduce the permit fee by 10 percent per business day late, with some exceptions.

How long does a Texas city have to issue a building permit?

Under Texas Local Government Code 214.904, a city must grant or deny a building permit, explain in writing why it cannot yet decide, or agree on a deadline with you within 45 days. If it sends that notice, it has 30 more days. If it misses the deadline, it cannot collect permit fees for that application and must refund any it collected.

Is it illegal for a window company to raise prices after a hurricane?

Not automatically. Florida's 501.160 and Texas DTPA 17.46(b)(27) ban unconscionable or exorbitant prices for necessities, including building materials, after an emergency or disaster declaration. Price increases explained by real cost increases are allowed. Florida's law creates no private lawsuit right; report suspected gouging to the Attorney General. Texas Attorney General actions can bring civil penalties up to $10,000 per violation.

Should I sign a contract right after a storm?

Be careful. Check the license in Florida, where unlicensed contracting during a declared emergency is a felony. In Texas, out-of-area disaster contractors may not demand payment before work begins under Chapter 58. Get three written bids, as TDI advises, and remember you have three business days to cancel a home solicitation sale in both states. Do not let urgency push you into an unpermitted job.

Can I protect only some openings now and the rest later?

Yes. In Texas, TDI says you can install windborne-debris products a few openings at a time for a TWIA retrofit credit, with an inspection each time. In Florida, the wind mitigation form rates the weakest opening, so partial protection usually will not earn the full opening protection credit until every glazed opening is protected. Plan the order so the most exposed openings and the garage door come first.

Do I need a new wind mitigation inspection after installing impact windows?

Usually, to get the discount. Citizens says forms are generally valid for up to five years unless improvements call for a new one, and a new inspection may be required before discounts for new features apply. Give the inspector your product approval or NOA letters, the permit and the final inspection, and make any stored panels available.

Will hurricane season delay my permit?

It can. A storm near your area can close offices and shift staff to emergency repair permits. Florida's statutory permit deadlines include an exception for force majeure or extraordinary circumstances, so a storm can pause the fee-reduction remedy. Apply early in the year so a season storm does not catch your project mid-permit.

Can I buy a TWIA policy right before a hurricane?

No. TDI says a TWIA policy cannot be bought when a hurricane is in the Gulf. If you need TWIA coverage, apply well before storm season, and remember that new work generally must have a Certificate of Compliance before it is insurable through TWIA.

Does My Safe Florida Home have a deadline once I'm approved?

Yes. Under Fla. Stat. 215.5586, grant recipients must finish construction and request the final inspection within 18 months of grant approval or the application is deemed abandoned and the money reverts. Build in time for permits, factory lead time and any condo or historic approvals. The program portal has been offline since November 10, 2026 for a platform change.

Sources

This guide was written by our editorial team from the public sources listed above. It is general information, not legal advice; confirm licensing and terms directly with any provider.

New ebook from The Company ChronicleHow to Research Like a Wall Street AnalystFind original sources, analyze trends, and build your own insights. 36 pages with worksheets.Get the ebook · $29Instant PDF download

Business Spotlight

Want us to publish your business?

Our team writes and publishes articles about your business on The Company Chronicle every month, with a link to your website. Plans from $30 a month, cancel anytime.

Publish with us

The Chronicle directory

What are you into?

The Chronicle, coast to coast

Every corner has a story.

The full Chronicle illustration